Projects / China · Commissioning
Linglong One (ACP100) Changjiang
CNNC's land-based ACP100 SMR demonstration unit at the Changjiang nuclear base in Hainan, China, is in pre-commissioning/testing.
Current status
- How current
- General record check . Bounded evidence review . 8 of 18 listed sources have a publication or document date recorded here; the newest is 1 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One) (1 Jul 2021). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- Reported 1 Oct 2026 · Recorded development: Linglong One reported in hot functional testing. Linglong One was in hot functional testing, the test after which fuel loading comes next, according to a China News Service site report. Source: China News Service: Linglong One hot functional testing (1 October 2026) (published 1 Oct 2026); NucNet: Hot Testing Begins At China’s Linglong-1 Small Modular Reactor (7 October 2026). Updates entry
More on this development
Fuel loading, criticality and grid connection had not happened; the 2026 dates are targets.
- Next dated milestone
- Planned step: 2026 (target). Reported target: Linglong One fuel loading and grid connection within 2026. This is not a commitment and is not an achieved milestone. Source: China News Service: Linglong One hot functional testing (1 October 2026) (published 1 Oct 2026); NucNet: Hot Testing Begins At China’s Linglong-1 Small Modular Reactor (7 October 2026).
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The stored 2026 commercial-operation plan is not treated as achieved; NucNet reported in October 2026 that a CNNC official had been quoted in December 2025 expecting commercial operation in the first half of 2026, and no later source read gives a commercial-operation date. Regulator notices of March, June and August 2026 record key review issues (main-pump nozzle safety, once-through steam generator flow stability), pre-fuel-load preparation and a review of commissioning anomalies; the regulator's operating-unit table, updated 30 September 2026, does not list the unit, and its under-construction table does, and the National Energy Administration's July 2026 report records cold functional tests completed in 2025. IAEA PRIS still lists the unit as under construction (construction start 13 July 2021; 385 MWth, 125 MWe gross, 100 MWe net) and gives a construction-license date of 15 July 2019, which conflicts with the NNSA construction license 国核安证字第2117号 dated 1 July 2021; the license document governs here and the PRIS date is kept visible as an unexplained discrepancy. China News Service reported from Changjiang on 1 October 2026 that hot functional testing was under way, that cold functional testing had been completed in October 2025, and that fuel loading and grid connection were still ahead and targeted within 2026. Neither later step is recorded as achieved. NucNet relayed the testing status on 7 October 2026. IAEA PRIS names Hainan Nuclear Power Company as the unit’s operator and owner; the 2021 NNSA construction license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations bearing nuclear-safety responsibility. CNNC is recorded as the design’s developer.
Key facts
- Design
- ACP100 (Linglong One) (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Reactor vessel of this design
- 10 m tall, 3.35 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 11.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Hainan Nuclear Power Company
- Vendor for linked design
- China National Nuclear Corporation
- Location
- Changjiang Nuclear Power Plant site · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Linglong unit 1 (ACP-100) at the Changjiang nuclear site (CC BY 4.0, derived from GEM's tracker). The export uses one point for the whole Changjiang site, so this is a site-area point. Replaces an earlier hand-rounded point. - Coordinates
- 19.459133, 108.896271 · site-area point (approximate)
- Electrical capacity
- 125 MWe (gross) · scope: module
- Thermal capacity
- 385 MWth (nameplate; basis unspecified)
- Purpose
- Power plant
- Construction start
- 13 Jul 2021Linglong-1 construction start (IAEA PRIS)
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: NNSA bureau-document listing: title screen to 2 November 2026. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Linglong One (ACP100) Changjiang is recorded at Changjiang Nuclear Power Plant site, Hainan, China. Operator: Hainan Nuclear Power Company. Recorded vendor: China National Nuclear Corporation. Stage: Commissioning. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'linglong-nuclear-power-plant-1' (19.459133, 108.896271)
Recorded electrical output is 125 MWe (gross), scope module. Modules planned: 1. Recorded thermal output is 385 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorHainan Nuclear Power Company
- Reactor supplier
- Vendor for the linked designChina National Nuclear Corporation
- Contractor
Source-backed project statement A September 2024 People's Daily app report says CNNC Engineering, CNNC Fifth Construction and CNNC 22 formed a turbine-installation group for Linglong One's generator stator lift. This identifies participants in that installation work; the report does not establish a plant-wide EPC award or contract terms. 全球首堆!“玲龙一号”发电机定子吊装就位_人民日报
- Funding and government decisions
Source-backed project statement The NNSA construction license of 1 July 2021 names CNNC Hainan Nuclear Power Co. as the project's investment and construction entity, responsible for resource provision and management, with Hainan Nuclear Power Co. entrusted with construction management. This identifies responsibility; it does not state a funding amount or establish a disbursement. NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)
Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
- Customer or offtaker
China News Service reported on 1 October 2026 that Linglong One was in hot functional testing and aiming for fuel loading and grid connection within 2026. That report names no buyer or offtake agreement for the unit's power or heat. China News Service: Linglong One hot functional testing (1 October 2026)
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
China News Service's 1 October 2026 report says fuel loading is the next step after Linglong One's hot testing. It does not name the fuel fabricator, a supply contract or a delivery. China News Service: Linglong One hot functional testing (1 October 2026)
- Comparable schedule revision
Comparable schedule revision not established. NucNet's 7 October 2026 report contrasts an earlier 2017 construction-start target with actual construction starting in July 2021. That is performance against a target, not two dated forecasts for the same milestone. The reviewed passage does not establish a comparable target-revision pair. NucNet: Hot Testing Begins At China’s Linglong-1 Small Modular Reactor (7 October 2026)
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Reported · Recorded development
Linglong One reported in hot functional testing - Notice published · Regulatory step
Regulator reviews Linglong One commissioning anomalies - Notice published · Regulatory step
Regulator's Linglong One working group urges pre-fuel-load preparation - Notice published · Regulatory step
China's regulator names key Linglong One review issues - · Recorded development
Linglong One completes cold functional testing
Earlier developments (3)
- · Recorded development
First Linglong One reactor operators licensed - · Construction start
Linglong-1 construction start (IAEA PRIS) - · Construction permission recorded
Construction permission recorded: NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One)
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Reported target: Linglong One fuel loading and grid connection within 2026
Dates on the project record: Planned commercial operation: 2026 (planned); Planned grid connection: 2026 (target).
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One)
Construction permission · Issued / approved · NNSA · decided 1 Jul 2021 · permit 国核安证字第2117号
NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.
Sources: NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. Linglong One is CNNC's ACP100 demonstration unit at the Changjiang nuclear base in Hainan. IAEA PRIS (read 19 October 2026) lists it as LINGLONG-1, under construction, at 385 MWt, 125 MWe gross and 100 MWe net. Its operator and owner is Hainan Nuclear Power Company. NNSA construction license 国核安证字第2117号 was issued on 1 July 2021 and is valid to 30 June 2031. It was granted on the construction application of 中核海南核电有限公司 and 海南核电有限公司, after an inspection of readiness to pour the first nuclear-island concrete. It names both companies as license holders. PRIS gives a construction-license date of 15 July 2019, which conflicts with the license document. The document governs, and the PRIS date stays visible as a discrepancy. PRIS dates construction start to 13 July 2021, and China News Service says construction formally began in July 2021. China News (1 October 2026) reports that civil works are complete, equipment installation is essentially finished and hot functional testing is under way. It says cold functional testing was completed in October 2025. Fuel loading, criticality tests, grid-connected generation and commercial operation are still ahead, with fuel loading and grid connection targeted within 2026. NNSA notices of 5 June and 18 August 2026 urge pre-fuel-load preparation and resolution of commissioning anomalies. No opened source shows a first-fuel-loading approval or an operating license, and PRIS has no operating-license, criticality or grid date. NNSA's unit tables, updated 30 September 2026, list the unit as under construction and not as operating. NucNet reports a CNNC official in December 2025 expecting commercial operation in the first half of 2026. That target has passed without fuel loading. The stored 125 MWe gross and 385 MWt match PRIS. The stored year-precision 2026 commercial-operation plan is kept and remains open: the reported first-half expectation has passed, which does not disprove a year-level plan, and China News places commercial operation after fuel loading, criticality and grid connection without giving it a date. Last checked 19 Oct 2026. China News Service: Linglong One hot functional testing (1 October 2026); NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One); NNSA: Linglong One work group on pre-fuel-load preparation (5 June 2026); NNSA: Linglong One commissioning review meeting (18 August 2026); IAEA PRIS statistics: reactors by country code (China), captured 9 October 2026; NucNet: Hot Testing Begins At China’s Linglong-1 Small Modular Reactor (7 October 2026); NNSA regulated-facility database: operating nuclear power units (updated 30 September 2026); NNSA regulated-facility database: nuclear power units under construction (updated 30 September 2026); NNSA bureau-document listing: title screen to 2 November 2026
What would change this
An NNSA first-fuel-loading approval or operating license for Linglong One, or a PRIS criticality or grid-connection date. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. A 1 October 2026 China News Service report says Linglong One was in hot functional testing, and that after the hot tests the next step is loading nuclear fuel, followed by criticality tests, grid connection and commercial operation, with fuel loading and grid connection targeted for 2026. Fuel loading needs regulatory approval that the reviewed sources do not show as granted, and NNSA was still reviewing open issues in August 2026. NNSA's table updated 30 September 2026 still lists the unit as under construction. Last checked 23 Oct 2026. China News Service: Linglong One hot functional testing (1 October 2026); NNSA: Linglong One commissioning review meeting (18 August 2026); NNSA regulated-facility database: nuclear power units under construction (updated 30 September 2026)
What would change this
NNSA approval of first fuel loading, or a report that fuel loading has begun. Next scheduled check: 23 Jan 2027.
- Permissions and public process. NNSA issued construction license No. 2117 for the Changjiang multipurpose small modular reactor demonstration on 1 July 2021, valid to 30 June 2031, after the ecology ministry approved the construction-stage environmental report the same day. The ministry accepted the operation-stage environmental report for review on 2 January 2025. NNSA's review group was still working through unclosed review issues in August 2026; no operating license or fuel-loading approval is shown in the sources reviewed. Last checked 23 Oct 2026. NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One); 关于海南昌江多用途模块式小型堆科技示范工程环境影响报告书(建造阶段)的批复 (环审〔2021〕54号); 生态环境部关于2025年1月2日建设项目环境影响评价文件受理情况的公示(核与辐射); NNSA: Linglong One commissioning review meeting (18 August 2026)
What would change this
An NNSA notice granting the first fuel-loading approval or operating license for the Changjiang demonstration unit. Next scheduled check: 23 Jan 2027.
- Site dependencies (land, grid, water). The 2021 construction license and environmental approval place the unit at former Tangxing village, Haiwei town, Changjiang County, north-west of the Changjiang nuclear plant, and the approval requires building or upgrading facilities shared with the Hainan nuclear base. A 1 October 2026 China News Service report says fuel loading and grid connection are targeted within 2026. Grid connection is a target, and the interconnection and cooling-water arrangements are not described in the sources reviewed. Last checked 23 Oct 2026. NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One); 关于海南昌江多用途模块式小型堆科技示范工程环境影响报告书(建造阶段)的批复 (环审〔2021〕54号); China News Service: Linglong One hot functional testing (1 October 2026)
What would change this
A grid-connection announcement or published environmental/site document describing interconnection and cooling arrangements. Next scheduled check: 23 Jan 2027.
- Spent fuel, waste and closure. The ecology ministry's July 2021 approval of the construction-stage environmental report requires the owners to implement the plan for disposing of radioactive solid waste and to push forward its final disposal, and to complete facilities shared with the Hainan nuclear base. The approval does not set out the spent fuel storage or management route, and the operation-stage environmental report accepted in January 2025 was not among the sources reviewed. Last checked 23 Oct 2026. 关于海南昌江多用途模块式小型堆科技示范工程环境影响报告书(建造阶段)的批复 (环审〔2021〕54号); 生态环境部关于2025年1月2日建设项目环境影响评价文件受理情况的公示(核与辐射)
What would change this
Approval of the operation-stage environmental report or an NNSA license condition setting spent fuel management for Linglong One. Next scheduled check: 23 Apr 2027.
Evidence dates
(8 of 18 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(18)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- IAEA Power Reactor Information System (PRIS) (IAEA/NEA, accessed 1 Oct 2026)
- World Nuclear Association — Small Nuclear Power Reactors (directory or tracker, accessed 1 Oct 2026)
- NNSA: Linglong One review issues (16 March 2026) (regulator, published 16 Mar 2026, accessed 6 Oct 2026)
- NNSA: Linglong One work group on pre-fuel-load preparation (5 June 2026) (regulator, published 5 Jun 2026, accessed 6 Oct 2026)
- NNSA: Linglong One commissioning review meeting (18 August 2026) (regulator, published 18 Aug 2026, accessed 6 Oct 2026)
- National Energy Administration: China Nuclear Power Development Report 2026 (July 2026) (government, accessed 6 Oct 2026)
- IAEA PRIS statistics: reactors by country code (China), captured 9 October 2026 (IAEA/NEA, accessed 17 Oct 2026)
- NucNet: Hot Testing Begins At China’s Linglong-1 Small Modular Reactor (7 October 2026) (news report, accessed 9 Oct 2026)
- China News Service: Linglong One hot functional testing (1 October 2026) (news report, published 1 Oct 2026, accessed 15 Oct 2026)
- NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One) (regulator, dated 1 Jul 2021, accessed 17 Oct 2026)
- NEA Small Modular Reactor Dashboard — Third Edition (2025) (IAEA/NEA, accessed 2 Oct 2026)
- 全球首堆!“玲龙一号”发电机定子吊装就位_人民日报 (news report, published 15 Sep 2024, accessed 21 Oct 2026)
- 关于海南昌江多用途模块式小型堆科技示范工程环境影响报告书(建造阶段)的批复 (环审〔2021〕54号) (government, published 1 Jul 2021, accessed 23 Oct 2026)
- 生态环境部关于2025年1月2日建设项目环境影响评价文件受理情况的公示(核与辐射) (government, published 6 Jan 2025, accessed 23 Oct 2026)
- NNSA regulated-facility database: operating nuclear power units (updated 30 September 2026) (regulator, page updated 30 Sep 2026, accessed 4 Nov 2026)
- NNSA regulated-facility database: nuclear power units under construction (updated 30 September 2026) (regulator, page updated 30 Sep 2026, accessed 4 Nov 2026)
- NNSA bureau-document listing: title screen to 2 November 2026 (regulator, accessed 4 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Linglong One (ACP100) Changjiang — https://smrmap.com/projects/linglong-one-changjiang/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Linglong One (ACP100) Changjiang”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/linglong-one-changjiang/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.