Projects / South Korea · Deferred
Daegu i-SMR proposal at the Gunwi industrial complex
A Daegu and KHNP plan for a plant at the Gunwi advanced industrial complex, under a 17 June 2024 feasibility-study memorandum reported by World Nuclear News, is recorded as deferred.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- 3 Feb 2026 · Recorded development: Daegu Gunwi: first-unit bid lapses after KHNP's coastal-site requirement. Daegu said its plan to host the first SMR unit fell through because KHNP's site call required coastal sites; it will pursue a later unit. Source: Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026). Updates entry
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- No map pin is shown for this record.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Its report of 3 July 2024 said this was in a bid to commercialise a 680 MWe plant equivalent to four 170 MW modules at the complex. The article does not say gross or net. It says a new special-purpose corporation would buy the land and finance construction. KHNP is a memorandum signatory, not a recorded licensed operator. Daegu pursued the first unit there and, after its plan fell through on 3 February 2026 because KHNP's site call required coastal sites, said it will pursue a later unit at the site. No termination of the memorandum is reported, so the record is deferred, not canceled; it is not an official project status.
Key facts
- Design
- i-SMR (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Reactor vessel of this design
- 30.4 m tall, 5.5 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 43.Dimensions refer to the reactor-vessel row. A separate containment vessel is described without dimensions. This is not the June 2025 29.7 / 5.5 point.SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- i-SMR Development Agency, KHNP and KAERI
- Location
- Gunwi advanced industrial complex (Daegu) · South Korea · precision: site area (named plant, laboratory, base, port, campus or parcel)
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Named site, no map pin
- Electrical capacity
- 680 MWe (gross/net unspecified) · scope: plant
World Nuclear News states a 680 MWe plant and calls it equivalent to four 170 MW modules. - Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- low
- Record reviewed
- 19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Daegu i-SMR proposal at the Gunwi industrial complex is recorded at Gunwi advanced industrial complex (Daegu), Daegu, South Korea. Operator: No operator is recorded. Recorded vendor: i-SMR Development Agency, KHNP and KAERI. Stage: Deferred. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.
Recorded electrical output is 680 MWe (gross/net unspecified), scope plant. World Nuclear News states a 680 MWe plant and calls it equivalent to four 170 MW modules. Modules planned: 4. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designi-SMR Development Agency, KHNP and KAERI
- Funding and government decisions
Source-backed project statement World Nuclear News reported on 3 July 2024 that a newly created special-purpose corporation would buy about 160,000 square metres at the Gunwi complex and that the total project cost of KRW 4 trillion (USD 2.9 billion) would be entirely financed by that corporation. This is a planned financing structure, not funds raised. The article does not say the corporation had been formed, and Daegu's first-unit plan fell through in February 2026. WNN: Korean city to study feasibility of i-SMR deployment
- Fuel
- Fuel form stated for i-SMR (catalog profile as of 14 Feb 2025)UO2 pellet / 17 X 17 square
World Nuclear News' 3 July 2024 report describes the i-SMR as a 170 MWe integrated pressurised water reactor. Neither it nor Yonhap's 3 February 2026 report names a fuel supplier, quantity or delivery for the Gunwi plant. WNN: Korean city to study feasibility of i-SMR deployment
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
Yonhap's 3 February 2026 report says Daegu's plan aimed to reduce energy costs for companies locating in the Gunwi advanced industrial complex, and World Nuclear News' 3 July 2024 report places the plant there. Neither names a company or other buyer that agreed to take the plant's power or heat. Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
- Contractor
World Nuclear News reported on 3 July 2024 that Daegu and KHNP signed a memorandum including a feasibility study for the Gunwi plant, to be done with KHNP and private construction companies that the article does not name. KHNP is the i-SMR developer, so this is not a separate contractor appointment, and the construction companies are unnamed. Yonhap reported on 3 February 2026 that the city's first-unit plan fell through because the site call required a coastal site. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News reported on 3 July 2024 that Daegu targeted standard design approval in 2028 and commercial development in 2033, and Yonhap on 3 February 2026 restated the 2033 aim while reporting that the first-unit plan had fallen through, with no date for a further site call. Neither source gives a replacement date, so this is a stalled plan, not a dated revision. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Daegu Gunwi: first-unit bid lapses after KHNP's coastal-site requirement
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes, 1 not yet reviewed)
- Evidence review. World Nuclear News reported on 3 July 2024 that Daegu and Korea Hydro and Nuclear Power signed a memorandum on 17 June 2024 for a feasibility study, in a bid to commercialise a 680 MWe plant equivalent to four 170 MW modules at the Gunwi advanced industrial complex. The article does not say gross or net. It says a new corporation would buy the land and finance construction, and it gives 2028 and 2033 as city targets. Yonhap reported on 3 February 2026 that the city's plan to host the first small modular unit at Gunwi fell through because the competition required a coastal site and Gunwi is inland. KHNP announced on 17 June 2026 that the selected small-modular candidate site is Gijang, and that the large-reactor candidates are Yeongdeok. The city said it would keep talking about a later unit. The 680 MWe and four-module figures are already stored and are not changed. Gijang is not this site. Last checked 20 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026); KHNP: candidate sites for new nuclear plants selected
What would change this
A later competition notice that either names Gunwi or drops the city's later-unit discussion. Next scheduled check: 20 Jan 2027.
- Plant capacity (scope qualified). World Nuclear News states a 680 MWe plant and calls it equivalent to four 170 MW modules. The article does not say gross or net, so the stored basis stays nameplate_unspecified. Last checked 19 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment
What would change this
A Daegu, KHNP or Korean government document states gross or net output for Gunwi. Next scheduled check: 19 Jan 2027.
- Module/unit count. The same article states four modules. That count is the press description of the proposed plant, not a licensed configuration. Last checked 19 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment
What would change this
A Daegu, KHNP or Korean government document states a different module count for Gunwi. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The 2024 article names the Gunwi advanced industrial complex as the place the city wanted to study. The 2026 articles say that inland site could not enter the coastal competition, and KHNP selected Gijang instead. No coordinates are added; the complex is recorded as a named site without a pin. Last checked 20 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
What would change this
A siting decision that accepts a Gunwi plot or names a different host. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. Yonhap reported on 3 February 2026 that Daegu's plan to host the first SMR at Gunwi fell through because the inland site could not meet the site call's conditions, and that the city will consult Gunwi and other bodies to pursue a second SMR unit, with no date set for a further call. The next decision depends on a future KHNP site call. Last checked 23 Oct 2026. Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
What would change this
Announcement of a further KHNP SMR site call, or Daegu's application for a second unit. Next scheduled check: 23 Apr 2027.
- Permissions and public process. World Nuclear News reported in July 2024 that Daegu and KHNP signed a memorandum on 17 June 2024 for a feasibility study covering site suitability, economics and resident acceptance at the Gunwi industrial complex. Yonhap reported in February 2026 that Daegu's bid for the first SMR lapsed because the site call's conditions made the inland Gunwi site hard to submit. A memorandum is not a permit, and no licensing or consultation step is shown. Last checked 23 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
What would change this
A new KHNP site call that Gunwi can enter, or a Daegu application for a later SMR unit. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). World Nuclear News reported in July 2024 that a new special-purpose company would buy about 160,000 square metres in the Gunwi Advanced Industrial Complex for the plant, and Yonhap says Daegu chose the Sobo-myeon area of that complex as its candidate site in 2023. The land purchase is a stated plan, not a completed acquisition, and grid and cooling arrangements are not described. Last checked 23 Oct 2026. WNN: Korean city to study feasibility of i-SMR deployment; Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026)
What would change this
A land purchase or site designation for an SMR at the Gunwi complex. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- WNN: Korean city to study feasibility of i-SMR deployment (news report, accessed 2 Oct 2026)
- KHNP: candidate sites for new nuclear plants selected (company, accessed 2 Oct 2026)
- Yonhap (via Daum): Daegu's first-unit SMR bid falls through; later unit sought (3 February 2026) (news report, accessed 6 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Daegu i-SMR proposal at the Gunwi industrial complex — https://smrmap.com/projects/daegu-gunwi-ismr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Daegu i-SMR proposal at the Gunwi industrial complex”. Record reviewed 19 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/daegu-gunwi-ismr/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.