Projects / Sweden · Licensing
Blykalla SEALER Untra / Tierp proposal
Blykalla applied to the Swedish Government on 25 August 2026 for approval of up to eight lead-cooled small modular reactors of up to 440 MWe in total at Untra in Tierp municipality.
Current status
- How current
- General record check . Bounded evidence review . 2 of 6 listed sources have a publication or document date recorded here; the newest is 31 Aug 2026. Swedish Government approval application for a nuclear facility at Untra, Tierp: status (under review) confirmed against Government of Sweden: Government review of new nuclear (status of applications).
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: Swedish Government approval application for a nuclear facility at Untra, Tierp. An application under review is not a permit. All permissions and applications
- Latest development
- 31 Aug 2026 · Recorded development: Untra Nuclear Power AB applies for Swedish state support. Untra Nuclear Power AB applied for Swedish state support. Source: blykalla.com: Untra Nuclear Power AB applies for Swedish state support (published 31 Aug 2026). Updates entry
- Next dated milestone
- Planned step: 30 Apr 2027 (target). Untra facility plan proposal due to the Government. This is not an achieved milestone. Source: Government of Sweden: facility-plan assignment for the Untra application.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 2 licensing, 1 siting. Separately: 1 canceled. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The Government recorded receipt on 26 August and assigned the county administrative board to draft a facility plan by 30 April 2027. On 31 August 2026 Untra Nuclear Power AB, a project company wholly owned by Blykalla, applied for state support for a park of six to eight units; an application is not an award. First-half-2030s operation is conditional on approvals; no approval, license or construction is established.
Key facts
- Design
- SEALER (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead
- Operator(s)
- Blykalla
- Vendor for linked design
- Blykalla
- Location
- Untra, Tierp municipality · Sweden · precision: town or locality only
Point from the Swedish Wikipedia article for the Untra hydropower station at Untra in Tierp, the place Blykalla names; Blykalla publishes no facility point, so this is a locality point, not the park. - Coordinates
- 60.43889, 17.33889 · town-level point (approximate)
- Electrical capacity
- 440 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Blykalla SEALER Untra / Tierp proposal is recorded at Untra, Tierp municipality, Uppsala County, Sweden. Operator: Blykalla. Recorded vendor: Blykalla. Stage: Licensing. Location precision: town or locality only; town-level point (approximate).
Coordinate source: Wikipedia: Untraverket (article coordinates), Article coordinate 60.43889, 17.33889 on 'Untraverket', read 30 October 2026
Recorded electrical output is 440 MWe (gross/net unspecified), scope plant. Modules planned: 8. Thermal output is not recorded on this project. The linked design record states 140 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 55 MWe (gross/net unspecified); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorBlykalla
- Reactor supplier
- Vendor for the linked designBlykalla
- Funding and government decisions
Source-backed project statement On 31 August 2026 Blykalla said Untra Nuclear Power AB, its wholly owned project company, applied for Swedish state support for the Untra park. The same company release says the model uses state loans, a contract for difference, and risk and gain sharing, with interest, strike price, and length still to be negotiated and reviewed by the European Commission. Negotiations start only if the Government Offices decide to proceed. The application is not money paid, and no amount is stated. blykalla.com: Untra Nuclear Power AB applies for Swedish state support
- Fuel
- Fuel form stated for SEALERUN (uranium nitride), as stated by ARIS
Blykalla's 25 August 2026 application describes the Untra units as lead-cooled SEALER reactors, which is a coolant and design description rather than a fuel-supply commitment. The 31 August 2026 financing release and the Government pages of 28 August 2026 and 2 October 2026 do not name a fuel supplier, fabrication contract, delivery, or loading for Untra. The Oskarshamn electric test facility named in the application is a different site. Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity; blykalla.com: Untra Nuclear Power AB applies for Swedish state support; Government of Sweden: facility-plan assignment for the Untra application
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
Blykalla's 25 August 2026 application says the Untra park would supply new capacity for industrial development and future energy-intensive establishments, and its 31 August 2026 financing release describes six to eight commercial SEALER-55 units in bidding zone SE3. Neither those company pages nor the Government's 28 August 2026 assignment and 2 October 2026 status page names an offtaker or a research-service customer. The developer and Tierp municipality are not treated as customers. Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity; blykalla.com: Untra Nuclear Power AB applies for Swedish state support; Government of Sweden: facility-plan assignment for the Untra application
- Contractor
Blykalla's 25 August 2026 application names value-chain partners and an electric test facility at Oskarshamn with Uniper, which is a different site from Untra. The 31 August 2026 financing release and the Government's 28 August 2026 assignment and 2 October 2026 status page name no engineering, FEED, or construction contractor for the Untra park. Those partner sentences are not an Untra construction award. Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity; blykalla.com: Untra Nuclear Power AB applies for Swedish state support; Government of Sweden: facility-plan assignment for the Untra application
- Comparable schedule revision
Comparable schedule revision not established. Blykalla stated the same operation target twice: first operations at Tierp in the first half of the 2030s on 25 August 2026, and the first reactor at Untra in the first half of the 2030s on 31 August 2026, both conditional on approvals. Repeating one target is not a revision. The Government's 30 April 2027 date is the deadline for the county board's draft facility plan, a different milestone. Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity; blykalla.com: Untra Nuclear Power AB applies for Swedish state support; Government of Sweden: facility-plan assignment for the Untra application
Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Untra Nuclear Power AB applies for Swedish state support - · Recorded development
Government assigns Uppsala county administrative board to draft Untra facility plan - Announced · Announcement
Blykalla reports application for up to eight SEALER units at Untra, Tierp - · Application submitted
Blykalla applies for Government approval of eight lead-cooled SMRs at Untra, Tierp
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Untra facility plan proposal due to the Government
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- Swedish Government approval application for a nuclear facility at Untra, Tierp
Site permission sought · Under review · Government of Sweden · submitted 25 Aug 2026
Blykalla AB applied on 25 August 2026 (recorded as received on 26 August) for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality; on 28 August 2026 the Government assigned the Uppsala county administrative board to draft a facility plan by 30 April 2027. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Untra applicationStatus confirmed on against Government of Sweden: Government review of new nuclear (status of applications). This confirms the recorded status only; the general record check date remains separate.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The source review names Untra outside Tierp and stores no facility point. The Government notice published 28 August 2026 says Blykalla AB applied on 25 August 2026 to approve a nuclear facility in Tierp municipality, and the status list shows Untra, Tierp, received 2026-08-26, still under preparation. The same notice says the application is for eight lead-cooled small modular reactors with a total electrical output of about 440 MW, and that the Uppsala county board must report its facility-plan draft by 30 April 2027. Blykalla's own release says the Tierp park would feature up to eight lead-cooled reactors and up to 440 MW, and elsewhere on that page names its reactor SEALER. The Government wording is eight and about 440 MW; the company wording is a ceiling. The stored eight modules and 440 MWe stay with that distinction, not as a per-module rating. On the Government's process page, approval under this law does not replace licensing under the Environmental Code and the Nuclear Activities Act. No construction is described. A 31 August 2026 state-financing application was not found in the opened Untra pages. Last checked 20 Oct 2026. Government of Sweden: facility-plan assignment for the Untra application; Government of Sweden: Government review of new nuclear (status of applications); Blykalla Untra application
What would change this
The Uppsala county board's Untra facility-plan draft, due to the Government by 30 April 2027, or a Government decision on the 25 August 2026 application. Next scheduled check: 20 Jan 2027.
- Site location recorded as disclosed. The Government's facility-plan assignment names the site as Untra outside Tierp, in Tierp municipality, Uppsala county, and Blykalla's application release gives the same location. No property designation or plan area has been published yet. Last checked 18 Oct 2026. Government of Sweden: facility-plan assignment for the Untra application; Blykalla Untra application
What would change this
Uppsala county board publishes consultation documents for the Untra facility plan. Next scheduled check: 18 Jan 2027.
- Map coordinates: Not disclosed in the reviewed evidence. Neither the Government nor Blykalla publishes a facility point, property designation or plan boundary for Untra. The county board's draft facility plan is due to the Government by 30 April 2027. The map uses a locality point for Untra, labeled approximate, not a facility point. Last checked 18 Oct 2026. Government of Sweden: facility-plan assignment for the Untra application; Government of Sweden: Government review of new nuclear (status of applications)
What would change this
Publication of the Untra plan map or plan description with a location reference. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The next steps are the Uppsala county board's draft facility plan, the municipality's approval of the plan and the application, and then the Government's decision. Approval would lead to separate Environmental Code and Nuclear Activities Act permit reviews. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
What would change this
The draft facility plan, a municipal vote or a Government decision for Untra in Tierp. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Government Offices list the application for Untra in Tierp as under preparation, with the Uppsala county administrative board drafting a facility plan on the Government's behalf. The municipality must approve both the plan and the application before the Government can decide, and Government approval does not replace permits under the Environmental Code and the Nuclear Activities Act. No municipal or Government decision is recorded. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
What would change this
A municipal decision on the facility plan or a Government decision on the Untra in Tierp application. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. The facility plan being drafted for Untra in Tierp is the instrument that guides how land and water areas may be used. It is a draft under preparation, not a secured land, grid or cooling-water arrangement, and the opened Government page describes none for this site. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
What would change this
The published draft facility plan or a grid or water arrangement for Untra in Tierp. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The Government's 2 October 2026 process page says an approval review considers whether there are conditions to manage the nuclear material handled and the nuclear waste that arises. That sentence is a criterion for the new process, not a spent-fuel, waste, or closure arrangement for Untra. Blykalla's 25 August and 31 August 2026 releases do not state one for this park. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications); Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity; blykalla.com: Untra Nuclear Power AB applies for Swedish state support
What would change this
An Untra application or permit text that states spent-fuel storage, waste disposition, or closure arrangements for this park. Next scheduled check: 21 Jan 2027.
Evidence dates
(2 of 6 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(6)
- Blykalla Untra application (company, accessed 18 Oct 2026)
- Blykalla news list (company, accessed 2 Oct 2026)
- Government of Sweden: Government review of new nuclear (status of applications) (government, accessed 3 Nov 2026)
- Government of Sweden: facility-plan assignment for the Untra application (government, accessed 18 Oct 2026)
- Blykalla submits application for second advanced nuclear reactor park in Sweden, with up to 440 MW of capacity (company, published 25 Aug 2026, accessed 21 Oct 2026)
- blykalla.com: Untra Nuclear Power AB applies for Swedish state support (company, published 31 Aug 2026, accessed 14 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Blykalla SEALER Untra / Tierp proposal — https://smrmap.com/projects/sealer-untra/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Blykalla SEALER Untra / Tierp proposal”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/sealer-untra/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.