Projects / United States · Construction

MARVEL microreactor test bed at INL's TREAT facility

DOE test reactor at INL's Transient Reactor Test Facility: sodium-potassium cooled, with natural-circulation cooling, 85 kW thermal and approximately 10 kW electric, not a commercial plant.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 5 of 11 listed sources have a publication or document date recorded here; the newest is 6 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: DOE finding of no significant impact for MARVEL (DOE/EA-2146) (12 Nov 2021). All permissions and applications
Latest development
Release dated 6 Oct 2026 · Recorded development: INL reports DOE approval of MARVEL's final documented safety analysis. INL says DOE's Idaho Operations Office approved MARVEL's final documented safety analysis just before the primary coolant system arrived at INL in mid-September 2026. Source: INL news release (6 Oct 2026): MARVEL reactor gets federal safety approval as its primary vessel arrives in Idaho. Updates entry
More on this development

INL describes it as a key safety document authorizing a dry criticality configuration at near-zero power with no coolant. Criticality in December is a target; the release does not report achieved criticality.

Next dated milestone
Planned step: 2026 (target). MARVEL assembly expected to finish. This is not an achieved milestone. Source: DOE Office of Nuclear Energy: MARVEL microreactor project page.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Construction start evidence (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

DOE's Idaho Operations Office issued a finding of no significant impact on 12 November 2021 (DOE/EA-2146); that is an environmental finding, not a safety authorization. DOE's project page, read on 5 October 2026, expects assembly to finish in 2026, installation in TREAT to start late in 2026, dry initial criticality in 2027 and full-power operation in 2028. It says the first stage is electricity and a second stage, likely in 2029, is process heat, with operation currently expected from 2028 to 2030. Those are targets, and late 2026 is not stored as a quarter. INL's release of 11 March 2026 instead describes MARVEL as producing 85-100 kWth and approximately 20 kW of electricity; SMRMap's stored ratings (0.085 MWth and 0.01 MWe) follow DOE's MARVEL project page, chosen because it is DOE's own program description of this test bed and gives single values; INL's 85-100 kWth and approximately 20 kW are disclosed here and not stored. Neither quoted capacity statement specifies whether the electrical figure is gross or net, so the basis stays unspecified, and the two descriptions have not been reconciled. INL releases of 11 March and 6 October 2026 say DOE's Idaho Operations Office approved MARVEL's preliminary and then final documented safety analyses; INL describes the final one as authorizing a dry criticality configuration at near-zero power with no coolant. Neither release gives an approval day. The October release anticipates criticality in December, which appears earlier than the DOE page's 2027; both are targets. No opened DOE instrument establishes fuel loading, a separate startup authorization, achieved criticality or full-power operating authority.

Key facts

Design
MARVEL (Microreactor)
Technology
Other · sodium-potassium
Operator(s)
Idaho National Laboratory
Vendor for linked design
Idaho National Laboratory
Location
TREAT facility, Idaho National Laboratory · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE names the TREAT facility at Idaho National Laboratory as the planned installation site, and DOE's TREAT fact sheet places TREAT at the Materials and Fuels Complex. The pin reuses the recorded MFC point (43.59507, −112.65716): a facility-area point, not the TREAT building.
Coordinates
43.59507, -112.65716 · site-area point (approximate)
Electrical capacity
10 kWe (gross/net unspecified) · scope: plant
Thermal capacity
85 kWth (nameplate; basis unspecified)
Modules planned
1
Purpose
Research or test reactor
Construction start
Not recorded
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

MARVEL microreactor test bed at INL's TREAT facility is recorded at TREAT facility, Idaho National Laboratory, Idaho, United States. Operator: Idaho National Laboratory. Recorded vendor: Idaho National Laboratory. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716

Recorded electrical output is 10 kWe (gross/net unspecified), scope plant. Modules planned: 1. Recorded thermal output is 85 kWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Funding and government decisions
  • Funder or lender named for this projectU.S. Department of Energy · sourceFunded under the DOE Office of Nuclear Energy Microreactor Program; amount not stated.
Source-backed project statement

DOE's MARVEL project page says MARVEL is funded under DOE's Office of Nuclear Energy Microreactor Program within the Advanced Reactor Technologies Program. No amount is stated. Future end-user tests are to be cost-shared, with no direct financial awards. DOE: MARVEL microreactor project

Fuel
  • Fuel supplier named for this projectTRIGA International · sourceAwarded an approximately $8.4 million contract (Nov 2023) to produce 37 TRIGA fuel elements for MARVEL; fabrication began January 2024; delivery not recorded.
  • Fuel form stated for MARVEL (catalog profile as of 17 Oct 2024)Uranium zirconium hydride fuel, a version of TRIGA fuel
Source-backed project statement

DOE reported on 7 February 2024 that TRIGA International was awarded an approximately 8.4 million dollar contract in November 2023 to produce 37 TRIGA fuel elements for MARVEL and had started fabrication at its Romans, France facility in January 2024. Delivery of the fuel to INL is not recorded in the sources read. DOE: Fuel fabrication starts for MARVEL microreactor

Comparable schedule revision

Source-backed project statement MARVEL's October 2022 technical-review presentation targeted criticality by summer 2024. INL's 6 October 2026 release, read in an archived copy, anticipated criticality in December; the year 2026 is inferred from that release's context. Its dry-criticality configuration has no coolant and is distinct from full-power operation. This is a partial history of criticality expectations, not proof that the two forecasts assumed the same coolant configuration. DOE's separate project page records a 2027 dry-criticality forecast, so the reviewed sources do not establish one reconciled current target. The February 2024 phrase 'online by 2027' does not identify criticality and is not used as an intermediate criticality forecast. No delay duration is calculated. MARVEL microreactor start-up now expected in 2027, as fuel fabrication begins -- ANS / Nuclear Newswire; DOE: Fuel fabrication starts for MARVEL microreactor; DOE Office of Nuclear Energy: MARVEL microreactor project page; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026); MARVEL reactor design overview, October 2022 technical review; INL news release (6 Oct 2026): MARVEL reactor gets federal safety approval as its primary vessel arrives in Idaho

Not found in the sources we checked (2): Customer or offtaker; Contractor
Customer or offtaker

DOE's MARVEL project page says the test bed will engage microreactor end-user companies, with preference for private-sector end users who can use the reactor's energy in self-funded or cost-shared test cases under an anticipated notice of opportunity. No end user, buyer or agreement is named. DOE: MARVEL microreactor project

Contractor

DOE's MARVEL project page and DOE's February 2024 fuel-fabrication article describe MARVEL as a DOE test bed being assembled for installation in INL's TREAT facility. They name TRIGA International as the fuel contractor but no engineering or construction contractor for the reactor itself. DOE: MARVEL microreactor project

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Targets

Planned, target and estimated dates are not achievements or commitments.

Permissions and applications

Environmental decision

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(9 notes)
  • Evidence review. DOE's MARVEL page (read 19 October 2026) describes a sodium-potassium-cooled test microreactor that DOE is developing. It will generate 85 kilowatts thermal and about 10 kilowatts of electricity in the TREAT facility within INL's Materials and Fuels Complex. The page says it is not intended as a commercial product. Interesting Engineering (6 October 2026) says INL leads the project for DOE. DOE's Idaho Operations Office issued a finding of no significant impact on 12 November 2021. That is an environmental finding. It says MARVEL needs no new facilities and no ground disturbance, so there is no site preparation in the usual sense. The work is off-site fabrication followed by installation in TREAT. DOE says key components are under fabrication and some systems, such as the guard vessel, are complete. Assembly is expected to finish in 2026, installation in TREAT to start late in 2026, dry initial criticality to follow in 2027 and full power in 2028. Operation is expected from 2028 to 2030, and electricity generation is the first stage. Nuclear Engineering International (16 March 2026) reports that DOE-ID approved the preliminary documented safety analysis. It clears only a near-zero-power dry criticality test. Interesting Engineering (6 October 2026) reports that DOE-ID then approved the final documented safety analysis, clearing a dry criticality configuration. It says the primary coolant vessel reached INL's TREAT facility in mid-September 2026 for integration, and that the project expects initial testing in December. That date is earlier than DOE's page, and both are targets. INL's own releases could not be opened when checked (access refused). NEI expected fuel delivery in July or August 2026 and fuel loading shortly after, but no opened source confirms delivery or loading. No opened source shows an authority to load fuel or run at power, an achieved criticality, or a dated start of reactor installation. Output figures conflict. DOE gives 85 kWt and about 10 kWe. NEI gives 85-100 kWt and about 20 kWe, and the 2021 finding also says about 20 kWe. The stored 0.085 MWth and 0.01 MWe follow DOE's page, with the basis unspecified. No source names a reactor operator; the closest statement is that INL leads the project. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: MARVEL microreactor project page; NEI: MARVEL cleared for dry criticality; DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor; INL news release (6 Oct 2026): MARVEL reactor gets federal safety approval as its primary vessel arrives in Idaho; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026)
    What would change this

    A DOE or INL notice that MARVEL fuel has been loaded or dry criticality achieved, or a readable copy of DOE-ID's final documented safety analysis approval. Next scheduled check: 19 Jan 2027.

  • Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. MARVEL is a DOE-authorized test reactor, not an NRC licensee. The stored permission is DOE-ID's finding of no significant impact of 12 November 2021, an environmental decision. Nuclear Engineering International (16 March 2026) reports that DOE-ID approved the preliminary documented safety analysis, clearing only a near-zero-power dry criticality test. Interesting Engineering (6 October 2026) reports DOE-ID approval of the final documented safety analysis for a dry criticality configuration, without an approval date. INL's own 6 October 2026 release could not be opened when checked (access refused). No opened source gives a DOE approval document, an approval date, or authority for fuel loading, startup or power operation. Last checked 19 Oct 2026. DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor; NEI: MARVEL cleared for dry criticality; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026); INL news release (6 Oct 2026): MARVEL reactor gets federal safety approval as its primary vessel arrives in Idaho
    What would change this

    DOE publishes MARVEL's final documented safety analysis approval or a startup authorization, or a readable copy of INL's 6 October 2026 release. Next scheduled check: 19 Jan 2027.

  • Construction start evidence: Not disclosed in the reviewed evidence. DOE says key components are under fabrication and some systems, such as the guard vessel, are complete and in storage. Assembly is expected to finish in 2026, with installation in TREAT starting late in 2026. Interesting Engineering reports that the primary coolant vessel reached TREAT in mid-September 2026 for integration. The 2021 finding says no new facilities or ground disturbance are needed. No opened source gives a dated start of fabrication or of reactor installation in TREAT. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: MARVEL microreactor project page; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026); DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor
    What would change this

    DOE or INL reports the start of MARVEL installation in TREAT or completion of assembly. Next scheduled check: 19 Jan 2027.

  • Operation or grid target (type stated). DOE expects dry initial criticality in 2027 and full-power operation in 2028, with electricity generation as the first stage and operation from 2028 to 2030. Interesting Engineering (6 October 2026) reports that the project now expects initial testing in December. These are targets. There is no commercial operation and no grid connection. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: MARVEL microreactor project page; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026)
    What would change this

    Dry criticality is achieved, or DOE revises the 2027 and 2028 targets. Next scheduled check: 19 Jan 2027.

  • Map coordinates: Not disclosed in the reviewed evidence. DOE names the TREAT facility within INL's Materials and Fuels Complex as MARVEL's location, and the 2021 finding names TREAT's north high bay. No opened source gives coordinates for the reactor or the TREAT building, so the map uses the Materials and Fuels Complex area point, where DOE's TREAT fact sheet places the facility. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: MARVEL microreactor project page
    What would change this

    An official map or document giving the TREAT reactor building location. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. DOE's MARVEL page, read on 5 October 2026, says installation in TREAT starts in late 2026, dry initial criticality is anticipated in 2027 and full-power operation in 2028. An October 2026 Interesting Engineering report says DOE Idaho approved the final documented safety analysis for the dry-criticality configuration and that the next major test is set for December. The December date and the 2027 page target differ; neither is an achieved criticality. Last checked 23 Oct 2026. DOE: MARVEL microreactor project; Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026)
    What would change this

    A DOE or INL announcement that MARVEL has reached initial criticality, or a revised criticality date. Next scheduled check: 23 Jan 2027.

  • Permissions and public process. DOE's June 2021 final environmental assessment for MARVEL (DOE/EA-2146) records a public comment period on the draft that DOE extended to 9 February 2021, and briefings for the Shoshone-Bannock Tribes, the Fort Hall Business Council and the Idaho Governor's Office in September 2020. DOE then held a 31-day review of the proposed finding of no significant impact, which closed on 8 July 2021, before issuing the finding in November 2021. These are DOE environmental-review steps; reactor safety authorization is a separate DOE safety-basis decision. Last checked 23 Oct 2026. DOE/EA-2146 Final Environmental Assessment for the MARVEL Project at Idaho National Laboratory; DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor
    What would change this

    A new or supplemental DOE environmental review for MARVEL, or a DOE start-up authorization decision. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). DOE's June 2021 final environmental assessment places MARVEL in a concrete storage pit in the north high bay of the existing TREAT reactor building near INL's Materials and Fuels Complex, with outside equipment such as heat-rejection units kept within the high bay and fenced TREAT perimeter; at start-up its Stirling engines, load banks and heat exchangers are connected. DOE's MARVEL page lists possible uses such as powering a microgrid or a small data-center node, but names no user or grid connection, and neither source describes a separate water supply. Last checked 23 Oct 2026. DOE/EA-2146 Final Environmental Assessment for the MARVEL Project at Idaho National Laboratory; DOE: MARVEL microreactor project
    What would change this

    A DOE decision connecting MARVEL's output to a microgrid or named end user, or a change to its location. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. DOE's June 2021 final environmental assessment says the MARVEL core will be disassembled and analyzed in existing Materials and Fuels Complex facilities, with containers dry stored at TREAT or shipped to that complex for storage or reprocessing. Because the fuel is sodium-bonded, the sodium must be removed before disposal, using processes DOE already applies to EBR-II fuel at INL. This is DOE's planned management in an environmental assessment; it names no repository, and a full criticality and shielding analysis must precede any transfer. Last checked 23 Oct 2026. DOE/EA-2146 Final Environmental Assessment for the MARVEL Project at Idaho National Laboratory
    What would change this

    A DOE decision or document fixing the storage location or treatment of irradiated MARVEL fuel. Next scheduled check: 23 Apr 2027.

Evidence dates

(5 of 11 sources with a publication or document date)
Latest dated listed source publication: Interesting Engineering: 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test (6 October 2026): 6 Oct 2026.Latest dated listed source document: MARVEL reactor design overview, October 2022 technical review: Oct 2022.Latest dated recorded event: INL reports DOE approval of MARVEL's final documented safety analysis: 6 Oct 2026.6 of 11 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(11)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: MARVEL microreactor test bed at INL's TREAT facility — https://smrmap.com/projects/inl-marvel/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “MARVEL microreactor test bed at INL's TREAT facility”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/inl-marvel/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.