Projects / United States · Suspended

Next Generation Nuclear Plant prototype HTGR at INL (2005-2013)

The Next Generation Nuclear Plant, a historical DOE and Idaho National Laboratory proposal for a prototype high-temperature gas-cooled reactor plant, is recorded as suspended.

Current status

Stage
Suspended
How current
General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: Aug 2008. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Under the Energy Policy Act of 2005, DOE and Idaho National Laboratory set up the NGNP Project to develop, license, build and operate a prototype modular high-temperature gas-cooled reactor plant for process heat and electricity. The statute requires the prototype and associated plant to be sited at Idaho National Laboratory. NRC's past-licensing page names DOE, INL and the NGNP Industry Alliance as the prelicensing parties. It does not name INL as the reactor operator, so that operator link is not kept. NRC prelicensing interactions began in 2006 and were suspended in 2013 after DOE decided in 2011 not to proceed to detailed design and license application. No design was licensed and nothing was built; output is not stored.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Not recorded
Vendor for linked design
No selected-design vendor recorded
Location
Idaho National Laboratory (NGNP prototype; location within INL not fixed) · United States · precision: town or locality only
The statute sites the NGNP prototype at Idaho National Laboratory without a location inside it. The pin is the recorded OpenStreetMap point for the laboratory at its Central Facilities Area (43.5306324, −112.94046): a laboratory-wide point, not a project site.
Coordinates
43.5306324, -112.94046 · town-level point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded. The NRC page calls the plant a prototype and states no module count.
Inclusion basis
Earlier-plan record (historical SMR program)
Confidence
medium
Record reviewed
19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Next Generation Nuclear Plant prototype HTGR at INL (2005-2013) is recorded at Idaho National Laboratory (NGNP prototype; location within INL not fixed), Idaho, United States. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Suspended. Location precision: town or locality only; town-level point (approximate).

Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Idaho National Laboratory, East Ogden Avenue, Central Facilities Area' (amenity=research_institute), 43.5306324, −112.94046

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Funding and government decisions

Source-backed project statement 42 U.S.C. 16025 authorized appropriations to the Secretary of Energy of US$1.25 billion for fiscal years 2006 to 2015, and such sums as necessary for 2016 to 2021, for NGNP research and construction, with industrial partners' work to be cost-shared. That is a statutory authorization, not a record of appropriations or spending, and the NRC page says DOE stopped before detailed design in 2011 after cost-sharing talks with industry reached an impasse. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting; NRC: Next Generation Nuclear Plant past licensing activities

Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
Customer or offtaker

The NRC's NGNP page says the prototype was meant to produce high-temperature process heat for hydrogen production and other energy-intensive industries while generating electricity, and 42 U.S.C. 16021 to 16025 set out the project, but neither names a buyer or user of its heat or power. DOE decided in 2011 not to proceed to detailed design and licensing. NRC: Next Generation Nuclear Plant past licensing activities

Contractor

42 U.S.C. 16022 required Idaho National Laboratory to organize a consortium of industrial partners for cost-shared research, design and construction, and the NRC's NGNP page says DOE's 2011 decision not to proceed cited impasses with the NGNP Industry Alliance over cost sharing for that public-private partnership. No design, engineering or construction contractor was appointed for the prototype in these sources. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting; NRC: Next Generation Nuclear Plant past licensing activities

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

42 U.S.C. 16023 lists nuclear fuel development, characterization and qualification as one of the NGNP Project's research elements, which is a development program, not a fuel supply. No fuel supplier, fabrication contract or delivery for a prototype at INL is stated, and nothing was built. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting

Comparable schedule revision

Comparable schedule revision not established. 42 U.S.C. 16025 set targets of 30 September 2011 for the first project phase and 30 September 2021 to complete construction and begin operations, each with the option of reporting an alternative date to Congress. The NRC's page says DOE decided in 2011 not to proceed and prelicensing was suspended in 2013. No source read states a revised completion date, so no revision is shown. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting; NRC: Next Generation Nuclear Plant past licensing activities

Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(9 notes)
  • Evidence review. The NRC page supports the 2006-2013 prelicensing history and the 2011 DOE decision not to proceed to detailed design and a license application, and that INL is not stored as the reactor operator. The saved United States Code text does contain the prototype siting sentence, which the earlier review had not opened. It names Idaho National Laboratory and gives no point inside the laboratory. Last checked 20 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities; 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting
    What would change this

    A DOE notice that restarts the NGNP license application, or a document that places the prototype on a point inside Idaho National Laboratory. Next scheduled check: 20 Jan 2027.

  • Plant capacity (scope qualified): Not disclosed in the reviewed evidence. The NRC page describes the prototype mission and states no electrical or thermal output. Last checked 19 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities
    What would change this

    A DOE or NRC document that states the prototype output. Next scheduled check: 19 Jan 2027.

  • Module/unit count: Not disclosed in the reviewed evidence. The NRC page calls the plant a prototype and states no module count. Last checked 19 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities
    What would change this

    A design or license document that states the prototype's module count. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed. The statute says the prototype nuclear reactor and associated plant shall be sited at the Idaho National Laboratory in Idaho. It gives no coordinates and no point inside the laboratory, so the map shows a laboratory-wide point. Last checked 20 Oct 2026. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting
    What would change this

    A site study that places the prototype on a stated point inside Idaho National Laboratory. Next scheduled check: 20 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. NRC's page describes the NGNP prototype only as a modular high-temperature gas-cooled reactor plant and says DOE decided in 2011 not to proceed into detailed design and license application. It names no selected vendor design. No design profile is linked. Last checked 19 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities
    What would change this

    A DOE or NRC document that records a reactor design selected for the NGNP prototype. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The NRC's page says DOE decided in 2011 not to proceed into the detailed design and license application phases of the NGNP Project, citing an impasse with the NGNP Industry Alliance over cost sharing, and that NRC interactions were suspended in 2013. The project remains suspended; any next step would be a new DOE decision to restart it, and none is recorded in these sources. Last checked 23 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities
    What would change this

    A DOE decision to restart or formally terminate the NGNP Project. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The NRC's past-licensing page says the NRC held prelicensing interactions with DOE and Idaho National Laboratory on the NGNP prototype from 2006, beginning with a joint licensing strategy report to Congress in August 2008 and reviews of white papers, and that the interactions were suspended in 2013. No license application was filed and no permit issued. Last checked 23 Oct 2026. NRC: Next Generation Nuclear Plant past licensing activities
    What would change this

    A DOE decision to resume NGNP licensing, or NRC records of a new application for an HTGR prototype at INL. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Section 642 of the Energy Policy Act of 2005, codified at 42 U.S.C. 16022, requires the NGNP prototype reactor and associated plant to be sited at Idaho National Laboratory and to use INL reactor test capabilities where appropriate. The statute fixes the host laboratory but names no plot, grid or water arrangement, and nothing was built. Last checked 23 Oct 2026. 42 U.S.C. 16022(b)(3) (Energy Policy Act of 2005, section 642): prototype plant siting
    What would change this

    A DOE document selecting a location at INL for an NGNP-type prototype. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. The August 2008 joint DOE-NRC licensing strategy report to Congress for the NGNP prototype says the NRC intended to apply existing light-water reactor requirements for spent fuel management when licensing an NGNP reactor, and that guidance would need to address NGNP-specific spent fuel issues. It sets a licensing approach only: the report names no storage facility, disposal route or responsible party for NGNP spent fuel. No license application followed, so no plant-specific arrangement is recorded in these sources. Last checked 23 Oct 2026. Next Generation Nuclear Plant Licensing Strategy: A Report to Congress
    What would change this

    A DOE or NRC document assigning storage or disposal of NGNP prototype fuel, or a revived license application, would change this answer. Next scheduled check: 22 Oct 2027.

Evidence dates

(1 of 3 sources with a publication or document date)
Latest dated listed source publication: Next Generation Nuclear Plant Licensing Strategy: A Report to Congress: Aug 2008.Latest dated recorded event: no date recorded.2 of 3 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(3)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Next Generation Nuclear Plant prototype HTGR at INL (2005-2013) — https://smrmap.com/projects/ngnp-inl/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Next Generation Nuclear Plant prototype HTGR at INL (2005-2013)”. Record reviewed 19 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/ngnp-inl/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.