Projects / Poland · Announced
HTGR-POLA research reactor (NCBJ)
Research and demonstration reactor of 30 MW thermal designed by Poland's NCBJ; technical design completed in 2024 and a technical dialogue with the regulator concluded in 2025.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
NEA's 2026 dashboard says NCBJ plans to build it at its Świerk site in Otwock. No license application is established.
Key facts
- Design
- HTGR-POLA (SMR)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Reactor vessel of this design
- 16 m tall, 4.08 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 205.belt line is not stated this is not the June 2025 16.2 / 4.08 belt-line pointSMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- National Centre for Nuclear Research
- Vendor for linked design
- National Centre for Nuclear Research
- Location
- NCBJ Świerk site, Otwock · Poland · precision: site area (named plant, laboratory, base, port, campus or parcel)
OpenStreetMap Nominatim point for 'Narodowe Centrum Badań Jądrowych, Andrzeja Sołtana, Świerk, Otwock' (office/research feature); NCBJ campus point, not a reactor plot. - Coordinates
- 52.12357, 21.340348 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- 30 MWth (nameplate; basis unspecified)
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
HTGR-POLA research reactor (NCBJ) is recorded at NCBJ Świerk site, Otwock, Masovian, Poland. Operator: National Centre for Nuclear Research. Recorded vendor: National Centre for Nuclear Research. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Narodowe Centrum Badań Jądrowych, Andrzeja Sołtana, Świerk, Otwock' (office/research)
Electrical output is not recorded on this project. Modules planned: 1. Recorded thermal output is 30 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerNational Centre for Nuclear Research · source
- Operator or intended licensed owner
- Reactor supplier
- Vendor for the linked designNational Centre for Nuclear Research
- Customer or offtaker
Source-backed project statement NCBJ's 23 September 2024 page says the HTGR-POLA concept would supply industrial heat for a test chemical installation assumed in the project, and electricity and office heating for NCBJ's own Świerk campus. The stated user is therefore NCBJ itself and a project test installation. No outside buyer, contract or quantity is named. NCBJ: HTGR-POLA research reactor designed
- Funding and government decisions
Source-backed project statement NCBJ's 13 October 2025 page says the science ministry approved on 20 May 2025 the final report of the HTGR-POLA technical-description project under Agreement No. 1/HTGR/2021/14 of 12 May 2021, for PLN 60 million. NCBJ's 23 September 2024 page describes that agreement with the ministry for the 2021-2024 design project. This is government funding for design work, not construction funding, and the pages do not state how much was disbursed. NCBJ concluded technical dialogue with PAA on HTGR-POLA
Not found in the sources we checked (3): Contractor; Fuel; Comparable schedule revision
- Contractor
NCBJ's 23 September 2024 and 13 October 2025 pages describe NCBJ's own design work, a 2021-2024 design project agreed with the science ministry, cooperation with the Japan Atomic Energy Agency since November 2022 and technical meetings with the Polish Atomic Energy Agency concluded on 25 September 2025. They name no engineering or construction contractor for HTGR-POLA. JAEA cooperation is a research agreement, not an appointment. NCBJ: HTGR-POLA research reactor designed; NCBJ concluded technical dialogue with PAA on HTGR-POLA
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
NCBJ's 23 September 2024 page says high-temperature reactors like HTGR-POLA use uranium dioxide enriched from a few to a dozen or so percent in TRISO fuel. That is a design description. Neither that page nor the 13 October 2025 page names a fuel manufacturer, quantity or delivery for HTGR-POLA. NCBJ: HTGR-POLA research reactor designed
- Comparable schedule revision
Comparable schedule revision not established. NCBJ's 23 September 2024 page expected the basic design and preliminary safety report in autumn 2024 and gives only durations for later phases, and its 13 October 2025 page reports the design submission in December 2024 and the end of regulator meetings on 25 September 2025. These are different acts, and neither page gives a construction or operation date for HTGR-POLA that could be revised. NCBJ: HTGR-POLA research reactor designed; NCBJ concluded technical dialogue with PAA on HTGR-POLA
Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. NCBJ describes HTGR-POLA as its high-temperature research reactor. A project page says work began on a concept of 30 megawatts thermal that could serve as a demonstrator, and that the 2021-2024 project was to prepare a basic design and a preliminary safety report for a future license application. A 25 September 2025 note says technical dialogue with the Polish Atomic Energy Agency had been held and that a final report was approved on 20 May 2025, including PLN 60 million under a May 2021 agreement for the technical-description project. Possible heat uses include a test chemical installation and the Świerk campus. The NEA dashboard capture is an access refusal (HTTP 403) and was not read, so it is not used for a Świerk construction decision. Last checked 19 Oct 2026. NCBJ: HTGR-POLA research reactor designed; NCBJ concluded technical dialogue with PAA on HTGR-POLA; NEA SMR Digital Dashboard edition 4.0 (per-design siting entries)
What would change this
A Polish Atomic Energy Agency application for HTGR-POLA, or an NCBJ siting decision, would change this record. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. NCBJ says its next step is an application for a general opinion under article 39b of the Polish Atomic Law, followed later by a request for an advance opinion on the planned location or specific project aspects. No dates or construction decision are given. Last checked 23 Oct 2026. NCBJ concluded technical dialogue with PAA on HTGR-POLA
What would change this
An NCBJ or Polish Atomic Energy Agency notice that the general-opinion application was filed or decided. Next scheduled check: 21 Jan 2027.
- Permissions and public process. NCBJ reports that four preliminary technical meetings with the Polish Atomic Energy Agency, held under the agency's pre-application dialogue policy, ended in September 2025. They prepared an application for the agency President's general opinion on the HTGR-POLA technology. Dialogue and a general opinion are not a site, construction or operating permit, and no application is recorded as filed. Last checked 23 Oct 2026. NCBJ concluded technical dialogue with PAA on HTGR-POLA
What would change this
A filed application for, or issued, general or location opinion of the President of the Polish Atomic Energy Agency on HTGR-POLA. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. NCBJ's September 2024 design release and its 2025 release on the technical dialogue with the Polish Atomic Energy Agency describe the HTGR-POLA design, its licensing path and later construction, but neither states where the reactor will be built or describes land, grid, heat-use or cooling arrangements. Last checked 23 Oct 2026. NCBJ: HTGR-POLA research reactor designed; NCBJ concluded technical dialogue with PAA on HTGR-POLA
What would change this
An NCBJ siting announcement, a PAA license application or a site-specific environmental decision for HTGR-POLA. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. NCBJ's 2025 release says its technical dialogue with the Polish Atomic Energy Agency covered fuel and radioactive waste management among other systems, but it does not describe how HTGR-POLA spent fuel or waste would be stored or who would take long-term responsibility. The 2024 design release discusses waste only in general terms. Last checked 23 Oct 2026. NCBJ concluded technical dialogue with PAA on HTGR-POLA
What would change this
A preliminary safety report summary, PAA license application or NCBJ statement on HTGR-POLA spent fuel and waste arrangements. Next scheduled check: 23 Apr 2027.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- NCBJ: HTGR-POLA research reactor designed (company, accessed 2 Oct 2026)
- NCBJ concluded technical dialogue with PAA on HTGR-POLA (company, accessed 2 Oct 2026)
- NEA SMR Digital Dashboard edition 4.0 (per-design siting entries) (IAEA/NEA, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: HTGR-POLA research reactor (NCBJ) — https://smrmap.com/projects/htgr-pola-ncbj/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “HTGR-POLA research reactor (NCBJ)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/htgr-pola-ncbj/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.