Policy and licensing / North Carolina
North Carolina: SMR policy and licensing
Selected federal, state, territory, and national measures whose official text was opened. This is not a complete list of laws, rules, programs or guidance for any jurisdiction. A jurisdiction without a page here is not a finding that it has no policy, and these pages do not rate or prefer any jurisdiction. Nothing here implies that a project is eligible for, or approved under, any measure.
89 projects in United States →
Federal measures apply in North Carolina as everywhere in the United States and are listed once on the federal page. They are not counted here.
Where licensing stands
Built only from the records on this page. It is not a complete account of the law and not legal advice.
- Authorities named in recorded applications, reviews and decisions
- NRC (1 record)
- Licensing law or framework in the record
- NRC licensing measures are recorded once, on the federal page (9 records).
- Latest recorded step
- Application submitted : Belews Creek early site permit application
- Open coverage gaps
- Commission or siting instruments (access blocked). What the review of 5 Oct 2026 read.
Laws, rules and executive directives
- North Carolina G.S. 166A-29: fixed nuclear facility emergency-planning fee · In effect
N.C. Gen. Stat. § 166A-29 · North Carolina General Assembly · affects: State program administration
North Carolina charges an annual emergency-planning fee, and a second radiation-protection fee, for each fixed nuclear facility that produces electricity and is in the state or has a plume emergency-planning zone partly in the state. The opened text sets minimums and leaves the payment schedule to the Department of Public Safety.
Not approved or pending: No Department of Public Safety fee schedule or assessment order was opened. No project is linked. The fee does not authorize construction. (Record checked .) - North Carolina G.S. 62-133.8: clean energy portfolio standard · In effect
N.C. Gen. Stat. § 62-133.8 · North Carolina General Assembly · affects: State program administration
North Carolina's current clean-energy portfolio statute counts nuclear energy facilities, including uprates, and fusion energy facilities as clean energy. It is not a small-modular category and it does not grant a construction certificate or a federal license.
Not approved or pending: Session Law 2025-25 was not opened. The current certificate section amended by Session Law 2023-138 was not opened, and the session-law display mixes struck and inserted certificate text, so that change is not restated as current law. No Utilities Commission order was opened. No project is linked. The portfolio standard does not approve a reactor. (Record checked .)
Bills, proposed rules and consultations
- None recorded.
Funding and support programs
- None recorded.
Regulatory guidance and inspector policies
- None recorded.
Recorded permissions and applications for tracked projects located in North Carolina
Listed by project location only, with each action's issuing authority recorded. The jurisdiction measures above do not themselves authorize reactor construction or operation.
Site applications and decisions
- Belews Creek early site permit application — Duke Belews Creek technology-neutral SMR proposal
Site permission sought · Under review · NRC · submitted 30 Dec 2025 · docket 52-055 · ADAMS ML25364A004, ML26016A624, ML26259A008, ML26274A437 · 91 FR 5787 · 91 FR 542 · 91 FR 22549 · 91 FR 50896
Duke Energy Carolinas applied on 30 December 2025 for an early site permit for the Belews Creek site in Stokes and Forsyth counties, North Carolina. The NRC accepted and docketed the application in February 2026 under Docket No. 52-055, and it is under review. If issued, an early site permit approves a site independent of a specific plant design. It is not a construction permit or a combined license, and no reactor design is selected. The NRC gave notice on 27 April 2026 that it will prepare an environmental impact statement, and its project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.
Sources: Federal Register 91 FR 5787 (9 Feb 2026): Belews Creek early site permit application, acceptance for docketing and opportunity to request a hearing; Federal Register 91 FR 542 (7 Jan 2026): Belews Creek early site permit application, notice of receipt; Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Federal Register 91 FR 50896 (6 Aug 2026): Belews Creek early site permit application, notice of uncontested hearing; NRC: Duke Energy's Belews Creek early site permit application; NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008); Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437)
What this review has read for North Carolina
As of 5 Oct 2026. Bounded review concluded with access gaps. A published record above is separate from research coverage: a class can be blocked or unreviewed even where records are published. Coverage for every state and territory.
- Statutes, session laws and bills: Evidence read. G.S. 62-133.8 (clean energy portfolio standard) and G.S. 166A-29 were read, with Session Laws 2023-138 and 2020-83. Session Law 2025-25 was also read and does not mention nuclear.
- Governor or energy instruments: None found in sources checked. The Energy Policy Council's 2024 biennial report was read. It recommends an authority and enacts nothing; it is a report, not an executive instrument.
- Commission or siting instruments: Access blocked. Two Utilities Commission files in the carbon-plan docket returned an access refusal (HTTP 403). A commission news release of 1 November 2024 was read; it is not the order.
- Funding measures and awards: None found in sources checked. Session Law 2025-2 (additional hurricane appropriations) was read. It does not mention nuclear.
Sources read (8):
- www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_62/GS_62-1… · checked 4 Oct 2026
- www.ncleg.gov/EnactedLegislation/SessionLaws/HTML/2023-2024/SL2023-138.html · checked 4 Oct 2026
- www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_166A/GS_16… · checked 4 Oct 2026
- www.ncleg.gov/EnactedLegislation/SessionLaws/HTML/2019-2020/SL2020-83.html · checked 4 Oct 2026
- www.deq.nc.gov/legislative-reports/energy-policy-council-biennial-report-11… · checked 4 Oct 2026
- www.ncuc.gov/documents/2024carbonplanpr.pdf · checked 4 Oct 2026
- www.ncleg.gov/EnactedLegislation/SessionLaws/HTML/2025-2026/SL2025-25.html · checked 4 Oct 2026
- www.ncleg.gov/EnactedLegislation/SessionLaws/HTML/2025-2026/SL2025-2.html · checked 4 Oct 2026
Sources that could not be read (2):
- starw1.ncuc.gov/NCUC/ViewFile.aspx?Id=ef6eb9bc-8bea-4abf-a3d3-b7faf0ff658a · checked 4 Oct 2026 · an access refusal (HTTP 403)
- starw1.ncuc.gov/NCUC/ViewFile.aspx?Id=5c560180-79f8-4d36-999a-575a4284c7e1 · checked 4 Oct 2026 · an access refusal (HTTP 403)