Projects / Ukraine · Announced
TEPLATOR heat-only reactor for Slavutych district heating
World ThermoExport's TEPLATOR for Slavutych in Ukraine is a heat-only district-heating project at the announced stage, with delivery foreseen only after the war and licensing.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- No map pin is shown for this record.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
In July 2023 World ThermoExport, Teploatom Service and the City of Slavutych signed a contract for delivery of a TEPLATOR to Slavutych after the war and licensing; timing, quantity and terms were not defined. The developer still listed it as an MoU for a first unit in June 2024.
Key facts
- Design
- TEPLATOR (SMR)
- Technology
- Other · other
- Operator(s)
- Not recorded
- Vendor for linked design
- World ThermoExport
- Design origin
- Czechia: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Slavutych district heating · Ukraine · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Town named, no map pin
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
TEPLATOR heat-only reactor for Slavutych district heating is recorded at Slavutych district heating, Kyiv Oblast, Ukraine. Operator: No operator is recorded. Recorded vendor: World ThermoExport. Stage: Announced. Location precision: town or locality only; town named, no map pin.
This project is recorded as thermal only (no MWe). Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designWorld ThermoExport
- Customer or offtaker
Source-backed project statement The Czech Technical University's CIIRC page of 13 July 2023 and a ČTK report of 12 July 2023 say the City of Slavutych signed, with World ThermoExport and Teploatom Service, a contract for future take-up of the TEPLATOR, making the city the first client for nuclear district heat. ČTK says the contract does not yet define when, in what quantity or on what terms the technology would be delivered, and delivery depends on the end of the war and licensing. CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině; ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město
- Contractor
Source-backed project statement ČTK reported on 12 July 2023 that Teploatom Service will be the representative for implementing the TEPLATOR technology, with subsequent construction and management in Slavutych, and CIIRC's 13 July 2023 page calls it the official implementation representative for construction and operation of facilities in Ukraine. This is a stated implementation role under a contract that defines no timing, quantity or terms. It is not a license or a defined construction contract. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město; CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině
- Fuel
- Fuel form stated for TEPLATOR (catalog profile as of 14 Feb 2025)VVER-440 spent fuel assemblies
Source-backed project statement
CIIRC's 13 July 2023 page quotes the TEPLATOR lead saying talks had begun with Atomremont Service, an Energoatom unit that stores, transports and unloads spent VVER-440 fuel, and says the company would play an important role in the Ukrainian TEPLATOR's nuclear fuel source. This is a prospective fuel-source partner in early negotiations. No agreement, quantity or delivery for Slavutych is stated. CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině
- Programs and agreements naming the project
- Feasibility or siting study; activeEnergoatom and the exclusion-zone agency: SMR siting in the Chornobyl exclusion zone (Kopachi, Leliv)
Not found in the sources we checked (2): Funding and government decisions; Comparable schedule revision
- Funding and government decisions
ČTK's 12 July 2023 report quotes the head of IPC Holding, Teplator's majority owner, saying the project needs multi-source financing, that licensing alone would cost 50 to 100 million crowns and a prototype over a billion crowns. These are company-level cost estimates, and the same report says the Slavutych contract defines no terms. No funder or amount for the Slavutych unit is stated. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město; CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině
- Comparable schedule revision
Comparable schedule revision not established. ČTK's 12 July 2023 report says delivery to Slavutych depends on the end of the war and on licensing, which could take up to five years, and that the contract sets no delivery date. CIIRC's 13 July 2023 page and the June 2024 TEPLATOR slides give no Slavutych construction or operation year. With no dated target there is nothing to revise. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město; R. Škoda (CTU/UWB): TEPLATOR presentation
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Operator or intended licensed owner; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Site host or owner
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. On 12 July 2023 World ThermoExport signed a three-party contract to deliver a Teplator to Slavutych. ČTK says delivery is counted on only after the war in Ukraine and after the technology's licensing proceeding, and that the contract does not define when, in what quantity, or on what terms. It also says the licensing proceeding was still to be started. A later slide lists an MoU with Slavutych for a FOAK. No plot, output, or granted license is stated. World ThermoExport remains the stored vendor. Teploatom Service is named and has no organization record. Last checked 20 Oct 2026. CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině; ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město; R. Škoda (CTU/UWB): TEPLATOR presentation
What would change this
A Slavutych license application or a contract amendment that states quantity, output, and a delivery date. Next scheduled check: 20 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The pages name the city of Slavutych in northern Ukraine. They do not name a plot or give coordinates. The stored location names only the city. Last checked 20 Oct 2026. CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině; ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město
What would change this
A siting notice for the heating plant inside Slavutych. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. The July 2023 ČTK report says the contract does not yet set when, in what quantity or on what terms TEPLATOR will be delivered to Ukraine, because of the war and because licensing had not begun; the developer said licensing and trial operation could take up to five years. The next steps are therefore the end of the war and completion of technology licensing, with no date fixed. Last checked 23 Oct 2026. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město
What would change this
Completion of TEPLATOR technology licensing or a dated delivery agreement for Slavutych. Next scheduled check: 23 Apr 2027.
- Permissions and public process. A ČTK report of 12 July 2023, republished by the Czech Technical University, says the contract signed that day with Ukrainian partners provides for delivery of a TEPLATOR to Slavutych after the war ends and after licensing of the technology is completed, and that licensing was only to start that year, prepared in Canada. No Ukrainian license, application or public procedure for a Slavutych unit is described. Last checked 23 Oct 2026. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město
What would change this
Start of a Ukrainian licensing or environmental procedure for a TEPLATOR unit in Slavutych. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). The July 2023 ČTK report says Slavutych, a town of about 27,000, is connected to a central heating system, which the developers consider ideal for TEPLATOR, and that Teploatom Service would implement, build and manage the unit there. The report names no plot, heat-network connection agreement or other site arrangement. Last checked 23 Oct 2026. ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město
What would change this
A Slavutych site selection or district-heating connection agreement for TEPLATOR. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. The Czech Technical University's July 2023 article says TEPLATOR's nuclear fuel source for Slavutych involves irradiated VVER-440 fuel, and that talks had begun with Atomremont Servis, part of Energoatom, which handles storage, transport and unloading of such spent fuel. This concerns supplying used fuel to TEPLATOR; the article does not say who would store or dispose of the fuel after use in TEPLATOR, and talks are not a contract. Last checked 23 Oct 2026. CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině
What would change this
A signed agreement with Atomremont Servis or Energoatom on fuel supply and spent-fuel return for a Slavutych TEPLATOR. Next scheduled check: 23 Apr 2027.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- CIIRC CTU: TEPLATOR slaví úspěch na Ukrajině (company, accessed 2 Oct 2026)
- ČTK via CTU news: Jaderný Teplator z ČVUT chce v budoucnu využívat ukrajinské město (news report, accessed 2 Oct 2026)
- R. Škoda (CTU/UWB): TEPLATOR presentation (company, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: TEPLATOR heat-only reactor for Slavutych district heating — https://smrmap.com/projects/teplator-slavutych/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “TEPLATOR heat-only reactor for Slavutych district heating”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/teplator-slavutych/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.