Licensing SMR projects

19 tracked projects and proposals in this directory. Named proposals, demonstrations and achieved deployments retain their recorded stages.

A formal project-specific application has been submitted or is under regulator review; design-only and pre-application advice do not qualify.

The recorded stage is separate from permission and does not guarantee current activity. Read each project’s dated evidence.

1 of these is an earlier-plan record: a proposal kept from an earlier plan, agreement, catalog or country profile. Their present status is not established, and their recorded stage is the last one evidenced, not proof of current activity.

Brazil: 1 · Canada: 1 · China: 1 · France: 2 · Romania: 1 · Russia: 1 · Rwanda: 1 · Sweden: 4 · United States: 7

Open these projects in Projects (on the map) · Coverage and stage definitions · Dated developments for all projects (Updates)

Counts describe the selected dataset, not a complete national or worldwide census. Sources and check dates are linked from each record.

Projects

Showing 19 of 19 projects

Project and categoryCountryDesignCapacityRecorded organizationsLocationRecord reviewed
Blue Energy BWRX-300 at Port of VictoriaSMRUnited StatesBWRX-3001500 MWe (gross/net unspecified) · plantPort of VictoriaTexas · named site, no map pin18 Oct 2026Latest source 8 Oct 2026Latest event 16 Sep 2026
Blykalla SEALER Norrsundet / Gävle proposalSMRSwedenSEALER330 MWe (gross/net unspecified) · plantNorrsundet, Gävletown-level point (approximate)18 Oct 2026Latest source 15 Oct 2026Latest event 9 Oct 2026
Blykalla SEALER Untra / Tierp proposalSMRSwedenSEALER440 MWe (gross/net unspecified) · plantUntra, Tierp municipalityUppsala County · town-level point (approximate)18 Oct 2026Latest source 31 Aug 2026Latest event 31 Aug 2026
Daqing NHR-200 nuclear heating plant (1990s)SMREarlier-plan recordChinaDesign profile not linked200 MWth (thermal only; nameplate; basis unspecified)Daqing nuclear heating plant siteHeilongjiang · town named, no map pin18 Oct 2026Latest source: none datedLatest event 1993
Dual Fluid critical demonstration experiment in RwandaSMRRwandaDF-CDE critical demonstration experiment—Nyamata nuclear research campus (planned)Eastern Province · town named, no map pin18 Oct 2026Latest source, document dated May 2026Latest event Feb 2025
Duke Belews Creek technology-neutral SMR proposalSMRUnited StatesDesign profile not linked—Site near Belews Creek Steam Station, Stokes CountyNorth Carolina · site-area point (approximate)18 Oct 2026Latest source, document dated 1 Oct 2026Latest event 1 Oct 2026
Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)SMRUnited StatesHoltec SMR-300680 MWe (gross/net unspecified) · plantHoltec states the two Pioneer units are designed to provide 680 MWe together, and the NRC's January 2026 release describes each SMR-300 unit as approximately 340 MWe.Palisades Nuclear Plant areaMichigan · site-area point (approximate)18 Oct 2026Latest source 10 Nov 2026Latest event 30 Sep 2026
Jimmy Cristanol Bazancourt heat microreactor proposalMicroreactorFranceJimmy Fermi heat microreactor20 MWth (thermal only; nameplate; basis unspecified)Cristanol industrial site, Bazancourtsite-area point (approximate)18 Oct 2026Latest source 11 Oct 2024Latest event 23 Jul 2026
Kärnfull Next SMR park at Målma, ValdemarsvikSMRSwedenBWRX-300—Målma, ValdemarsvikÖstergötland · town named, no map pin18 Oct 2026Latest source 3 Jun 2026Latest event 3 Sep 2026
Last Energy first commercial PWR-20 site, Caldwell CountyMicroreactorUnited StatesPWR-2020 MWe (net) · module · 80 MWth (nameplate; basis unspecified)Maxwell, Caldwell CountyTexas · region only, no map pin28 Oct 2026Latest source 5 Nov 2026Latest event Jul 2026
Long Mott Generating Station (Xe-100 at Dow Seadrift)SMRUnited StatesXe-100320 MWe (net) · plant · 800 MWth (nameplate; basis unspecified)The NRC application page lists a four-module plant at 800 MWth/320 MWe, intended to supply electricity and steam to Dow's adjacent Seadrift Operations, and says each module could produce 80 MWe of electricity or about 200 MWth of steam.Dow UCC Seadrift / Long MottTexas · site-area point (approximate)18 Oct 2026Latest source 12 Nov 2026Latest event 9 Nov 2026
NB Power ARC-100 at Point LepreauSMRCanadaARC-100100 MWe (gross/net unspecified) · modulePoint Lepreau Nuclear Generating Station siteNew Brunswick · site-area point (approximate)18 Oct 2026Latest source 7 May 2024Latest event 22 Dec 2022
NuScale VOYGR Doicești (Romania)SMRRomaniaNuScale VOYGR (US460 / NPM)462 MWe (gross) · plantDoicești NuScale siteDâmbovița · site-area point (approximate)18 Oct 2026Latest source, document dated 29 Oct 2026Latest event 29 Oct 2026
Stellaria Alvin experimental reactor (INB Alpha) at CadaracheSMRFranceAlvin experimental molten-salt reactorMWe not recorded · plant · 200 kWth (nameplate; basis unspecified)CEA CadaracheProvence-Alpes-Côte d'Azur · site-area point (approximate)18 Oct 2026Latest source 23 Apr 2026Latest event 16 Jun 2026
Studsvik new nuclear at the Nyköping home siteSMRSwedenBWRX-300—Studsvik site, NyköpingSödermanland · town-level point (approximate)18 Oct 2026Latest source 14 Oct 2026Latest event 3 Sep 2026
TVA Clinch River BWRX-300SMRUnited StatesBWRX-300300 MWe (net) · moduleThe IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure.Clinch River Nuclear SiteTennessee · site-area point (approximate)18 Oct 2026Latest source, document dated 28 Sep 2026Latest event 29 Sep 2026
UCRI critical unit for the Brazilian microreactor program at IENMicroreactorBrazilDesign profile not linked—IEN Argonauta building, UFRJ campus, Rio de JaneiroRio de Janeiro · site-area point (approximate)18 Oct 2026Latest source 21 Jan 2026Latest event 21 Jan 2026
University of Illinois KRONOS MMRMicroreactorUnited StatesKRONOS MMRMWe not recorded · module · 45 MWth (nameplate; basis unspecified)University of Illinois Urbana-Champaign campusIllinois · exact point18 Oct 2026Latest source 27 Oct 2026Latest event 27 Oct 2026
Yakutia land-based RITM-200N (Ust-Kuyga)SMRRussiaRITM-200N55 MWe (gross/net unspecified) · moduleUst-Kuyga (Yakutia land-based RITM-200N)Sakha (Yakutia) · site-area point (approximate)18 Oct 2026Latest source 3 Mar 2026Latest event 27 Feb 2026

Research coverage for the 19 matching projects: of 171 answers to nine review questions, 102 have a supported statement, 63 were reviewed with a stated limit and 6 are not reviewed yet. This counts recorded research, not readiness or the likelihood of construction.

Coverage by question

Each project is asked the same nine questions: five commercial questions and four reader questions. Only completed source reviews are counted. A supported statement can describe a conditional plan or preparatory work; read it on the project page. Not disclosed, not applicable, conflicting evidence and source unavailable are reviewed limits. Not reviewed is unfinished research, not a finding that nothing exists. The counts cover every page of matching projects, not only the page shown or the projects chosen for comparison.

QuestionSupported statementNot disclosedNot applicableConflicting evidenceSource unavailableNot reviewedProjects
Customer or offtaker810000119
Contractor135000119
Funding126000119
Project fuel commitment414000119
Comparable schedule revision513010019
Permissions and public process190000019
Site dependencies (land, grid, water)154000019
Spent fuel, waste and closure89000219
Next decision and prerequisites181000019
All nine questions102620106171