Projects / United States · Announced
Nine Mile Point Gen III+ SMR early site permit evaluation
Constellation's January 2025 announcement proposes early-site-permit work for one or more advanced reactors at Nine Mile Point, with NYSERDA cost-share support.
Current status
- How current
- General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
DOE's May 2026 award names Constellation SMR Development, LLC and $17,264,292 for pursuing an ESP at a New York location, without naming Nine Mile Point. An issued permit, selected reactor model and future operating entity are not established. The proposed reactor remains separate from the existing units and the canceled large Unit 3 proposal.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Not recorded
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Nine Mile Point Clean Energy Center (advanced/SMR ESP evaluation) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain export station point (derived from GEM's tracker) for the existing Nine Mile Point plant, the named host of the ESP evaluation; plant-area pin, because new SMR coordinates within the site are not fixed. - Coordinates
- 43.5205, -76.4068 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Nine Mile Point Gen III+ SMR early site permit evaluation is recorded at Nine Mile Point Clean Energy Center (advanced/SMR ESP evaluation), New York, United States. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'nine-mile-point-nuclear-power-plant-smr' (43.5205, -76.4068)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerConstellation Energy Corporation · source
- Funding and government decisions
Source-backed project statement Constellation's January 2025 release says New York's energy research authority joined its proposal for Department of Energy support of an early site permit for one or more advanced reactors at Nine Mile Point, and calls that cost-share funding a first step, with no amount or payment stated. The Department of Energy's May 2026 award of 17,264,292 dollars to Constellation SMR Development, LLC is for an early site permit at a New York location and does not name Nine Mile Point. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
- Customer or offtaker
Constellation's 15 January 2025 release describes an early site permit effort for one or more advanced reactors at Nine Mile Point and refers to statewide households and businesses, and DOE's 14 May 2026 award supports an early site permit for a New York location. Neither names a buyer of power from a new reactor. Constellation's Google and Amazon agreements listed on the same page concern other plants. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
- Contractor
Constellation's 15 January 2025 release says NYSERDA joined its grant proposal to seek an early site permit at Nine Mile Point, which is a cost-share partnership, not a contractor role. Neither that release, POWER Magazine's 16 January 2025 report nor DOE's 14 May 2026 award names an engineering firm or reactor vendor for the project. Constellation's Rolls-Royce SMR interest concerns the Netherlands. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; POWER: Constellation seeking permit for SMR at Nine Mile Point; Syracuse.com: DOE awards Constellation $17.3M for Nine Mile Point ESP
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
Constellation's 15 January 2025 release names no fuel supplier for a new Nine Mile Point reactor, and the fuel-fabrication awards on DOE's 14 May 2026 page, to Framatome in Richland and Global Nuclear Fuel in Wilmington, do not name Nine Mile Point. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
- Comparable schedule revision
Comparable schedule revision not established. Constellation's 15 January 2025 release, POWER Magazine's 16 January 2025 report and DOE's 14 May 2026 award give no construction or operation year for a new Nine Mile Point reactor. The early site permit's 10 to 20 year validity and DOE's reference to new generation in the 2030s are not project targets, so there is nothing to revise. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; POWER: Constellation seeking permit for SMR at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. Constellation's 15 January 2025 announcement identifies Nine Mile Point as the intended site for evaluation of one or more advanced reactors and an early-site-permit effort with NYSERDA cost-share support. DOE's 14 May 2026 award names Constellation SMR Development, LLC and $17,264,292 for pursuing an early site permit at a New York location; DOE does not name Nine Mile Point in that award text. Neither source establishes an issued permit, selected design, reactor capacity, unit count or future operating entity. Constellation's role as proposer and existing-station operator does not appoint it as the operator of a new reactor. Last checked 19 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
What would change this
An opened Constellation or NRC project filing linking the awarded ESP work to the specific site and identifying its applicant, selected configuration and next regulatory decision. Next scheduled check: 19 Jan 2027.
- Design identified: Not disclosed in the reviewed evidence. One or more advanced/Gen III+ reactors are being evaluated; neither the company nor DOE passage selects a model. Last checked 19 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
What would change this
An opened Constellation or NRC project filing linking the awarded ESP work to the specific site and identifying its applicant, selected configuration and next regulatory decision. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next step named in Constellation's January 2025 release is to pursue an early site permit at Nine Mile Point. The May 2026 award supports an early site permit somewhere in New York and does not show that an application for this site has been filed. Last checked 23 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
What would change this
A docketed early site permit application naming Nine Mile Point. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Constellation's January 2025 release says the company is seeking a Nuclear Regulatory Commission early site permit for one or more advanced reactors at Nine Mile Point. It does not say an application has been filed. An early site permit, if issued later, would approve a site and would not be a construction permit. Last checked 23 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point
What would change this
A docketed early site permit application for Nine Mile Point. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Constellation's January 2025 release places the proposal at the existing Nine Mile Point Clean Energy Center in Oswego, New York. It states no new land transfer, water withdrawal or grid interconnection. This is a named existing site only. Last checked 23 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point
What would change this
A site, water or interconnection agreement for the new reactors at Nine Mile Point. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Constellation's January 2025 Nine Mile Point release and the Department of Energy's May 2026 award notice discuss an early site permit and funding. Neither describes spent fuel, waste storage or closure for the proposed reactors. Last checked 23 Oct 2026. Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point; DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M)
What would change this
A spent-fuel, waste or decommissioning plan for the Nine Mile Point proposal. Next scheduled check: 21 Jan 2027.
Evidence dates
(0 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- DOE: $94M awards to expedite Gen III+ SMR deployments (Constellation $17.264M) (government, accessed 2 Oct 2026)
- Constellation: NY joins pursuit of DOE funding for advanced nuclear at Nine Mile Point (company, accessed 2 Oct 2026)
- Syracuse.com: DOE awards Constellation $17.3M for Nine Mile Point ESP (news report, accessed 2 Oct 2026)
- POWER: Constellation seeking permit for SMR at Nine Mile Point (news report, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Nine Mile Point Gen III+ SMR early site permit evaluation — https://smrmap.com/projects/nine-mile-point-advanced-smr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Nine Mile Point Gen III+ SMR early site permit evaluation”. Record reviewed 2 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/nine-mile-point-advanced-smr/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.