Projects / France · Siting
newcleo LFR-AS-30 at Beaumont-en-Véron / Savigny-en-Véron
newcleo began buying land in 2025 for a 30 MWe LFR-AS-30 lead-cooled reactor in the Chinon area; the national public debate ran from April to July 2026.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Notice updated 30 Sep 2026 · Recorded development: Véron newcleo proposal: CNDP says the debate reports are available. A CNDP notice says the debate reports are available. Source: CNDP: the public debate's report and assessment are online (notice updated 30 September 2026). Updates entry
More on this development
It gives newcleo and RTE until 30 December to explain how they take the debate into account and communicate their decision. The 30 December date is not a regulator's licensing-decision deadline.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- No map pin is shown for this record.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
No creation authorization is established. A CNDP notice published on 29 September and updated on 30 September 2026 says the debate's report and assessment are online; newcleo and RTE must state by 30 December 2026 how they take the debate into account and announce their decision.
Key facts
- Design
- LFR-AS-30 (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead
- Operator(s)
- Not recorded
- Vendor for linked design
- newcleo
- Location
- Beaumont-en-Véron / Savigny-en-Véron · France · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Town named, no map pin
- Electrical capacity
- 30 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
newcleo LFR-AS-30 at Beaumont-en-Véron / Savigny-en-Véron is recorded at Beaumont-en-Véron / Savigny-en-Véron, Indre-et-Loire, France. Operator: No operator is recorded. Recorded vendor: newcleo. Stage: Siting. Location precision: town or locality only; town named, no map pin.
Recorded electrical output is 30 MWe (gross/net unspecified), scope plant. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designnewcleo
- Fuel
- Project fuel information is described in the source-backed statement below.
Source-backed project statement newcleo's February 2026 public-debate brochure presents its planned MOX-LFR fuel plant in the Aube and the Véron reactor as linked steps of one fuel cycle, with the reactor's fuel to be made from existing recoverable nuclear material. This is a planned in-house fuel route, not a supply contract or delivery. Neither installation is authorized, and no quantity is stated. CNDP public debate brochure: newcleo LFR-AS-30
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
World Nuclear News reported on 14 February 2025 that newcleo's 30 MWe reactor would serve as an industrial demonstrator and technology showcase, and the February 2026 public-debate brochure says RTE would connect the projects to the grid. A grid connection is not a buyer, and neither source names a recipient of the reactor's electricity or heat. WNN: newcleo seeks to buy land for demonstration SMR; CNDP public debate brochure: newcleo LFR-AS-30
- Contractor
World Nuclear News reported on 14 February 2025 that newcleo's siting would be accompanied by preliminary studies for administrative authorizations, without naming a study firm, and the February 2026 debate brochure says RTE would provide the grid connection. A grid connection by the transmission operator is not an engineering or construction appointment, and no contractor is named for the Véron reactor. WNN: newcleo seeks to buy land for demonstration SMR; CNDP public debate brochure: newcleo LFR-AS-30
- Funding and government decisions
The February 2026 public-debate brochure gives a total investment of 3 billion euros for newcleo's two projects together, the Aube fuel plant and the Indre-et-Loire reactor, without a split, and says newcleo won a France 2030 innovative-reactor call without an amount. An investment estimate and a company-level award are not funding committed to the Véron reactor. CNDP public debate brochure: newcleo LFR-AS-30
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News reported on 14 February 2025 a target for newcleo's first French reactor to operate by the end of 2031. The February 2026 public-debate brochure gives 2032 and 2033 for two projects, with information fixed at 1 December 2025. The captured text does not assign either year to the Véron reactor. A project-specific comparable revision is therefore not established. WNN: newcleo seeks to buy land for demonstration SMR; CNDP public debate brochure: newcleo LFR-AS-30
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Notice updated · Recorded development
Véron newcleo proposal: CNDP says the debate reports are available
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(1)
- newcleo LFR-AS-30 safety-options request — applies to the design, not to a site
Design assessment sought · Application received · ASNR · submitted 19 Dec 2025
ASNR states that newcleo filed a safety-options request on 19 December 2025 for LFR-AS-30. The page does not record an opinion or a creation authorization.
Sources: ASNR, PRM projects and their fuel-fabrication plants
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. The CNDP public-debate brochure (newcleo and RTE, February 2026) presents a 30 MWe advanced modular reactor called LFR-AS-30 in Indre-et-Loire at Beaumont-en-Véron and Savigny-en-Véron near Chinon, alongside a separate MOX-LFR fuel-fabrication plant in the Aube, with RTE to provide the grid connections; the national public debate ran from 2 April to 30 July 2026. World Nuclear News reported that newcleo had started the land-acquisition process for its LFR-AS-30 demonstration reactor in the Chinon Vienne et Loire community of municipalities and would refer the project to the CNDP. The CNDP notice (published 29 September, updated 30 September 2026) says the debate report and the CNDP chair's assessment are online and that newcleo and RTE have until 30 December to explain how they take the debate into account and communicate their decision; if the project continues, a continuous consultation runs until the public inquiry. No creation-authorization application or regulator decision appears in the opened sources, and no operator is named. The next documentary decision is newcleo's response to the debate by 30 December 2026, followed by a creation-authorization application. The stored single LFR-AS-30 of 30 MWe, newcleo as vendor and the siting stage stay; the site is named by its two communes but has no coordinates. Last checked 19 Oct 2026. CNDP public debate brochure: newcleo LFR-AS-30; WNN: newcleo seeks to buy land for demonstration SMR; CNDP: the public debate's report and assessment are online (notice updated 30 September 2026)
What would change this
newcleo's published response to the public debate (due by 30 December 2026) stating whether it continues, then its creation-authorization application for the LFR-AS-30 at Beaumont-en-Véron / Savigny-en-Véron. Next scheduled check: 6 Jan 2027.
- Site location recorded as disclosed. The CNDP brochure locates the 30 MWe reactor in Indre-et-Loire at Beaumont-en-Véron and Savigny-en-Véron, and WNN reports land acquisition in the Chinon Vienne et Loire community of municipalities. No parcel or coordinate is published, so the commune pair can be recorded as named communes without a map pin, as for other named localities. Last checked 19 Oct 2026. CNDP public debate brochure: newcleo LFR-AS-30; WNN: newcleo seeks to buy land for demonstration SMR
What would change this
newcleo's creation-authorization application or the public-inquiry file giving the parcel and coordinates of the reactor site, which would allow a map point. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. CNDP says newcleo and RTE have until 30 December 2026 to state how they will take the debate into account, answer the public's questions and announce their decision, after which CNDP will give an opinion on that response. A creation-authorization application would be a later step. Last checked 23 Oct 2026. CNDP: the public debate's report and assessment are online (notice updated 30 September 2026)
What would change this
newcleo's and RTE's published decision after the debate, or CNDP's opinion on it. Next scheduled check: 6 Jan 2027.
- Permissions and public process. The National Commission for Public Debate ran a public debate on this reactor and newcleo's planned Aube fuel plant from 2 April to 30 July 2026. A CNDP notice published on 29 September and updated on 30 September 2026 says the report and assessment are online. If the project continues, continued public participation would run until a public inquiry. A debate is not an authorization, and no creation-authorization application is recorded. Last checked 23 Oct 2026. CNDP public debate brochure: newcleo LFR-AS-30; CNDP: the public debate's report and assessment are online (notice updated 30 September 2026)
What would change this
newcleo's published response to the debate, a creation-authorization application or a public-inquiry notice. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). newcleo began a land-acquisition process with the Chinon Vienne et Loire community of municipalities in February 2025, and the debate brochure says the grid operator RTE would provide the electrical connection for both newcleo projects. Neither source describes a completed land purchase, a signed connection agreement or the cooling arrangement. Last checked 23 Oct 2026. WNN: newcleo seeks to buy land for demonstration SMR; CNDP public debate brochure: newcleo LFR-AS-30
What would change this
A land purchase, RTE connection agreement or authorization file describing the Véron site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The debate brochure says spent fuel from the reactor would be stored and then intended for reprocessing by other existing operators before reuse. This is a planned fuel-cycle route, not a storage design, reprocessing contract or waste agreement, and neither newcleo installation is authorized. Last checked 23 Oct 2026. CNDP public debate brochure: newcleo LFR-AS-30
What would change this
An authorization file or agreement describing spent-fuel storage or reprocessing for the Véron reactor. Next scheduled check: 21 Jan 2027.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- CNDP public debate brochure: newcleo LFR-AS-30 (government, accessed 2 Oct 2026)
- WNN: newcleo seeks to buy land for demonstration SMR (news report, accessed 2 Oct 2026)
- CNDP: the public debate's report and assessment are online (notice updated 30 September 2026) (government, accessed 6 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: newcleo LFR-AS-30 at Beaumont-en-Véron / Savigny-en-Véron — https://smrmap.com/projects/newcleo-veron-lfr-as-30/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “newcleo LFR-AS-30 at Beaumont-en-Véron / Savigny-en-Véron”. Record reviewed 6 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/newcleo-veron-lfr-as-30/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.