ACP100 (Linglong One)
Chinese land-based integral PWR SMR. IAEA PRIS lists the Linglong One unit at 385 MWth, 125 MWe gross and 100 MWe net; the 125 MWe recorded here is the gross figure.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
- Projects
- Commissioning: Linglong One (ACP100) Changjiang.
- Evidence
- 5 sources; first primary source: IAEA Power Reactor Information System (PRIS). Record reviewed 9 Oct 2026.
Key facts · Tracked projects · Sources · Evidence · Regulatory actions · Its projects in the table · Compare with other designs
Key facts
- Class
- SMR
- Technology
- Integral pressurized water reactor (iPWR)
- Coolant
- Light water
- Spectrum
- Thermal
- Developer / vendor(s)
- China National Nuclear Corporation
- Module electrical
- 125 MWe (gross)
- Module thermal
- 385 MWth (nameplate; basis unspecified)
- Reactor vessel
- 10 m tall, 3.35 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 11.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.All vessels to scale10 m bar; a person 1.8 m tallACP100 (Linglong One)
10 m tall, 3.35 m across - Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 9 Oct 2026 (record review date, not proof of current availability or a deployment)
Tracked deployment projects
- Linglong One (ACP100) Changjiang — Commissioning · China
Design sources
(5)
- World Nuclear Association — Small Nuclear Power Reactors (directory or tracker, accessed 1 Oct 2026)
- IAEA Power Reactor Information System (PRIS) (IAEA/NEA, accessed 1 Oct 2026)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- IAEA PRIS statistics: reactors by country code (China), captured 9 October 2026 (IAEA/NEA, accessed 17 Oct 2026)
- IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026) (IAEA/NEA, accessed 9 Oct 2026)
Evidence and open questions
(1 note)
- Evidence review. The live IAEA PRIS unit list for China (captured 19 October 2026, Member-State submissions) lists LINGLONG-1, model ACP100, alternate name Hainan Changjiang SMR, as a pressurized light-water-moderated and cooled reactor under construction at the Chang Jiang site, with 385 MWth thermal power, 125 MWe gross, 100 MWe net and 100 MWe design net capacity. PRIS gives a construction license date of 15 July 2019 and construction start of 13 July 2021, no criticality or grid date, and Hainan Nuclear Power Company as operator; it names China First Heavy Industries as reactor supplier, a component supplier rather than the design developer. EnergyNote's licensing map (early September 2026, partly updated 2 October) describes Linglong One ACP100 as an integral LWR of 125 MWe in pre-commissioning, with cold tests done in October 2025, pre-startup tests still under way in early August 2026, the H1 2026 target missed and no criticality yet. Both sources tie the design to the linked Linglong One unit at Changjiang. Stored iPWR, light-water coolant, 385 MWth and 125 MWe gross stay supported; the stored vendor CNNC is not named as the ACP100 developer in any opened source, and the thermal spectrum rests on the light-water-moderated type rather than an explicit statement. Last checked 19 Oct 2026. IAEA PRIS statistics: reactors by country code (China), captured 9 October 2026; EnergyNote 2026 SMR licensing map
What would change this
PRIS or an NNSA notice recording Linglong One's first criticality or grid connection (or an NNSA operating license), which would move the deployment out of construction; a CNNC/NPIC design document would confirm the developer. Next scheduled check: 19 Jan 2027.
Regulatory actions
Compare reviews and approvals across designs
Construction applications and decisions
- NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One) — Linglong One (ACP100) Changjiang
Construction permission · Issued / approved · NNSA · decided 1 Jul 2021 · permit 国核安证字第2117号
NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.
Sources: NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)