Projects / Romania · Announced
ALFRED lead-cooled demonstrator at Mioveni (EAGLES-300 program)
Planned ALFRED lead-cooled demonstrator at Mioveni, associated with development of the separate commercial EAGLES-300 design.
Current status
- How current
- General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 20 Aug 2021. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- Planned step: 2031 (target). ALFRED: RATEN roadmap target for siting permit. This is not an achieved milestone. Source: RATEN presentation on ALFRED, IAEA LFR workshop 2026.
- Selected limitations
- Electrical output is not recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The existing approximate 300 MWth plant figure is not an electrical rating. RATEN's 2026 roadmap targets a siting permit in 2031, construction permit in 2032, commissioning permit in 2036 and operation in 2037. These are targets, not issued permissions. Electrical output has not been established for the project configuration; that does not mean it is heat-only.
Key facts
- Design
- ALFRED lead-cooled fast-reactor demonstrator (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead
- Operator(s)
- RATEN
- Vendor for linked design
- —
- Location
- RATEN ICN Mioveni nuclear platform · Romania · precision: town or locality only
Town point from the Wikipedia article for Mioveni; the sources name the RATEN ICN nuclear platform at Mioveni, near Pitești. No parcel point is published, so this is a town-level point. - Coordinates
- 44.95694, 24.94056 · town-level point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- 300 MWth (nameplate; basis unspecified)
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
ALFRED lead-cooled demonstrator at Mioveni (EAGLES-300 program) is recorded at RATEN ICN Mioveni nuclear platform, Argeș, Romania. Operator: RATEN. Recorded vendor: No vendor is recorded. Stage: Announced. Location precision: town or locality only; town-level point (approximate). Other records at this site: Last Energy PWR-20 demonstrator at RATEN Mioveni (2022 plan).
Coordinate source: Wikipedia: Mioveni (article coordinates), Article coordinate 44.95694, 24.94056 on 'Mioveni', read 30 October 2026
Electrical output is not recorded on this project. Modules planned: 1. Recorded thermal output is 300 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorRATEN
- Contractor
Source-backed project statement The World Nuclear Association Romania profile, updated 13 August 2026, says ENEA, Ansaldo Nucleare and Romania's ICN set up the Fostering Alfred Construction (Falcon) consortium in December 2013 for building ALFRED at ICN's Mioveni facility. ENEA's August 2021 journal article confirms ENEA's membership of FALCON with Ansaldo Nucleare and RATEN-ICN. This is a development consortium, not an awarded construction contract, and RATEN's roadmap still targets a construction permit in 2032. WNA: Nuclear power in Romania; ENEA: Overview on Lead-Cooled Fast Reactor Design and Related Technologies Development in ENEA
- Fuel
- Fuel form stated for ALFRED lead-cooled fast-reactor demonstrator (catalog profile as of 20 Aug 2021)MOX
The World Nuclear Association Romania profile, updated 13 August 2026, says the ALFRED design would use mixed-oxide fuel with about 17 percent plutonium. That is a design fuel description. The profile, RATEN's 2026 workshop slides and ENEA's 2021 article name no fuel fabricator, allocation or delivery for ALFRED. WNA: Nuclear power in Romania
Not found in the sources we checked (3): Customer or offtaker; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
The World Nuclear Association Romania profile, updated 13 August 2026, says RATEN's research institute ICN will host the ALFRED demonstrator at Mioveni. A host is not a buyer, and the profile names no recipient of ALFRED's power or heat. Its reference to a later industrial unit of about 600 MWe describes a successor concept, not a customer. WNA: Nuclear power in Romania
- Funding and government decisions
The World Nuclear Association Romania profile, updated 13 August 2026, puts ALFRED's total cost at some 1.0 billion euros, which is an estimate, not financing. It also reports a 20 million euro ATHENA contract (2021), a 112 million euro 4ALFRED program for four test facilities (announced March 2025) and a 36 million euro RATEN contract for HELENA-2 and ELF test facilities (early 2026). These support facilities are not the reactor, and the profile names no funder or instrument for ALFRED itself. WNA: Nuclear power in Romania
- Comparable schedule revision
Comparable schedule revision not established. RATEN ICN's slides for a 2026 IAEA lead-cooled reactor workshop give one ALFRED roadmap: design certification 2030, siting permit 2031, construction permit 2032, commissioning permit 2036 and operation 2037. The slides read do not set out an earlier date for any of these milestones, so they show targets, not a revision. The slide file prints no cover date. RATEN presentation on ALFRED, IAEA LFR workshop 2026
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
ALFRED: RATEN roadmap target for siting permit - Target · Planned step
ALFRED: RATEN roadmap target for construction permit - Target · Planned step
ALFRED: RATEN roadmap target for commissioning permit - Target · Planned step
ALFRED: RATEN roadmap target for operation
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes, 1 not yet reviewed)
- Evidence review. World Nuclear Association's Romania profile says the Institute for Nuclear Research Pitesti (ICN), the R&D subsidiary of RATEN, is responsible for Romanian involvement in ALFRED and will host it, and that ALFRED will be built at ICN's facility in Mioveni, near Pitesti. RATEN's 2026 workshop slides show an ALFRED roadmap with design certification in 2030, a siting permit in 2031, a construction permit in 2032, a commissioning permit in 2036 and an operational phase in 2037; the slide spells the siting permit 'Sitting Permit'. Those are targets on a roadmap, not issued permits. A 2021 ENEA paper calls ALFRED a prototype for a commercial SMR. WNA puts the project cost at some €1.0 billion. Electrical output is not stated in these passages. The stored ALFRED design, 300 MWth figure, one module and announced stage are not contradicted by the passages used here; the 300 MWth figure was not re-read in these quotes. The NEA dashboard returned an access refusal (HTTP 403) and the EAGLES-300 homepage failed on the TLS handshake, so neither was read. Last checked 19 Oct 2026. WNA: Nuclear power in Romania; RATEN presentation on ALFRED, IAEA LFR workshop 2026; ENEA: Overview on Lead-Cooled Fast Reactor Design and Related Technologies Development in ENEA
What would change this
A CNCAN siting or construction application for ALFRED at Mioveni, or a RATEN decision that replaces the 2031-2037 roadmap, would change this record. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. WNA says ALFRED will be built at ICN's facility in Mioveni, near Pitesti. No coordinates are given. Last checked 19 Oct 2026. WNA: Nuclear power in Romania
What would change this
A siting application with a plot plan would allow a finer location. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. On RATEN's 2026 roadmap the next licensing steps are design certification, targeted for 2030, and a siting permit, targeted for 2031, after a pre-licensing phase to 2027. These are targets, and the presentation does not name the decision-maker's schedule or funding for construction. Last checked 23 Oct 2026. RATEN presentation on ALFRED, IAEA LFR workshop 2026
What would change this
A CNCAN design or siting decision, or a revised RATEN roadmap. Next scheduled check: 21 Jan 2027.
- Permissions and public process. RATEN's 2026 roadmap for ALFRED shows a pre-licensing phase running from 2017 to 2027, then targets design certification in 2030, a siting permit in 2031, a construction permit in 2032 and a commissioning permit in 2036. These are planned milestones; no permit has been issued, and the presentation describes no public consultation. Last checked 23 Oct 2026. RATEN presentation on ALFRED, IAEA LFR workshop 2026
What would change this
A CNCAN decision or a published siting-permit application for ALFRED. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). RATEN's 2026 presentation sites the supporting experimental facilities on the Mioveni nuclear platform, using existing buildings and space, and plans a siting permit for ALFRED itself in 2031. It describes no land, grid or cooling arrangement for the demonstrator. Last checked 23 Oct 2026. RATEN presentation on ALFRED, IAEA LFR workshop 2026
What would change this
A siting-permit application or environmental assessment for ALFRED at Mioveni. Next scheduled check: 21 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(1 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- NEA SMR Digital Dashboard edition 4.0 (per-design siting entries) (IAEA/NEA, accessed 2 Oct 2026)
- EAGLES-300 (company, accessed 2 Oct 2026)
- RATEN presentation on ALFRED, IAEA LFR workshop 2026 (company, accessed 13 Oct 2026)
- WNA: Nuclear power in Romania (directory or tracker, accessed 2 Oct 2026)
- ENEA: Overview on Lead-Cooled Fast Reactor Design and Related Technologies Development in ENEA (peer-reviewed, published 20 Aug 2021, accessed 13 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: ALFRED lead-cooled demonstrator at Mioveni (EAGLES-300 program) — https://smrmap.com/projects/alfred-mioveni/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “ALFRED lead-cooled demonstrator at Mioveni (EAGLES-300 programme)”. Record reviewed 13 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/alfred-mioveni/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.