Projects / United States · Construction
Last Energy PWR-5 pilot at Texas A&M-RELLIS
Last Energy's PWR-5 pilot at Texas A&M-RELLIS, selected for DOE's Reactor Pilot Program, is at construction stage, with its first phase limited to 100 kWth of low-power testing.
Current status
- How current
- General record check . Bounded evidence review . 2 of 8 listed sources have a publication or document date recorded here; the newest is 16 Dec 2025. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: DOE PWR-5 Phase 1 environmental categorical exclusion (30 Sep 2026). All permissions and applications
- Latest development
- Announced 7 Oct 2026 · Announcement: Last Energy says DOE approved its PWR-5 final safety analysis. Last Energy said DOE approved its final Documented Safety Analysis for the PWR-5 pilot at Texas A&M-RELLIS. Source: Last Energy announces PWR-5 documented safety analysis approval. Updates entry
More on this development
The company says DOE readiness review and startup authorization are still ahead. The announcement does not establish operating authority or criticality.
- Next dated milestone
- First criticality: 2026 (target). Last Energy targets a PWR-5 criticality demonstration in 2026. This is not an achieved milestone. Source: Last Energy: Last Energy Announces Oversubscribed $100 Million Series C (published 16 Dec 2025); Last Energy announces PWR-5 documented safety analysis approval.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Operation or grid target (type stated) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Texas A&M reported facility construction under way in May 2026, so the project is shown at construction stage; completion of reactor installation, fuel loading and criticality are not established. Last Energy's 28 May statement says DOE approved a preliminary documented safety analysis, but the DOE letter was not opened. DOE's signed 30 September 2026 categorical exclusion DOE-ID-26-008 covers Phase 1 initial criticality and low-power testing as a proposed environmental action. Phase 1 is an open-pool, near-atmospheric-pressure research configuration limited to 100 kWth and fewer than 1,000 cumulative operating hours, with no grid electricity export. The 19.5 MWth design point and 5 MWe electrical description refer to later phases, not achieved or authorized Phase 1 output; each phase needs separate DOE authorization and an updated safety basis. Last Energy announced on 7 October that DOE approved the final documented safety analysis. The DOE approval letter and decision date were not opened, so this is a dated company claim. DOE readiness review and startup authorization still lie ahead. The environmental decision and safety-analysis claims are not operating authority or an NRC license. Last Energy says it holds a lease at Texas A&M-RELLIS and procured a full core load of low-enriched uranium fuel. It said in December 2025 that it expected a criticality demonstration in 2026. DOE startup authorization for criticality follows the readiness review that began after the October 2026 safety-analysis approval.
Key facts
- Design
- Last Energy PWR-5 (Microreactor)
- Technology
- Pressurized water reactor (PWR) · light water
- Operator(s)
- Last Energy
- Vendor for linked design
- Last Energy
- Location
- Texas A&M-RELLIS Energy Proving Ground · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Shared campus pin for distinct company proposals. Coordinate is the NuclearChain CC BY 4.0 sites export pin for the Aalo Texas A&M discovery row (position_approximate=1), which sits on the RELLIS campus. It is not a reactor-building survey and is not a headquarters pin. - Coordinates
- 30.6420749, -96.4682751 · site-area point (approximate)
- Electrical capacity
- 5 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Purpose
- Research or test reactor
- Construction start
- 2026Last Energy states it began PWR-5 construction at RELLIS
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Last Energy PWR-5 pilot at Texas A&M-RELLIS is recorded at Texas A&M-RELLIS Energy Proving Ground, Texas, United States. Operator: Last Energy. Recorded vendor: Last Energy. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Aalo commercial proposal at Texas A&M-RELLIS, Kairos commercial proposal at Texas A&M-RELLIS, Natura MSR-100 proposal at Texas A&M-RELLIS, Terrestrial Energy IMSR at Texas A&M-RELLIS.
Coordinate source: NuclearChain data exports, NuclearChain sites.csv row 'aalo-atomics-texas-a-and-m-nuclear-power-plant' (30.6420749, -96.4682751)
Recorded electrical output is 5 MWe (gross/net unspecified), scope module. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 19.5 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorLast Energy
- Reactor supplier
- Vendor for the linked designLast Energy
- Fuel
- Project fuel information is described in the source-backed statement below.
Source-backed project statement Last Energy said on 15 October 2025 that it had procured a full-core load of fuel, and on 28 May 2026 that the fuel had been manufactured while authorization to receive fuel on site was still ahead. On 7 October 2026 it said the pilot uses low-enriched uranium tied to a commercial supply chain, without naming the supplier. Manufacture is not site delivery or loading. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); Last Energy announces PWR-5 documented safety analysis approval
- Site host or owner
- Site hostThe Texas A&M University System · source
- Programs and agreements naming the project
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
Last Energy said on 15 October 2025 that the RELLIS pilot would demonstrate low-power criticality and the ability to generate electricity for commercial output, and on 28 May 2026 that its separate commercial plant is designed for industrial customers and data centers. Neither statement names a buyer of this pilot’s electricity or heat. Texas A&M is described as the lessor of the site, not as the offtaker. No power purchase agreement for this pilot is stated. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026)
- Contractor
Last Energy’s 15 October 2025 and 28 May 2026 releases say the company secured the site, advanced construction, and procured equipment. They name no engineering, FEED, or construction contractor and no contract value. Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026)
- Funding and government decisions
Last Energy said on 15 October 2025 that it had signed an Other Transaction Agreement with the Department of Energy. The releases reviewed state no amount, no payment, and no financing terms for the RELLIS pilot. Selection into the pilot program is not money paid. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus
- Comparable schedule revision
Comparable schedule revision not established. The releases reviewed give a preliminary safety analysis approval announced on 28 May 2026 and a documented safety analysis approval announced on 7 October 2026. Those are successive documents, not two forecasts of one milestone. No operation date is revised in these texts. Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); Last Energy announces PWR-5 documented safety analysis approval
Not recorded in SMRMap's reviewed evidence (1): Project proposer or applicant
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Timeline
Recorded developments
- Announced · Announcement
Last Energy says DOE approved its PWR-5 final safety analysis - · Environmental decision recorded
DOE approves environmental determination for PWR-5 Phase 1 testing at RELLIS - Announced · Announcement
Last Energy states DOE approved a PWR-5 preliminary safety analysis - · Construction start
Last Energy states it began PWR-5 construction at RELLIS - Announced · Announcement
Last Energy and the Texas A&M System announce the PWR-5 pilot at RELLIS
Earlier developments (1)
- · Recorded development
Last Energy selected for DOE's Reactor Pilot Program
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · First criticality
Last Energy targets a 2026 criticality demonstration for its RELLIS pilot
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- DOE PWR-5 Phase 1 environmental categorical exclusion
Environmental decision · Issued / approved · U.S. Department of Energy, Office of Nuclear Energy · decided 30 Sep 2026
DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.
Sources: DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. On 15 October 2025 Last Energy and the Texas A&M University System announced a PWR-5 microreactor pilot at the Texas A&M-RELLIS campus near Bryan-College Station. The PWR-5 is described as physically identical to the PWR-20 but scaled to 5 MW of electrical output. It is to demonstrate low-power criticality and then electricity generation. Last Energy said it held a lease at RELLIS, had procured a full core load of fuel, had signed an Other Transaction Agreement with DOE and had begun licensing submissions. The project is authorized through DOE, not the NRC. On 28 May 2026 Last Energy announced DOE approval of its preliminary documented safety analysis. It said it began construction in 2026, delivered key reactor components to the site and advanced construction of the reactor building. The Texas A&M System's statement of 29 May 2026 says construction is under way and the facility was expected to be finished that week. These describe building and component work. No opened source reports reactor installation, fuel receipt, fuel loading or a dated nuclear-construction milestone. On 7 October 2026 Last Energy announced DOE approval of its final documented safety analysis. It said DOE's readiness review is the last step before DOE can issue startup authorization for criticality and operation. Both approvals are company announcements; no DOE letter or decision date was opened. DOE's 30 September 2026 environmental determination DOE-ID-26-008 could not be opened when checked (access refused). Its stored Phase 1 limits (100 kWth, fewer than 1,000 hours, no grid export) were not re-read. Last Energy said in December 2025 that it expected a criticality demonstration in 2026, a target. No opened source gives a date for electricity generation. The stored 5 MWe is the scaled design output, and the sources give no gross or net basis. It is not an authorized or achieved Phase 1 output. Last checked 19 Oct 2026. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); Texas A&M System: PWR-5 construction under way at RELLIS; Last Energy announces PWR-5 documented safety analysis approval; Last Energy: Last Energy Announces Oversubscribed $100 Million Series C; DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008
What would change this
DOE's startup authorization for PWR-5 Phase 1, or a Last Energy or DOE notice that fuel has been received or criticality achieved at RELLIS. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. The stored permission is DOE environmental determination DOE-ID-26-008, signed 30 September 2026 for Phase 1. It could not be opened when checked (access refused) and was not re-read. Last Energy announced DOE approval of its preliminary safety analysis on 28 May 2026 and of its final safety analysis on 7 October 2026. It said DOE's readiness review comes before startup authorization for criticality and operation. No DOE approval letter, decision date or startup authorization has been opened. No construction or operating permission from DOE is published. Last checked 19 Oct 2026. Last Energy announces PWR-5 documented safety analysis approval; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008
What would change this
DOE issues or publishes the PWR-5 startup authorization, or confirms the safety-analysis approvals. Next scheduled check: 19 Jan 2027.
- Operation or grid target (type stated): Not disclosed in the reviewed evidence. Last Energy says the pilot will demonstrate low-power criticality and then move to electricity generation. In December 2025 it expected the criticality demonstration in 2026. No opened source gives a dated target for electricity generation, grid connection or commercial operation. DOE's Phase 1 environmental determination, which the stored record says excludes grid export, could not be opened when checked (access refused). Last checked 19 Oct 2026. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: Last Energy Announces Oversubscribed $100 Million Series C; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026)
What would change this
Last Energy or DOE gives a date for PWR-5 electricity generation or a later-phase authorization. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Last Energy said on 7 October 2026 that, with the documented safety analysis approved, the project moves into the Department of Energy readiness review, which it calls the final step before startup authorization for criticality and operation. That is the next decision the release names. The authorization itself is not reported as issued. Last checked 23 Oct 2026. Last Energy announces PWR-5 documented safety analysis approval
What would change this
The Department readiness-review result or the startup authorization for the RELLIS pilot. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Last Energy said on 28 May 2026 that the Department of Energy had approved the preliminary documented safety analysis, and on 7 October 2026 that it had approved the documented safety analysis. Those are company reports of safety-basis approvals, not an operating authorization. The October release says a readiness review still precedes startup authorization. The Department’s own environmental determination is not among the sources reviewed. Last checked 23 Oct 2026. Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); Last Energy announces PWR-5 documented safety analysis approval
What would change this
The Department readiness-review result or startup authorization, or the text of the safety-analysis approvals. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Last Energy said on 15 October 2025, and again on 28 May 2026, that it had secured a land lease at Texas A&M-RELLIS. The releases do not state a grid interconnection or a water arrangement. The stated aim of later electricity generation is not an interconnection agreement. Last checked 23 Oct 2026. Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026)
What would change this
The lease instrument, or a grid or water agreement for the pilot. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Source unavailable. No readable source states a spent-fuel, waste or closure arrangement for the RELLIS pilot. Last Energy's releases of 15 October 2025, 28 May 2026 and 7 October 2026 and the Texas A&M System's 18 June 2026 article contain no spent-fuel or waste statement (checked by text search on 13 November 2026). DOE's signed 30 September 2026 determination DOE-ID-26-008, which covers Phase 1 under categorical exclusion B5.26, is the likely source. A direct fetch returned an access refusal (HTTP 403) on 19 October 2026; its Phase 1 limits were recorded when it was accessed on 8 October 2026, but no spent-fuel or waste statement was recorded and it was not re-read for this review. Reviewed 13 November 2026. Last checked 13 Nov 2026. Last Energy announces PWR-5 documented safety analysis approval; Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus; Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026); America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS; DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008
What would change this
A readable copy of DOE-ID-26-008, or a DOE, Texas A&M or Last Energy document stating the RELLIS pilot's spent-fuel, waste and closure arrangement. Next scheduled check: 12 Feb 2027.
Evidence dates
(2 of 8 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(8)
- America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS (government, accessed 1 Oct 2026)
- Last Energy: company statement on PWR-5 preliminary documented safety analysis (28 May 2026) (company, accessed 4 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008 (government, accessed 8 Oct 2026)
- Last Energy announces PWR-5 documented safety analysis approval (company, accessed 8 Oct 2026)
- Texas A&M System: PWR-5 construction under way at RELLIS (government, accessed 8 Oct 2026)
- Last Energy: Last Energy Partners With Texas A&M to Build Microreactor at RELLIS Campus (company, published 15 Oct 2025, accessed 18 Oct 2026)
- Last Energy: Last Energy Announces Oversubscribed $100 Million Series C (company, published 16 Dec 2025, accessed 18 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Last Energy PWR-5 pilot at Texas A&M-RELLIS — https://smrmap.com/projects/last-energy-pwr-5-rellis/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Last Energy PWR-5 pilot at Texas A&M-RELLIS”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/last-energy-pwr-5-rellis/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.