Projects / China · Licensing
Daqing NHR-200 nuclear heating plant (1990s)
The 200 MWt NHR-200 demonstration heating plant for Daqing, China, is a historical heat-only proposal decided in 1991.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- 1993 · Recorded development: Daqing siting report, EIA and feasibility study approved. Source: IAEA-TECDOC-965: Design approaches for heating reactors. Updates entry
- Next dated milestone
- No upcoming target date is recorded. Most recent target: Construction start: 1997 (target). Daqing NHR-200 construction start (historical target, not met). Date passed; not recorded as met. Source: IAEA-TECDOC-965: Design approaches for heating reactors.
- Selected limitations
- No map pin is shown for this record.
- Expected for this stage but not recorded as a structured fact: Design identified; Permission evidence appropriate to stage. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Its siting report, environmental assessment and feasibility study were approved in 1993 and its preliminary safety and environmental license documents later passed review. The plant was not built; no formal cancellation record was found. INET's NHR200 page states that the 200 MW heating reactor obtained a construction license in December 1996 after preliminary design, without naming the site; the stage is unchanged without a source tying that license to Daqing.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- INET, Tsinghua University
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Daqing nuclear heating plant site · China · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Town named, no map pin
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- 200 MWth (nameplate; basis unspecified)
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Daqing NHR-200 nuclear heating plant (1990s) is recorded at Daqing nuclear heating plant site, Heilongjiang, China. Operator: INET, Tsinghua University. Recorded vendor: No selected-design vendor is recorded. Stage: Licensing. Location precision: town or locality only; town named, no map pin.
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 200 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorINET, Tsinghua University
- Customer or offtaker
Source-backed project statement IAEA-TECDOC-965 (September 1997) says the NHR-200 demonstration plant at Daqing would be the main heat source for that city's district heating grid, about 2.5 km from the city boundary, and that the grid supply temperature was raised to 130°C at the customer's request. The customer is not named, and no heat-supply contract is stated. IAEA-TECDOC-965: Design approaches for heating reactors
Not found in the sources we checked (4): Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Contractor
IAEA-TECDOC-965 says it had been decided to build an NHR-200 demonstration plant in Daqing, that the basic design was finished and that detailed design was under way. The account names no engineering or construction contractor for that plant. IAEA-TECDOC-965: Design approaches for heating reactors
- Funding and government decisions
IAEA-TECDOC-965 records the decision to build an NHR-200 demonstration plant at Daqing and the approval of its siting report, environmental assessment and feasibility study. That account states no funder, budget or amount for the plant. IAEA-TECDOC-965: Design approaches for heating reactors
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
IAEA-TECDOC-965 says the integrated NHR-200 design for Daqing includes in-vessel spent-fuel storage. That is a design feature. The account names no fuel supplier, fabrication contract or delivery for the plant. IAEA-TECDOC-965: Design approaches for heating reactors
- Comparable schedule revision
Comparable schedule revision not established. IAEA-TECDOC-965 (September 1997) says in its summary that the first NHR-200 was expected to operate in 2000, and in an INET paper in the same volume that it was expected in 1999. Those are inconsistent expectations in one volume, not an earlier forecast later revised. IAEA-TECDOC-965: Design approaches for heating reactors
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Daqing siting report, EIA and feasibility study approved - · Recorded development
Decision to build an NHR-200 demonstration heating plant at Daqing
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Construction start · Date passed; not recorded as met
Daqing NHR-200 construction start (historical target, not met)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(9 notes)
- Evidence review. IAEA-TECDOC-965 (September 1997) says it was decided in 1991 to build an NHR-200 demonstration heating plant at Daqing city in northeastern China, with a thermal power of 200 MW, to serve as the main heat source for one residential quarter about 2.5 km from the plant; the NHR-200 is the 200 MW(th) heating reactor developed by INET, Tsinghua University. The same document says the siting report, environmental impact assessment report and feasibility study were approved by the respective authorities in 1993, that construction was scheduled to start in 1997, and gives the expected start of operation as 2000 in its summary and as 1999 in INET's paper; these are historical targets. The China Atomic Energy Authority's article of 21 May 2015 says the license-application documents for the Daqing 200 MW nuclear heating reactor, including the preliminary safety analysis report and environmental impact assessment, later passed review by the relevant state departments, and that the 200 MW commercial demonstration reactor had not been built. Passing review of application documents is not shown to be a construction permit for Daqing: INET's page (updated April 2026) says the 200 MW heating reactor obtained a construction license from the National Nuclear Safety Administration in December 1996 but names no site. No opened source reports site preparation or nuclear construction at Daqing, any later decision, or a cancellation. Output is heat only, 200 MW thermal, with no electrical rating. No opened source names an owner or operator for the Daqing plant; INET designed the reactor, so the stored operator INET is not supported as the plant's operator. The licensing stage, the 200 MWt heat-only rating and one unit stay stored; whether the stage should reflect an abandoned 1990s project is a coordinator decision, since no cancellation record was found. Last checked 19 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors; CAEA: low-temperature heating reactor development; INET, Tsinghua University: NHR200 low-temperature heating reactor page
What would change this
An NNSA, CAEA or INET document that ties the December 1996 construction license to Daqing, names the plant's owner or operator, or records the project's abandonment. Next scheduled check: 19 Jan 2027.
- Design identified. IAEA-TECDOC-965 (1997) names the Daqing demonstration plant as an NHR-200, the 200 MW(th) heating reactor developed by INET; INET's page calls its 200 MW low-temperature heating reactor NHR200-I, and the CAEA article of 21 May 2015 distinguishes NHR200-I (city heating) from NHR200-II (industrial steam). The catalog's NHR200-II record is a later variant developed in 2006 and should not be linked; no NHR-200/NHR200-I design record exists to link. Last checked 19 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors; INET, Tsinghua University: NHR200 low-temperature heating reactor page
What would change this
A catalog design record for NHR-200/NHR200-I is created; otherwise none. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The opened sources name only Daqing city. IAEA-TECDOC-965 says the plant was to heat one residential quarter about 2.5 km from the plant; no site name, district or coordinates are given. Last checked 19 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors
What would change this
An INET, CAEA or NNSA document naming the Daqing plant's site or district. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage. The CAEA article of 21 May 2015 says the license-application documents for the Daqing 200 MW nuclear heating reactor, including the preliminary safety analysis report and environmental impact assessment, passed review by the relevant state departments; IAEA-TECDOC-965 records approval of the siting report, environmental impact assessment and feasibility study in 1993. Neither gives a regulator instrument, and the review outcome is undated. INET's December 1996 construction license for the 200 MW heating reactor names no site and is not tied to Daqing. Last checked 19 Oct 2026. CAEA: low-temperature heating reactor development; IAEA-TECDOC-965: Design approaches for heating reactors; INET, Tsinghua University: NHR200 low-temperature heating reactor page
What would change this
An NNSA document or INET history tying the December 1996 construction license to the Daqing plant. Next scheduled check: 19 Jan 2027.
- Map coordinates: Not disclosed in the reviewed evidence. No opened source gives coordinates or a named site for the unbuilt Daqing plant; the Daqing heat-grid paper gives only the city, a 2.5 km distance and grid data. Last checked 19 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors
What would change this
A document naming the site location. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. In IAEA-TECDOC-965 the urgent task for the Daqing demonstration was to implement the project, with operation then expected in 1999 or 2000. The pages read name no later decision to build, amend or cancel that plant. Last checked 23 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors
What would change this
A later government or company decision that builds, amends or cancels the Daqing NHR-200. Next scheduled check: 21 Jan 2027.
- Permissions and public process. IAEA-TECDOC-965 says the siting report, environmental impact assessment and feasibility study for the Daqing NHR-200 were approved by the respective authorities in 1993. It does not name those authorities or quote a construction permit. INET's heating-reactor page says a construction license was issued in December 1996 for the 200 MW heating reactor and names no site, so this source does not tie that license to Daqing. Last checked 23 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors; INET, Tsinghua University: NHR200 low-temperature heating reactor page
What would change this
A regulator instrument that names the Daqing plant and states the permission granted. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). IAEA-TECDOC-965 describes the intended Daqing heating grid: the plant about 2.5 km from the city boundary, the NHR-200 as the main heat source, four loops, and fossil-fired peak boilers. It does not state a land right, a water withdrawal or an executed connection. This covers the described grid plan only. Last checked 23 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors
What would change this
A site, water or heat-network agreement for the Daqing plant. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The only Daqing statement in IAEA-TECDOC-965 about spent fuel is that the integrated NHR-200 design includes in-vessel storage. That is a design feature, not a storage site, transport plan or closure arrangement. Last checked 23 Oct 2026. IAEA-TECDOC-965: Design approaches for heating reactors
What would change this
A spent-fuel, waste or decommissioning plan for the Daqing plant. Next scheduled check: 21 Jan 2027.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- IAEA-TECDOC-965: Design approaches for heating reactors (IAEA/NEA, accessed 2 Oct 2026)
- CAEA: low-temperature heating reactor development (government, accessed 2 Oct 2026)
- INET, Tsinghua University: NHR200 low-temperature heating reactor page (company, accessed 6 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Daqing NHR-200 nuclear heating plant (1990s) — https://smrmap.com/projects/daqing-nhr-200/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Daqing NHR-200 nuclear heating plant (1990s)”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/daqing-nhr-200/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.