Shandong Haiyang integrated small reactor demonstration project (heat only)
SPIC Nuclear Energy's Haiyang integrated small reactor is a 200 MWt heat-only demonstration at the Haiyang nuclear power plant in Shandong, China, at the siting stage.
Current status
- How current
- Record checked · Evidence reviewed · Next recheck due
Development and review dates
Newest recorded development . None of the 5 listed sources has a publication or document date recorded here. Status not rechecked since the record check; this project is not covered by the nightly status check. Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration (10 Sep 2024). All permissions and applications
- Latest development
- 10 Sep 2024 · Recorded development: Haiyang integrated small reactor: regulator siting review opinion issued. NNSA issued site-selection review opinion No. 2414; a siting opinion, not a construction license. Source: NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024). Updates entry
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Not yet recorded for this stage: Design identified (not stated in the sources read). Not recorded does not mean zero or that none exists; the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The National Nuclear Safety Administration's site-selection review opinion No. 2414 of 10 September 2024 covers one 200 MWt integrated, natural-circulation small pressurised-water reactor without main pipes or main coolant pumps in the south-west corner of the Haiyang plant, owned by SPIC Nuclear Energy and built and operated by Shandong Nuclear Power; the siting-stage environmental assessment (accepted November 2023, proposed approval August 2024) describes industrial steam of up to 250 t/h, heat for thermal desalination and standby district heat. The regulator's siting opinion reviews it under its small reactor (小型堆) framework, the term China's regulator uses for small modular reactors, including the Linglong One (ACP100) unit that its under-construction table lists as a small reactor demonstration project, and its September 2026 interpretation of the technical opinion on small nuclear power reactors sets 300 MWt as the light-water limit that this 200 MWt plant falls within. That regulator classification is the basis for inclusion; the integral natural-circulation layout is a design feature, not the qualification, and no document opened here states factory fabrication. The thermal output is not the basis. The siting opinion is not a construction license, and no construction-stage assessment or license had been issued by September 2026. The design brand is not stated in the documents, so no design profile is linked; a relationship to HAPPY200 is unverified.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- SPIC Nuclear Energy Co., Shandong Nuclear Power Co.
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Haiyang nuclear power plant, south-west corner · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate NuclearChain export point for the Haiyang nuclear power plant (derived from GEM's tracker); the small reactor sits in the south-west corner of the same plant per the regulator's siting review opinion. - Coordinates
- 36.708698, 121.377983 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- 200 MWth (nameplate; basis unspecified)
- Record reviewed
- 6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Shandong Haiyang integrated small reactor demonstration project (heat only) is recorded at Haiyang nuclear power plant, south-west corner, Shandong, China. Operator: SPIC Nuclear Energy Co., Shandong Nuclear Power Co.. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'haiyang-nuclear-power-plant-1-1' (36.708698, 121.377983)
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 200 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorSPIC Nuclear Energy Co.
- OperatorShandong Nuclear Power Co.
- Customer or offtaker
Source-backed project statement The 2023 siting-stage environmental report says the 200 MWt reactor would mainly supply industrial steam to outside users, provide heat for thermal desalination at Haiyang units 5 and 6, and serve as a standby winter heat source for Haiyang city. The desalination and plant-site uses belong to the owner's own Haiyang station, and the city heating role is standby. The industrial steam buyers are not named and no supply agreement is stated. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
- Contractor
Source-backed project statement The Ministry of Ecology and Environment's August 2024 notice of proposed approval names Shanghai Nuclear Engineering Research and Design Institute as the environmental assessment body for the siting-stage report, a preparatory licensing role. The report says SPIC Nuclear Energy owns the project and has commissioned Shandong Nuclear Power to manage construction and operation, which are the recorded operator roles. No construction contractor is named, and the NNSA siting opinion bars safety-related construction before a construction license. MEE: proposed approval of the Haiyang integrated small reactor siting-stage environmental impact report (23 August 2024); MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project; NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024)
- Funding and government decisions
Source-backed project statement The 2023 siting-stage environmental report says SPIC Nuclear Energy, as investor and owner, provides the resources for construction and operation, including funding, oversight and final economic responsibility. The Ministry of Ecology and Environment's August 2024 notice puts environmental-protection investment at 93.6 million yuan, 3.4% of total investment, without stating the total. No investment approval or financing close is reported. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
- Fuel
- Project fuel information is described in the source-backed statement below.
Source-backed project statement The 2023 siting-stage environmental report says the first core and reload fuel assemblies will be supplied by SPIC Uranium Industry Development, which may commission CNNC Baotou Nuclear Fuel Element or CNNC Jianzhong Nuclear Fuel to fabricate them, with road transport from either plant. This is a planned supply arrangement described in a regulatory filing, with no contract, quantity or delivery date stated. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
Not found in the sources we checked (1): Comparable schedule revision
- Comparable schedule revision
Comparable schedule revision not established. The 2023 siting-stage environmental report gives a 48-month construction period and a 60-year design life, and says the actual start depends on the state's approval of construction. The NNSA's 10 September 2024 siting opinion sets no date. No dated construction or operation target is stated, so no revision is shown. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Haiyang integrated small reactor: regulator siting review opinion issued - · Site permission recorded
Site permission recorded: NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration
Site permission · Issued / approved · NNSA · decided 10 Sep 2024
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2414号) on 10 September 2024 for one 200 MWt integrated natural-circulation small PWR and auxiliary facilities at the southwest corner of the Haiyang nuclear plant site. The opinion agrees that design work may proceed on the stated site parameters.
Sources: NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024)
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. The National Nuclear Safety Administration's notice of 10 September 2024 (国核安发〔2024〕163号), addressed to SPIC Nuclear Energy and Shandong Nuclear Power, issues site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project after finding no disqualifying site factors, and forbids safety-related construction or foundation concrete before a construction license. The siting-stage environmental report (2023) describes one 200 MWt integrated small reactor on the Haiyang plant's land, in the south-west corner of the site, supplying up to 250 t/h of industrial steam, heat for thermal desalination at units 5 and 6 and standby winter heating. The report says SPIC Nuclear Energy is the investor and owner and Shandong Nuclear Power is commissioned to manage construction and operation and bears responsibility for safe construction and operation. The ministry's notice of proposed decisions dated 23 August 2024 covers that siting-stage report. No design brand is named, and the report states that construction scale and reactor-type selection are ultimately subject to the state's approval opinion (gloss of '具体建设规模和堆型选择最终以国家核准意见为准'). The next documentary decisions are state approval of the project and an NNSA construction license with a construction-stage environmental report; the stored 200 MWt, heat-only basis, one unit, owner and operator links, site and siting stage stay, and no design is linked. Last checked 19 Oct 2026. NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024); MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project; MEE: proposed approval of the Haiyang integrated small reactor siting-stage environmental impact report (23 August 2024)
What would change this
The state approval (核准) of the Haiyang small reactor project or an NNSA construction-license application and construction-stage environmental report naming the reactor design. Next recheck due .
- Design identified: Not disclosed in the reviewed evidence. The siting-stage environmental report and NNSA's siting notice describe one 200 MWt integrated natural-circulation small PWR and give no design brand. The report states that construction scale and reactor-type selection are ultimately subject to the state's approval opinion, so the design is not formally fixed in the opened documents. No opened source links HAPPY200 or any other catalog design, and one bounded search found no SPIC or regulator page naming one. Last checked 19 Oct 2026. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
What would change this
The state approval of the project or an NNSA construction-license application and construction-stage EIA naming the reactor design. Next recheck due .
- Next decision and prerequisites. The siting-stage environmental report says the final construction scale and reactor type are subject to the national project approval, and NNSA's September 2024 siting opinion says no safety-related construction may start before a construction license. The next consequential steps are therefore national project approval and an NNSA construction license; neither is shown in the documents reviewed. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project; NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024)
What would change this
A State Council approval or NNSA construction license for the Haiyang integrated small reactor. Next recheck due .
- Permissions and public process. NNSA issued its site-selection review opinion No. 2414 for the Haiyang integrated small reactor demonstration on 10 September 2024, which is a siting approval, not a construction license; it bars safety-related construction or basemat pouring before a construction license. The siting-stage environmental report says the owners ran public notices, questionnaires and forums and that no member of the public opposed the project, and the Ministry of Ecology and Environment published its proposed approval in August 2024. Last checked 23 Oct 2026. NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024); MEE: proposed approval of the Haiyang integrated small reactor siting-stage environmental impact report (23 August 2024); MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
What would change this
An NNSA construction license or State Council project approval for the Haiyang integrated small reactor. Next recheck due .
- Site dependencies (land, grid, water). The 2023 siting-stage environmental report places the reactor in the south-west corner of the existing Haiyang nuclear plant, south of the units 1-2 radwaste area, and says plant-wide land acquisition and site levelling are already complete. It says access roads, the emergency road and the heavy-cargo wharf already exist and several facilities are shared with other units. Final scale and reactor type remain subject to national project approval, and the report does not show signed steam or heat offtake arrangements. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
What would change this
National project approval or a construction-stage environmental report confirming the layout, or a signed heat/steam supply agreement. Next recheck due .
- Spent fuel, waste and closure. The 2023 siting-stage environmental report plans an on-site spent fuel pool with storage racks and says solid radioactive waste will be held at the plant's shared site waste treatment facility for about five years before transport to a national regional disposal site. These are planned arrangements described for licensing, not executed contracts, and the report passages reviewed do not name an off-site destination for spent fuel itself. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project
What would change this
A construction-stage environmental report or license condition setting the spent fuel management route. Next recheck due .
Evidence dates
(0 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024) (regulator, accessed 6 Oct 2026)
- MEE: siting-stage environmental impact report (September 2023), Shandong Haiyang integrated small reactor demonstration project (government, accessed 6 Oct 2026)
- MEE: proposed approval of the Haiyang integrated small reactor siting-stage environmental impact report (23 August 2024) (government, accessed 6 Oct 2026)
- NNSA: interpretation of the technical opinion on small nuclear power reactors (September 2026) (regulator, accessed 6 Oct 2026)
- National Energy Administration: China Nuclear Power Development Report 2026 (July 2026) (government, accessed 6 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Shandong Haiyang integrated small reactor demonstration project (heat only) — https://smrmap.com/projects/haiyang-integrated-small-reactor/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Shandong Haiyang integrated small reactor demonstration project (heat only)”. Record reviewed 6 Oct 2026. https://smrmap.com/projects/haiyang-integrated-small-reactor/ (accessed [date]).
“Record reviewed” is the record review date; the evidence review, individual sources and later additions keep their own dates. Add the date you read the page; save a PDF if you need a copy of it.
Record details