Projects / Rwanda · Licensing
Dual Fluid critical demonstration experiment in Rwanda
Experimental functional prototype of DF300, not a commercial power plant.
Current status
- How current
- General record check . Bounded evidence review . 2 of 6 listed sources have a publication or document date recorded here; the newest is May 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Feb 2025 · Recorded development: Initial Safety Assessment Report (ISAR) review begins. Source: RAEB: Critical Demonstration Experiment. Updates entry
- Next dated milestone
- Construction start: 2026 (target). CDE construction start (company target stated in February 2026, not reconfirmed by the May edition). This is not an achieved milestone. Source: Dual Fluid: February 2026 white paper, CDE programme (dated Feb 2026); Dual Fluid whitepaper, May 2026 edition: CDE status as of March 2026 (dated May 2026).
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No map pin is shown for this record.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
RAEB says the minimal critical CDE configuration would run for at most two years, that formal initial safety assessment review began in February 2025, and that a site license and regulator review of the technical design/safety report remain next steps. Dual Fluid identifies itself as designer and operator, with Rwanda providing infrastructure. The February 2026 paper gave a 2025 licensing expectation and a 2028–2030 testing target. Its May 2026 edition, describing status as of March 2026, instead expected site licensing during 2026 and describes core completion two years after financing, followed by two years of testing. These are company expectations, not an issued license or achieved construction. The May edition also reports completion of a first uranium-chromium fuel-production phase in 2026, without establishing a completed CDE core, delivery or approval. Press reporting of the 2023 agreement places the planned research campus in Nyamata, south of Kigali. No grid export, precise rating or construction start is established.
Key facts
- Design
- DF-CDE critical demonstration experiment (SMR)
- Technology
- Other · unknown
- Operator(s)
- Dual Fluid Energy
- Vendor for linked design
- Dual Fluid Energy
- Design origin
- Canada: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Nyamata nuclear research campus (planned) · Rwanda · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Town named, no map pin
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Dual Fluid critical demonstration experiment in Rwanda is recorded at Nyamata nuclear research campus (planned), Eastern Province, Rwanda. Operator: Dual Fluid Energy. Recorded vendor: Dual Fluid Energy. Stage: Licensing. Location precision: town or locality only; town named, no map pin.
Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorDual Fluid Energy
- Reactor supplier
- Vendor for the linked designDual Fluid Energy
- Contractor
Source-backed project statement The 14 September 2023 reports say Dual Fluid is responsible for technical implementation and will build the demonstration reactor, while Rwanda provides the site and infrastructure. The February 2026 paper says Dual Fluid is responsible for design and operation and Rwanda will provide infrastructure. No separate construction firm and no executed construction contract are named. WNN: Demonstration reactor to be built in Rwanda; Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme
- Funding and government decisions
Source-backed project statement The Globe and Mail reported on 14 September 2023 that Dual Fluid is paying for the project and that its finance chief was seeking to raise 70 million euros. The February 2026 paper places 15 million euros beside fabrication development and says capital acquisition for construction is being ramped up. Neither source says those amounts have been paid. Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme
- Fuel
- Fuel form stated for DF-CDE critical demonstration experimentliquid-metallic fuel
The sources describe liquid metallic fuel as the concept being tested. They do not name a supplier, a fabrication contract or a delivery of fuel for the Rwanda experiment. Dual Fluid: February 2026 white paper, CDE programme; RAEB: Critical Demonstration Experiment
- Comparable schedule revision
Source-backed project statement World Nuclear News and The Globe and Mail reported on 14 September 2023 that the demonstration was to be operational by 2026, with testing completed by 2028. Dual Fluid's February 2026 paper places construction and completion in 2026 and the testing phase in 2028–2030, so the end of testing moved from 2028 to as late as 2030. The 2023 dates were announced by the Rwandan government and the 2026 dates are the company's own; neither is an achieved date. WNN: Demonstration reactor to be built in Rwanda; Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme
Not found in the sources we checked (1): Customer or offtaker
- Customer or offtaker
The September 2023 reports and Dual Fluid's February 2026 paper describe a cooperation agreement: Rwanda provides the site and infrastructure, and Dual Fluid implements the critical experiment. The Globe and Mail and the company paper both say the demonstration is not to supply the grid. No energy buyer and no research-service customer are named. RAEB says the experiment is to study a low-power core for at most two years. Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme; RAEB: Critical Demonstration Experiment
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Initial Safety Assessment Report (ISAR) review begins - · Recorded development
Preliminary site survey report finds the site suitable - · Recorded development
IAEA expert mission on CDE safety analysis and design safety features - · Recorded development
RAEB and Dual Fluid sign the CDE cooperation agreement
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Construction start
CDE construction start (company target stated in February 2026, not reconfirmed by the May edition) - Target · Planned step
CDE testing phase (company target stated in February 2026, not reconfirmed by the May edition)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(10 notes)
- Evidence review. The Rwanda Atomic Energy Board's project page (opened 19 October 2026, no page date) says RAEB signed a cooperation agreement with Dual Fluid Energy Inc. in September 2023 to develop the Critical Demonstration Experiment (CDE) in Rwanda, the functional prototype for Dual Fluid's commercial DF300 design, run as a minimal critical configuration with a core about 60 cm across for at most two years. Dual Fluid's white paper (February 2026) says Dual Fluid is responsible for the design and operation of the reactor and Rwanda provides the infrastructure, and that the reactor is not intended to feed power into the grid; a press report of 13 September 2023 places the planned site at a new nuclear research campus in Nyamata, south of Kigali, which RAEB and Dual Fluid do not name. RAEB says a site survey delivered in April 2024 found the site suitable, a formal Initial Safety Assessment Report review began in February 2025, a site license is expected as a next step, and the Technical Design and Safety Report will soon be submitted to the regulator RURA, with a design approval expected; none of these is a license or permission. The white paper's roadmap expected site licensing to conclude by late 2025 and says, as of November 2025, that site licensing was over 90% complete and infrastructure preparations had started; no opened source reports a site license, nuclear construction or criticality. No power rating is published: RAEB gives only core size and duration, and a 2023 press report called it a one-megawatt reactor without a thermal or electrical basis. Targets, not achievements: construction and completion in 2026 and testing in 2028 to 2030 (white paper), replacing the 2023 statements of operation by 2026 and testing completed by 2028. The licensing stage rests on the formal safety-assessment review and a site licensing process; no application document or regulator acknowledgment is published. Dual Fluid as designer and stated operator, one unit and no output stay stored. Last checked 19 Oct 2026. RAEB: Critical Demonstration Experiment; Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme
What would change this
RURA acknowledgement of the Technical Design and Safety Report, a site license for the CDE, or a RAEB or Dual Fluid notice of construction start. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. RAEB says initial safety assessment review began in February 2025 and that the technical design/safety report will go to RURA. Dual Fluid's May 2026 whitepaper, describing status as of March 2026, expected site licensing to conclude during 2026, updating the earlier company's 2025 expectation. A company roadmap is not a regulator decision: no issued license or decision instrument is established by these sources. Last checked 27 Oct 2026. RAEB: Critical Demonstration Experiment; Dual Fluid whitepaper, May 2026 edition: CDE status as of March 2026
What would change this
RURA acknowledges the TDSR submission or issues a site license. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. The Globe and Mail's report of 13 September 2023 on the Rwandan government's announcement places the CDE at a new nuclear research campus in Nyamata, south of Kigali, with Rwanda supplying the site; World Nuclear News (14 September 2023) says the government agreed to provide the site and infrastructure. RAEB's project page and Dual Fluid's February 2026 white paper do not name the site, and RAEB says the site license is still a next step. Last checked 19 Oct 2026. Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; WNN: Demonstration reactor to be built in Rwanda
What would change this
A RAEB or RURA site-license document naming the site. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. RAEB describes a minimal critical configuration with a core about 60 cm across, run for at most two years, and Dual Fluid's February 2026 white paper says the reactor will not feed the grid; neither states a power rating. A 2023 press report called it a one-megawatt reactor without saying thermal or electrical, so no figure is stored. Last checked 19 Oct 2026. RAEB: Critical Demonstration Experiment; Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; Dual Fluid: February 2026 white paper, CDE programme
What would change this
The Technical Design and Safety Report summary or a RURA document stating the rating. Next scheduled check: 19 Jan 2027.
- Module/unit count. RAEB and Dual Fluid describe one demonstration reactor (the CDE) with a single core. Last checked 18 Oct 2026. RAEB: Critical Demonstration Experiment
What would change this
A change to the CDE configuration. Next scheduled check: 18 Jan 2027.
- Map coordinates: Not disclosed in the reviewed evidence. No opened source gives a facility point; the named locality (Nyamata) comes from 2023 press reporting, and a locality geocode is not used as a deployment pin. Last checked 19 Oct 2026. Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor
What would change this
A site-license document or official site description with a location. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. RAEB identifies site permission and regulator review of the technical design/safety report as next steps. The May 2026 company whitepaper, with status as of March 2026, expected site licensing during 2026 and makes core completion conditional on financing: two years after financing, followed by two years of CDE testing. It establishes no issued license, secured construction financing or achieved construction start. Last checked 27 Oct 2026. RAEB: Critical Demonstration Experiment; Dual Fluid whitepaper, May 2026 edition: CDE status as of March 2026
What would change this
An issued site license, a regulator decision on the design report, or a construction start for this experiment. Next scheduled check: 21 Jan 2027.
- Permissions and public process. RAEB says a formal initial safety-assessment review began in February 2025, an IAEA expert mission was held in Kigali on 25-29 March 2024, and a site survey delivered in April 2024 found the site suitable. The same undated page calls a site license a next step and says the technical design and safety report will go to the regulator. Dual Fluid's May 2026 edition, describing status as of March 2026, expected site licensing during 2026, replacing its earlier 2025 expectation. These sources establish no issued license or regulator decision. Last checked 27 Oct 2026. RAEB: Critical Demonstration Experiment; Dual Fluid: February 2026 white paper, CDE programme; Dual Fluid whitepaper, May 2026 edition: CDE status as of March 2026
What would change this
An issued site license, or a regulator decision on the technical design and safety report. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The Globe and Mail places the site at a nuclear research campus in Nyamata, south of Kigali, and says Rwanda will supply the site and infrastructure. RAEB says an April 2024 engineering survey found the site suitable and that a site license is still a next step. The demonstration is described as not feeding the grid. No land title, water right or interconnection is stated. Last checked 23 Oct 2026. Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor; WNN: Demonstration reactor to be built in Rwanda; RAEB: Critical Demonstration Experiment
What would change this
A site license, land title, water right or grid connection for the Nyamata experiment. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The February 2026 paper discusses waste burning and on-site recycling as features of the commercial concept. It does not state a spent-fuel storage, transport or waste arrangement for the Rwanda critical experiment. Last checked 23 Oct 2026. Dual Fluid: February 2026 white paper, CDE programme
What would change this
A spent-fuel or radioactive-waste arrangement for the critical demonstration experiment. Next scheduled check: 21 Jan 2027.
Evidence dates
(2 of 6 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(6)
- RAEB: Critical Demonstration Experiment (government, accessed 18 Oct 2026)
- WNN: Demonstration reactor to be built in Rwanda (news report, accessed 18 Oct 2026)
- Globe and Mail: Rwanda signs deal with Canadian startup to build nuclear reactor (news report, accessed 18 Oct 2026)
- NEA SMR Digital Dashboard edition 4.0 (per-design siting entries) (IAEA/NEA, accessed 2 Oct 2026)
- Dual Fluid: February 2026 white paper, CDE programme (company, dated Feb 2026, accessed 18 Oct 2026)
- Dual Fluid whitepaper, May 2026 edition: CDE status as of March 2026 (company, dated May 2026, accessed 27 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Dual Fluid critical demonstration experiment in Rwanda — https://smrmap.com/projects/dual-fluid-rwanda/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Dual Fluid critical demonstration experiment in Rwanda”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/dual-fluid-rwanda/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.