Projects / Argentina · Announced
ACR-300 SMR proposal at Atucha (Meitner Energy)
Argentina's December 2024 nuclear plan identified a new SMR at Atucha.
Current status
- How current
- General record check . Bounded evidence review . None of the 6 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- 23 Sep 2026 · Recorded development: Atucha shareholders reportedly authorize a tender for a privately financed reactor. Shareholders reportedly declared the reactor initiative of business interest and authorized the board to call a public tender for a privately financed reactor over 12 hectares of land reserved for the canceled Atucha III. Source: Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026). Updates entry
More on this development
Authorizing a tender is not an award.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- State or province is not recorded.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
On 2 July 2026 the government announced Meitner Energy's private proposal for one INVAP-designed ACR-300 (about 300 MWe) at the Atucha site; construction needs Economy Ministry approval and a regulator license first. Kept separate from the existing Atucha reactors and the suspended CAREM-25. The approximate rating comes from press reporting. Regional press reports that on 23 September 2026 Nucleoeléctrica's shareholders canceled the large Atucha III projects, declared the reactor initiative of business interest and authorized the board to call a public tender for a privately financed reactor of about USD 1,203 million under a surface right over 12 hectares of the reserved land; the tender is not awarded, Meitner Energy is not the awardee, and its chief executive resigned on 28 August 2026. No Nucleoeléctrica primary copy of the decision was found.
Key facts
- Design
- ACR-300 (SMR)
- Technology
- Pressurized water reactor (PWR) · light water. The attached report says the ACR-300 uses PWR technology but does not describe its primary-circuit layout, so no integral layout is recorded.
- Operator(s)
- Not recorded
- Vendor for linked design
- INVAP
- Location
- Atucha nuclear power plant site · Argentina · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates of the named Atucha site from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker); additional SMR proposal at Atucha. - Coordinates
- -33.9672, -59.2075 · site-area point (approximate)
- Electrical capacity
- 300 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by regulator classification
- Confidence
- medium
- Record reviewed
- 6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
ACR-300 SMR proposal at Atucha (Meitner Energy) is recorded at Atucha nuclear power plant site, state or province not recorded, Argentina. Operator: No operator is recorded. Recorded vendor: INVAP. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'atucha-nuclear-power-plant-3' (-33.9672, -59.2075)
Recorded electrical output is 300 MWe (gross/net unspecified), scope plant. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerMeitner Energy · source
- Reactor supplier
- Vendor for the linked designINVAP
- Funding and government decisions
Source-backed project statement The Herald reports a plan to invest US$1.2 billion. Dinámica reports an estimated US$1,203 million under a scheme it quotes as 100 percent private capital, without public funds or guarantees. EconoJournal reports the same US$1,200 million announcement and the later resignation of the chief executive. These are attributed estimates and an unawarded tender authorization, not disbursements. The primary Nucleoeléctrica document was not available in this review. Buenos Aires Herald: private project to build nuclear reactor; Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
- Customer or offtaker
The December 2024 government page says an SMR at the Atucha site would improve access to energy and reduce outages. That is a national description, not a named customer or quantity. The later private-project articles name no offtaker. Data-center and artificial-intelligence language on the plan page is not a named buyer for this reactor. Argentina government Atucha SMR plan
- Contractor
The checked press reports do not identify an awarded construction contract. Their reported option for Nucleoeléctrica Argentina to undertake operation and maintenance has not been confirmed against the primary shareholder act; no operator or contractor appointment is established here. Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha); Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026)
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
The December 2024 plan says a second stage would develop uranium reserves for domestic demand and fuel-element exports. That is a national-plan stage, not a supplier, quantity, or delivery for this reactor. The project articles name no fuel contract. Argentina government Atucha SMR plan
- Comparable schedule revision
Comparable schedule revision not established. Infobae on 2 July 2026 gives one conditional construction duration of five years after Economy Ministry approval and a nuclear-regulator license. The Buenos Aires Herald on 3 July 2026 recalls a March 2025 announcement of four ACR-300 reactors at Atucha, a different count from this one-reactor proposal. Neither article states two forecasts of the same milestone. Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha); Buenos Aires Herald: private project to build nuclear reactor
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Atucha shareholders reportedly authorize a tender for a privately financed reactor
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(4 notes, 1 not yet reviewed)
- Evidence review. The government page on the December 2024 nuclear plan says the project would start by building an SMR on the Atucha nuclear plant site, without naming a design or a private company. Infobae, reporting the 2 July 2026 announcement, says the proposal presented by Meitner Energy would be installed at Nucleoeléctrica Argentina's Atucha site and includes an ACR-300 of about 300 MWe. The Buenos Aires Herald says the plan is a US$1.2 billion private investment in an ACR-300 designed in Argentina. Dinámica reports a later shareholder decision authorizing a public tender for a privately financed reactor at an estimated US$1,203 million, with no public funds or guarantees; the article does not name Meitner as the awardee. EconoJournal reports that Teófilo Lacroze resigned as Meitner's chief executive. The stored ACR-300 design, about 300 MWe, one unit and announced stage stay. Meitner is the named proposer of the July announcement, not a named licensed operator, and the tender is not an award. Last checked 19 Oct 2026. Argentina government Atucha SMR plan; Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha); Buenos Aires Herald: private project to build nuclear reactor; Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026); EconoJournal: Meitner chief executive resigns (August 2026)
What would change this
The tender award, or an ARN license application naming the owner and the design, would change this record. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next recorded step is Nucleoeléctrica's public tender for a privately financed reactor on reserved Atucha land, which its board was authorized to prepare in September 2026. Economy Ministry approval and regulator licensing would follow. The tender is not awarded, and the reports do not make Meitner Energy the selected bidder. Last checked 23 Oct 2026. Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026); Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha)
What would change this
Publication or award of the Nucleoeléctrica tender, or a ministry or regulator decision on the Atucha reactor. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Infobae reported in July 2026 that construction of the proposed ACR-300 would follow approval by the Economy Ministry and licensing by Argentina's Nuclear Regulatory Authority. Neither step is recorded. Nucleoeléctrica's September 2026 shareholder resolution, as reported by trade press, authorizes preparing a public tender; a tender is a procurement step, not a permission. Last checked 23 Oct 2026. Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha); Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026)
What would change this
An Economy Ministry approval, a regulator license application, or the published tender for the Atucha reactor. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The September 2026 shareholder resolution, as reported, requires granting a real surface right over 12 hectares of the land reserved for the canceled Atucha III plant, and raises the possibility that Nucleoeléctrica would operate and maintain the unit. The surface right is a stated requirement, not a granted right, and no grid or cooling arrangement is described. Last checked 23 Oct 2026. Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026)
What would change this
A granted surface right or tender document describing the Atucha site arrangements. Next scheduled check: 21 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 6 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(6)
- Argentina government Atucha SMR plan (government, accessed 1 Oct 2026)
- Global Energy Monitor Global Nuclear Power Tracker (directory or tracker, accessed 2 Oct 2026)
- Infobae: government announces private project for a new nuclear plant (Meitner Energy, Atucha) (news report, accessed 2 Oct 2026)
- Buenos Aires Herald: private project to build nuclear reactor (news report, accessed 2 Oct 2026)
- Dinámica: Atucha III cancelled; tender for a private reactor authorised (September 2026) (news report, accessed 6 Oct 2026)
- EconoJournal: Meitner chief executive resigns (August 2026) (news report, accessed 6 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: ACR-300 SMR proposal at Atucha (Meitner Energy) — https://smrmap.com/projects/atucha-new-smr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “ACR-300 SMR proposal at Atucha (Meitner Energy)”. Record reviewed 6 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/atucha-new-smr/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.