Projects / United States · Licensing

Duke Belews Creek technology-neutral SMR proposal

Duke Energy Carolinas submitted an early site permit application for the Belews Creek site in Stokes and Forsyth counties, North Carolina, on 30 December 2025.

Current status

Stage
Licensing
How current
General record check . Bounded evidence review . 4 of 10 listed sources have a publication or document date recorded here; the newest is 1 Oct 2026. A listed page was last updated 29 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Under review: Belews Creek early site permit application. An application under review is not a permit. All permissions and applications
Latest development
Letter dated 1 Oct 2026 · Regulatory step: Duke files Revision 2 of its Belews Creek early site permit application. Duke Energy Carolinas submitted Revision 2 of the Belews Creek early site permit application in response to regulatory-audit questions. Source: U.S. NRC: NRC draft safety evaluation sections completed for the Belews Creek ESP (published 7 Oct 2026); Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437) (dated 1 Oct 2026). Updates entry
More on this development

Duke states it is not requesting a limited work authorization. Revision 2 is an applicant filing, not an NRC permit, a design selection or a construction start.

Next dated milestone
Planned step: Dec 2026 (target). NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP. This is not an achieved milestone. Source: U.S. NRC: NRC draft safety evaluation sections completed for the Belews Creek ESP (published 7 Oct 2026); NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008) (dated 29 Sep 2026).
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Module/unit count (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

The NRC docketed it in February 2026 (Docket No. 52-055). It is under review. An early site permit approves a site independent of a plant design; it is not a construction permit. The application considers several SMR / advanced reactor alternatives. No design, vendor or construction decision is selected. A planning capacity is not a selected reactor capacity. The NRC's project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees for this application. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 review schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The permit decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Duke Energy
Vendor for linked design
No selected-design vendor recorded
Location
Site near Belews Creek Steam Station, Stokes County · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate coordinates for the named Belews Creek facility from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker); Duke Belews Creek SMR proposal at that named plant.
Coordinates
36.293, -80.0796 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded. The application seeks approval of the site for future construction of multiple nuclear reactors and considers six potential reactor technologies, four of them small modular designs.
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Duke Belews Creek technology-neutral SMR proposal is recorded at Site near Belews Creek Steam Station, Stokes County, North Carolina, United States. Operator: Duke Energy. Recorded vendor: No selected-design vendor is recorded. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'belews-creek-nuclear-power-plant-1' (36.2930081, -80.0796288)

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Customer or offtaker

Source-backed project statement Duke Energy's 30 December 2025 release says that, if further evaluation confirms SMRs at Belews Creek offer the best value for customers, Duke plans to add 600 MW of advanced nuclear to its system by 2037. The intended recipient is Duke Energy's own regulated system and customers. Duke has not decided to build, and no separate buyer or agreement is named. Duke Belews Creek early site application

Comparable schedule revision
A documented comparable revision is recorded. It is not a completed source review.

Source-backed project statement The NRC's 29 September 2026 letter moved its Belews Creek early-site-permit review milestones earlier than its February 2026 schedule, for example the final safety evaluation from May 2027 to February 2027 and the final environmental impact statement from May 2027 to March 2027. These are regulator review targets, not plant milestones. Duke's 2023 plan had two SMRs at Belews Creek by 2035, while its 2025 plan gives a potential 2037 date for SMRs there or a large reactor elsewhere; that later target covers a different scope, so it is not a like-for-like revision. NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008); Duke Energy brings large-scale new-build into resource plan - World Nuclear News

Not found in the sources we checked (3): Contractor; Funding and government decisions; Fuel
Contractor

Duke Energy's 30 December 2025 release says Duke submitted the Belews Creek early site permit application after two years of work and has not decided to build. Neither it nor the NRC's 29 September 2026 fee-cap and schedule letter names an engineering, site-study or construction contractor for the project. Duke Belews Creek early site application

Funding and government decisions

The NRC's 29 September 2026 letter sets a 2,178,000 dollar cap on NRC fees for reviewing the Belews Creek early site permit application. That is a regulatory fee cap, not project funding. Duke Energy's 30 December 2025 release states no funder, amount or financing for the project. NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008)

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

Duke Energy's 30 December 2025 release and the NRC's early site permit documents concern a technology-neutral site permit and name no reactor design, fuel supplier or fuel delivery for Belews Creek. Duke Belews Creek early site application

Not recorded in SMRMap's reviewed evidence (3): Reactor supplier; Site host or owner; Programs and agreements naming the project
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Earlier developments (2)

Targets

Planned, target and estimated dates are not achievements or commitments.

Schedule changes

The same milestone as stated at two dates. A revised target is still a target; the earlier target is kept for comparison and no longer counts as upcoming.

Permissions and applications

Site applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes, 1 not yet reviewed)
  • Evidence review. Duke Energy's release of 30 December 2025 says it submitted an early site permit application to the NRC that day for a site near the Belews Creek Steam Station in Stokes County, North Carolina; Duke Energy Carolinas, LLC is the applicant named in its letter of 1 October 2026. The early site permit is technology neutral: the application includes six potential reactor technologies, four of them small modular designs, Duke has not selected a reactor technology, and Duke says it has yet to decide to build new nuclear units. By letter of 8 February 2026 the NRC found the application acceptable for docketing; the NRC page (updated 7 October 2026) lists the draft safety evaluation as completed in July 2026 and the hearing as held on 17 September 2026, and lists the permit decision as TBD. An early site permit application is not a permit, and an early site permit would not authorize construction. Duke's Revision 2 letter of 1 October 2026 says Duke is not requesting a limited work authorization, and no opened source reports site preparation or nuclear construction. No reactor, unit count or plant output is selected; Duke's 600 MW by 2037 with a first SMR on line in 2036 is a conditional plan, not a rating. NRC targets, not completed: advanced safety evaluation and draft environmental impact statement December 2026, final safety evaluation February 2027, final environmental impact statement March 2027. The NRC's Federal Register notice of 27 April 2026 (read in the govinfo copy) places the site in Sauratown Township, Stokes County, and Belews Creek Township, Forsyth County, and says the NRC will prepare an environmental impact statement. The licensing stage, the two counties and the empty design, module and output fields stay stored; the docketing notice details rest on a Federal Register page that could not be opened when checked. No opened source names an intended reactor operator, so the stored operator Duke Energy rests on its role as applicant rather than on a stated operator role. Last checked 19 Oct 2026. Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Duke Belews Creek early site application; Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437); NRC: Duke Energy's Belews Creek early site permit application; Federal Register 91 FR 22549 (27 Apr 2026), govinfo copy: Belews Creek early site permit, notice of intent to conduct scoping and prepare an environmental impact statement
    What would change this

    The NRC's advanced safety evaluation or draft environmental impact statement for the Belews Creek early site permit (targeted December 2026), the permit decision, or a Duke technology selection or construction permit application. Next scheduled check: 7 Jan 2027.

  • Plant capacity (scope qualified): Not disclosed in the reviewed evidence. The NRC's Belews Creek environmental-review page reports an early site permit bounding site maximum of 6,250 MW thermal and 2,250 MWe gross. The application remains technology neutral; these envelope maxima do not establish a selected plant or reactor rating. Duke's conditional plan for 600 megawatts of advanced nuclear by 2037 is a separate planning figure, not a selected rating. Last checked 26 Oct 2026. Belews Creek Early Site Permit environmental review (EIS) page; Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Duke Belews Creek early site application
    What would change this

    Duke selects a reactor technology or files a construction permit or combined license application stating the selected plant rating. Next scheduled check: 19 Jan 2027.

  • Module/unit count: Not disclosed in the reviewed evidence. The application seeks approval of the site for future construction of multiple nuclear reactors and considers six potential reactor technologies, four of them small modular designs. Duke says it has yet to decide to build new nuclear units. No number of units is selected. Last checked 19 Oct 2026. Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Duke Belews Creek early site application
    What would change this

    Duke selects a technology and unit count, or files a construction permit or combined license application. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The NRC's Belews Creek page, updated 7 October 2026, targets the draft environmental impact statement and the advanced safety evaluation in December 2026, the final safety evaluation in February 2027 and the final environmental impact statement in March 2027, with the permit decision itself shown as to be determined. Duke's December 2025 release says that, if further evaluation confirms SMRs offer the best value, it plans its first SMR on line at Belews Creek in 2036. These are regulator and company targets, and no reactor has been selected. Last checked 23 Oct 2026. NRC: Duke Energy's Belews Creek early site permit application; Duke Belews Creek early site application
    What would change this

    Issue of the draft environmental impact statement, a schedule change letter, or the ESP decision. Next scheduled check: 23 Jan 2027.

  • Permissions and public process. Duke Energy Carolinas' early site permit application for Belews Creek is under NRC review (Docket 52-055); the NRC's April 2026 notice opened a 30-day public scoping period for the environmental impact statement, with the U.S. Army Corps of Engineers as a cooperating agency. The NRC project page lists the February 2026 acceptance notice with an opportunity for hearing and a mandatory-hearing public meeting on 17 September 2026, and shows the permit decision as to be determined. An early site permit would approve the site only, not construction or a reactor design. Last checked 23 Oct 2026. Federal Register 91 FR 22549 (27 Apr 2026), govinfo copy: Belews Creek early site permit, notice of intent to conduct scoping and prepare an environmental impact statement; NRC: Duke Energy's Belews Creek early site permit application
    What would change this

    Publication of the draft environmental impact statement and its comment period, or the NRC's early site permit decision. Next scheduled check: 23 Jan 2027.

  • Site dependencies (land, grid, water). The NRC's Belews Creek environmental review page says the site lies in Stokes and Forsyth counties, adjacent to Duke's existing Belews Creek Steam Station along Belews Creek and Belews Lake, and could hold up to three nuclear plant complexes with a bounding 2,250 MWe. It says the new reactors would replace the steam station, due to retire in the mid-2030s, and be integrated into the existing grid. The page gives no cooling-water withdrawal, transmission or land arrangement; Duke's environmental report, which would describe them, was not among the sources reviewed. Last checked 23 Oct 2026. Belews Creek Early Site Permit environmental review (EIS) page
    What would change this

    The draft environmental impact statement describing Belews Creek cooling-water and transmission arrangements. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(4 of 10 sources with a publication or document date)
Latest dated listed source publication: Federal Register 91 FR 22549 (27 Apr 2026), govinfo copy: Belews Creek early site permit, notice of intent to conduct scoping and prepare an environmental impact statement: 27 Apr 2026.Latest dated listed source document: Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437): 1 Oct 2026.Latest dated recorded event: Duke submits Revision 2 of the Belews Creek ESP application: 1 Oct 2026.6 of 10 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(10)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Duke Belews Creek technology-neutral SMR proposal — https://smrmap.com/projects/belews-creek/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Duke Belews Creek technology-neutral SMR proposal”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/belews-creek/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.