VBER-300
VBER-300 is JSC Afrikantov OKBM's multipurpose pressurized water reactor, evolved from modular marine propulsion reactors. It is intended for land-based plants, cogeneration plants and transportable floating plants.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
- Projects
- No live project recorded here; 1 suspended (VBER-300 nuclear plant project near Aktau, Mangystau). Development status as stated in the catalog dated 18 Oct 2024: Licensing stage.
- Evidence
- 3 sources; first primary source: ARIS original status report — VBER-300 (2024-10-18). Record reviewed 2 Oct 2026.
Key facts · Tracked projects · Sources · Evidence · Its projects in the table · Compare with other designs
Catalog identity snapshot: 18 Oct 2024 (ARIS report publication). Later technical descriptions, where recorded, are dated separately below. Source review does not establish current availability or a deployment.
Key facts
- Class
- SMR
- Technology
- Pressurized water reactor (PWR)
The 2024 SMR Technology Catalogue labels the VBER-300 an integral PWR, while its description and the IAEA's 2020 SMR booklet describe steam-generator and pump vessels and a primary loop connected directly to the reactor vessel; with these conflicting descriptions, the type is recorded as a pressurized water reactor without an integral claim. - Coolant
- Light water
- Spectrum
- Thermal
- Developer / vendor(s) as of 18 Oct 2024
- Afrikantov OKBM
- Fuel form
- UO2
- Development status (as stated)
- Licensing stage
- Reactor vessel
- 9.3 m tall, 3.9 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 171.overall height diameter basis not stated verified against section 25: overall height 9.3 m and diameter 3.9 mSMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.All vessels to scale10 m bar; a person 1.8 m tallVBER-300 *
9.3 m tall, 3.9 m across - Inclusion basis
- SMR by design class
- Confidence
- medium
- Not yet recorded
- Expected but not recorded as a structured fact: Module rating. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Record reviewed
- 2 Oct 2026 (record review date, not proof of current availability or a deployment)
All fields
(2 without a known value)
- Module electrical
- Not recorded
- Module thermal
- Not recorded
Tracked deployment projects
- VBER-300 nuclear plant project near Aktau, Mangystau (2006) — Suspended · Kazakhstan
Design sources
(3)
- ARIS original status report — VBER-300 (2024-10-18) (IAEA/NEA, accessed 2 Oct 2026)
- Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition) (IAEA/NEA, published Jun 2025, accessed 2 Oct 2026)
- IAEA, Advances in Small Modular Reactor Technology Developments (2020 edition) (IAEA/NEA, accessed 3 Oct 2026)
Evidence and open questions
(3 notes)
- Evidence review. The IAEA Small Modular Reactor Technology Catalogue, 2024 edition (third edition printed June 2025, material supplied by Afrikantov OKBM), names JSC Afrikantov OKBM (Rosatom) as developer of the VBER-300 and lists it as an integral PWR with light-water coolant and moderator at 917 MW(t) and 325 MW(e). It describes a multipurpose medium-sized power reactor, evolved from marine propulsion reactors, for land-based plants, cogeneration plants and floating plants, with a rated electric power of 325 MW per reactor and a reference two-unit plant of 600 MW(e); the basis of either electrical figure is not stated. On status, the catalog says final design documentation can start on a customer's request and would take 36 months to reach a construction license application, so no license exists in that edition. Its milestone list records feasibility and investment studies of a VBER-300 plant for the Mangistau Region of Kazakhstan, which matches the linked Aktau project, and the ARIS report (published 18 October 2024) classifies the spectrum as thermal. Stored vendor, light-water coolant and thermal spectrum stay supported; the stored family is PWR rather than the catalog's 'Integral PWR', for the conflict set out in the technology-family review, and the catalog's rating is not stored on this identity profile. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); ARIS original status report — VBER-300 (2024-10-18)
What would change this
A customer order or regulator filing for a VBER-300 plant (for example a renewed Kazakhstan project), or a newer IAEA catalog edition, stating the per-unit gross or net rating and licensing stage. Next scheduled check: 19 Jan 2027.
- Module rating. The 2024 IAEA SMR Technology Catalogue (third edition, June 2025) gives VBER-300 917 MW(t) and a rated electric power of 325 MW per reactor, without a gross or net basis. This record is one of the dated catalog identity profiles that, by the project's standing rule and its regression test, carry no rating until a current technical primary for the same version is reviewed; the figure is therefore not stored. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition)
What would change this
An Afrikantov OKBM or Rosatom technical document stating whether 325 MW(e) is gross or net (the two-unit plant's 600 MW(e) suggests a different basis), which would qualify the electrical rating. Next scheduled check: 19 Jan 2027.
- Technology family. The 2024 SMR Technology Catalogue labels the VBER-300 an integral PWR, while its description and the IAEA's 2020 SMR booklet describe steam-generator and pump vessels and a primary loop connected directly to the reactor vessel; with these conflicting descriptions, the type is recorded as a pressurized water reactor without an integral claim. Last checked 1 Nov 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); IAEA, Advances in Small Modular Reactor Technology Developments (2020 edition)
What would change this
A developer, regulator or IAEA document that states this design's primary-circuit layout. Next scheduled check: 1 Feb 2027.