Last Energy PWR-5
Last Energy's PWR-5 pilot design at Texas A&M-RELLIS. The company's 28 May 2026 statement describes the pilot as scaled for 5 MW electrical; gross versus net is not stated. DOE's 30 September environmental determination states a 19.5 MWth PWR-5 design point for later program phases. The initial Phase 1 open-pool research configuration is limited to 100 kWth, fewer than 1,000 cumulative operating hours, and no grid export. Neither design rating is achieved or authorized Phase 1 output; subsequent phases need separate DOE authorization.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
- Projects
- Construction: Last Energy PWR-5 pilot at Texas A&M-RELLIS.
- Evidence
- 3 sources; first primary source: America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS. Record reviewed 8 Oct 2026.
Key facts · Tracked projects · Agreements · Sources · Evidence · Regulatory actions · Its projects in the table · Compare with other designs
Key facts
- Class
- Microreactor
- Technology
- Pressurized water reactor (PWR)
- Coolant
- Light water
- Spectrum
- Thermal
- Developer / vendor(s)
- Last Energy
- Module electrical
- 5 MWe (gross/net unspecified)
- Module thermal
- 19.5 MWth (nameplate; basis unspecified)
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 8 Oct 2026 (record review date, not proof of current availability or a deployment)
Tracked deployment projects
- Last Energy PWR-5 pilot at Texas A&M-RELLIS — Construction · United States
Agreements naming this design (1)
Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.
- DOE Reactor Pilot Program (DOE-authorized advanced test reactors) — Government program · Active · announced 18 Jun 2025
Concerns United States
Design sources
(3)
- America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS (government, accessed 1 Oct 2026)
- Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026) (company, accessed 4 Oct 2026)
- DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008 (government, accessed 8 Oct 2026)
Evidence and open questions
(2 notes)
- Evidence review. Last Energy's 28 May 2026 statement says the Department of Energy approved the preliminary documented safety analysis for its PWR-5 pilot at Texas A&M-RELLIS, that construction was nearing completion, and that the PWR-5 uses the same reactor geometry as the commercial PWR-20 with enrichment scaled for 5 MW of electrical output. A later Texas A&M page repeats that DOE approval for the PWR-5 pilot at the campus. The DOE categorical-exclusion file returned an access refusal (HTTP 403), so it was not read. Stored 5 MWe matches the company statement. The stored 19.5 MWth figure is not in the readable pages. Last checked 19 Oct 2026. Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS; DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008
What would change this
A readable DOE safety or environmental document that states the PWR-5 thermal power and whether 5 MW electrical is gross or net. Next scheduled check: 19 Jan 2027.
- Technology family: Source unavailable. The DOE determination returned an access-denied page and was not read, and the readable pages do not describe the PWR-5's primary-circuit layout, so no integral layout is recorded. Last checked 1 Nov 2026. DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026)
What would change this
A readable DOE or Last Energy description of the PWR-5's primary-circuit layout. Next scheduled check: 1 Feb 2027.
Regulatory actions
Compare reviews and approvals across designs
Environmental decision
- DOE PWR-5 Phase 1 environmental categorical exclusion — Last Energy PWR-5 pilot at Texas A&M-RELLIS
Environmental decision · Issued / approved · U.S. Department of Energy, Office of Nuclear Energy · decided 30 Sep 2026
DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.
Sources: DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008