Projects / Russia · Canceled
Dimitrovgrad SVBR-100 pilot proposal (2013 land lease)
AKME-Engineering's 2013 proposal for a pilot SVBR-100 lead-bismuth fast reactor at Dimitrovgrad, Russia, is recorded as canceled on the World Nuclear Association's account.
Current status
- How current
- General record check . Bounded evidence review . 2 of 5 listed sources have a publication or document date recorded here; the newest is 2024. A listed page was last updated 28 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
World Nuclear News reported an 18 June 2013 AKME-Engineering land lease adjacent to RIAR in Dimitrovgrad for the pilot unit. The World Nuclear Association's Russia profile says that "in 2018 the project had been dropped". That reference profile is the only basis for the canceled stage: Global Energy Monitor's catalog gives the same 2018 year but cites a September 2022 archived copy of that same profile, and no Rosatom or AKME decision document or exact date was found. The developer's own later paper does not describe the project as ended. AKME-Engineering's paper for the IAEA's October 2024 conference on small modular reactors says development of the SVBR-100 reactor design for a first plant is under way, and that the paper draws on the first-plant design developed for the Dimitrovgrad site. It also says the cost of building the first plant was clarified in 2019, that further research and development is planned, and that the 2015 siting license must be renewed. It gives no construction or investment date. The two accounts conflict, and the stage follows the reference profile's explicit statement until a Rosatom or AKME statement settles it. Kept distinct from MBIR progress at the same institute campus.
Key facts
- Design
- SVBR-100 (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead bismuth
- Operator(s)
- Not recorded
- Vendor for linked design
- AKME-engineering JSC
- Location
- Dimitrovgrad · Russia · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate coordinates of the named Dimitrovgrad / RIAR-adjacent SVBR-100 pilot proposal from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker). Project names Dimitrovgrad; lease is adjacent to RIAR. Exact pad layout unknown. Same point as GEM public map layer (August 2026) feature L100000500284 (approx 54.1866, 49.4793); workbook/NOTICE not retrieved. Only the coordinates were taken from this layer; the project's stage is recorded on the project page from its own sources. - Coordinates
- 54.1866, 49.4793 · site-area point (approximate)
- Electrical capacity
- 100 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Dimitrovgrad SVBR-100 pilot proposal (2013 land lease) is recorded at Dimitrovgrad, Ulyanovsk, Russia. Operator: No operator is recorded. Recorded vendor: AKME-engineering JSC. Stage: Canceled. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'dimitrovgrad-nuclear-power-plant-1' (54.1866, 49.4793)
Recorded electrical output is 100 MWe (gross/net unspecified), scope plant. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designAKME-engineering JSC
- Fuel
- Fuel form stated for SVBR-100 (catalog profile as of 15 Oct 2024)UO2 - FOAK; UO2 / (U-Pu)O2 / (U Pu)N / (U-Pu)C - NOAK
AKME-engineering's 28 April 2014 environmental impact assessment, book 5, says emergency centers must exist before nuclear fuel is brought to the SVBR-100 site, but names no supplier, fabricator or delivery. World Nuclear News of 18 June 2013 describes the lead-bismuth coolant, not fuel supply. AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
World Nuclear News of 18 June 2013 says the SVBR-100 module could supply heat, industrial steam, desalination and electricity, and a regional official refers to an unnamed project customer that would own the finished unit. AKME-engineering's 28 April 2014 environmental impact assessment, book 5, names no buyer or consumer. No recipient, quantity or agreement for the Dimitrovgrad pilot's output is stated. WNN: Land secured for SVBR-100 pilot at Dimitrovgrad
- Contractor
World Nuclear News of 18 June 2013 says AKME-Engineering, the Rosatom-founded developer of the SVBR-100, leased the Dimitrovgrad plot and had just received a license to provide construction services, and the 28 April 2014 environmental impact assessment is issued in AKME's name. AKME is the developer acting for itself. No separate engineering or construction contractor is named. The sources read for this review did not establish what later became of the pilot; the World Nuclear Association's Russia profile, read afterwards, says that "in 2018 the project had been dropped". WNN: Land secured for SVBR-100 pilot at Dimitrovgrad; AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
- Funding and government decisions
World Nuclear News of 18 June 2013 describes a ten-year lease of a 15-hectare plot and AKME-Engineering's commitments to build an access road and two concrete plants, without any cost or rent. AKME-engineering's 28 April 2014 environmental impact assessment, book 5, states no investment, financing or budget for the pilot. No amount or funder is stated. WNN: Land secured for SVBR-100 pilot at Dimitrovgrad
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News of 18 June 2013 reported AKME's plan to start up the pilot in late 2018, and AKME's 28 April 2014 environmental impact assessment gives preparation in 2015 to 2016 and construction in 2016 to 2019. The later document dates construction, not startup, so the two do not state the same milestone. No source read gives a revised startup date. The 2018 year in the World Nuclear Association's profile, and in Global Energy Monitor's catalog, which cites that profile, is when they say the project ended, not a schedule statement. WNN: Land secured for SVBR-100 pilot at Dimitrovgrad; AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014; GEM Global Nuclear Power Tracker public map ? Dimitrovgrad
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. AKME-engineering's own environmental impact assessment, book 5, dated 28 April 2014, is the EIA for a pilot industrial unit with a fast-neutron lead-bismuth reactor in Ulyanovsk oblast. The contents name that unit as OP EB with reactor installation SVBR-100. Reference 98 inside the same book is the 20 November 2013 state expert conclusion on engineering surveys for construction of that unit in Melekessky district of Ulyanovsk oblast (Dimitrovgrad). The book also places the SVBR-100 site inside the sanitary-protection zone of GNTs NIIAR. This is the company document for the stored Dimitrovgrad pilot. The 2013 lease text was not in this book. A cited license-justification title says 100 MWt without stating electrical or thermal, so the stored 100 MWe is not confirmed or replaced. No operator is added. GEM's operator column stays directory text. This review also left GEM's 2018 cancellation cell as directory text; the canceled stage now recorded rests on the World Nuclear Association's Russia profile, updated 28 October 2026 and read after this review. The broad last-checked date stays 2026-10-02. Last checked 20 Oct 2026. WNN: Land secured for SVBR-100 pilot at Dimitrovgrad; GEM Global Nuclear Power Tracker public map ? Dimitrovgrad; AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
What would change this
A Rosatom or AKME status note that confirms or contradicts the 2018 end of the project stated by the World Nuclear Association (Global Energy Monitor's 2018 cancellation cell cites that same profile). Next scheduled check: 20 Jan 2027.
- Primary source. The 28 April 2014 EIA is AKME-engineering's document for this lead-bismuth pilot and names SVBR-100 and Dimitrovgrad. Attaching it fills the primary-source predicate. World Nuclear News and Global Energy Monitor stay press and directory sources. No field edit is proposed because the source register is not a side-path field. Last checked 20 Oct 2026. AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
What would change this
No further page is required to identify this EIA. A later status note would be a separate instrument. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites: Not applicable. The World Nuclear Association's Russia profile, updated 28 October 2026, says the pilot SVBR-100 unit was planned next to RIIAR Dimitrovgrad by AKME-engineering and that in 2018 the project had been dropped, so no next decision is pending for this proposal. AKME-Engineering's paper for the IAEA's October 2024 conference on small modular reactors says the 2015 siting license must be renewed and lists further research planned before a first SVBR-100 plant, without a construction or investment date. No Rosatom or AKME decision ending the project, or its exact date, was found. Last checked 9 Nov 2026. World Nuclear Association: Nuclear Power in Russia (SVBR-100 described as dropped); AKME-Engineering: SVBR-100 project key features and current state (IAEA SMR conference paper, 2024)
What would change this
A Rosatom or AKME statement that revives or formally ends the Dimitrovgrad SVBR-100 project, or a renewal of its siting license. Next scheduled check: 9 May 2027.
- Permissions and public process. An AKME-Engineering paper for the IAEA's October 2024 conference on small modular reactors says Rostekhnadzor issued a siting license for the first SVBR-100 plant at Dimitrovgrad in 2015, and that the license now has to be renewed. AKME's April 2014 environmental impact assessment for the pilot unit lists public-discussion materials in a separate volume, which was not among the sources reviewed. These sources show no construction license. Last checked 23 Oct 2026. AKME-Engineering: SVBR-100 project key features and current state (IAEA SMR conference paper, 2024); AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
What would change this
A Rostekhnadzor renewal of the Dimitrovgrad SVBR-100 siting license or a construction license application. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). World Nuclear News reported on 18 June 2013 that AKME-Engineering agreed to lease a 15-hectare plot adjacent to the Research Institute of Atomic Reactors in Dimitrovgrad for the pilot SVBR-100, with the lease valid for ten years and a new lease needed once the plant was built. AKME also committed to a 3 km access road. A ten-year lease from 2013 would have run to about 2023; these sources do not say whether it was renewed or describe grid or water arrangements. Last checked 23 Oct 2026. WNN: Land secured for SVBR-100 pilot at Dimitrovgrad
What would change this
A record of renewal or termination of the Dimitrovgrad land lease, or a renewed siting license. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. AKME-Engineering's April 2014 environmental impact assessment for the pilot SVBR-100 unit says that, after final shutdown, spent fuel would be unloaded into an on-site chamber-type spent-fuel store and then sent for reprocessing, and that radioactive waste must be removed and transferred to the national radioactive-waste operator under Russian law. This is the 2014 design plan for a unit that was never built; no reprocessing contract or decommissioning fund is described. Last checked 23 Oct 2026. AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014
What would change this
A renewed AKME or Rosatom licensing document for the Dimitrovgrad unit describing spent-fuel management. Next scheduled check: 23 Apr 2027.
Evidence dates
(2 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- WNN: Land secured for SVBR-100 pilot at Dimitrovgrad (news report, accessed 2 Oct 2026)
- GEM Global Nuclear Power Tracker public map ? Dimitrovgrad (directory or tracker, accessed 2 Oct 2026)
- AKME-engineering: SVBR-100 Ulyanovsk EIA, book 5, 28 April 2014 (company, dated 28 Apr 2014, accessed 20 Oct 2026)
- AKME-Engineering: SVBR-100 project key features and current state (IAEA SMR conference paper, 2024) (company, published 2024, accessed 23 Oct 2026)
- World Nuclear Association: Nuclear Power in Russia (SVBR-100 described as dropped) (directory or tracker, page updated 28 Oct 2026, accessed 9 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Dimitrovgrad SVBR-100 pilot proposal (2013 land lease) — https://smrmap.com/projects/dimitrovgrad-svbr100/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Dimitrovgrad SVBR-100 pilot proposal (2013 land lease)”. Record reviewed 2 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/dimitrovgrad-svbr100/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.