Projects / United States · Siting
Idaho State University / NuCube Advanced Research and Test Reactor
Research and test reactor, heat only, no electricity.
Current status
- How current
- General record check . Bounded evidence review . 1 of 4 listed sources has a publication or document date recorded here: 16 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 16 Sep 2026 · Announcement: Idaho State University names site for its Advanced Research and Test Reactor. An Idaho State University announcement identifies the Business and Research Park as the site of the future Advanced Research and Test Reactor. Source: ISU: site revealed for Advanced Research and Test Reactor (published 16 Sep 2026). Updates entry
More on this development
The announcement establishes no nuclear permission.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Idaho State University requested authorization to host NuCube's Advanced Research and Test Reactor and in September 2026 named its Business and Research Park as the site; criticality targeted for 2029-2030.
Key facts
- Design
- Design profile not linked (Microreactor)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Idaho State University
- Vendor for linked design
- NuCube Energy
- Location
- ISU Business and Research Park, Pocatello · United States · precision: town or locality only
Town point from the Wikipedia article for Pocatello; ISU places the reactor at its Business and Research Park in Pocatello. No parcel point is published, so this is a town-level point. - Coordinates
- 42.8622, -112.4506 · town-level point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Idaho State University / NuCube Advanced Research and Test Reactor is recorded at ISU Business and Research Park, Pocatello, Idaho, United States. Operator: Idaho State University. Recorded vendor: NuCube Energy. Stage: Siting. Location precision: town or locality only; town-level point (approximate).
Coordinate source: Wikipedia: Pocatello, Idaho (article coordinates), Article coordinate 42.8622, -112.4506 on 'Pocatello, Idaho', read 30 October 2026
This project is recorded as thermal only (no MWe). Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerIdaho State University · source
- Project proposerNuCube Energy · source
- Operator or intended licensed owner
- OperatorIdaho State University
- Reactor supplier
- Vendor named for this project (no design profile is linked)NuCube Energy
- Site host or owner
- Site hostIdaho State University · source
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Customer or offtaker
Idaho State University's project FAQ says the reactor is designed to produce heat for education, research and testing and is not intended to generate electricity for the grid, and lists research topics such as process heat and hydrogen production. The university's April and September 2026 announcements name no outside buyer of heat or power. Idaho State University: Advanced Research and Test Reactor project FAQ; ISU: site revealed for Advanced Research and Test Reactor
- Contractor
Idaho State University's 29 April 2026 release says NuCube designed the reactor and the university requested authorization to host it, and its 16 September 2026 release says the university, in partnership with NuCube, plans to design and commission it at its Business and Research Park. These are the project's proposers. Neither release nor the FAQ names an engineering or construction contractor. ISU and NuCube selected for DOE Launch Pad; ISU: site revealed for Advanced Research and Test Reactor; Idaho State University: Advanced Research and Test Reactor project FAQ
- Funding and government decisions
Idaho State University's 29 April 2026 release says selection for DOE's Launch Pad USA program gives the university and NuCube access to federal infrastructure, technical expertise and regulatory support. That is program participation, not money, and the release, the September 2026 release and the FAQ state no amount or funder for the reactor. ISU and NuCube selected for DOE Launch Pad
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
Idaho State University's 29 April 2026 release and FAQ say the reactor is designed to use TRISO fuel, and the FAQ says used-fuel removal arrangements are being evaluated and not yet final. That is a design fuel and a back-end question. No fresh-fuel supplier, quantity or delivery is named. ISU and NuCube selected for DOE Launch Pad; Idaho State University: Advanced Research and Test Reactor project FAQ
- Comparable schedule revision
Comparable schedule revision not established. Idaho State University's FAQ says the construction schedule will depend on design, regulatory review, licensing and approvals and gives no year, and its April and September 2026 releases date only the selection and the site announcement. The record's 2029-2030 criticality target came from an East Idaho News article that could not be read here. No earlier and later dates for the same milestone were read. ISU and NuCube selected for DOE Launch Pad; ISU: site revealed for Advanced Research and Test Reactor; Idaho State University: Advanced Research and Test Reactor project FAQ; East Idaho News: site chosen for ISU's Advanced Research and Test Reactor
Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
Idaho State University names site for its Advanced Research and Test Reactor
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. Idaho State University's spring 2026 announcement says the university has officially requested authorization to host the NuCube Energy Advanced Research and Test Reactor on its Pocatello campus, that the joint ISU-NuCube proposal was selected for DOE's Nuclear Energy Launch Pad USA program, and that NuCube designed the reactor as an adaptation of its commercial 4 MWth microreactor with TRISO fuel and heat-pipe cooling, without stating the test reactor's own rating. ISU's release of 16 September 2026 says the university, in partnership with NuCube Energy, plans to design and commission the reactor as a functional microreactor at ISU's Business and Research Park, where leaders gathered at the future site. ISU's undated project FAQ, captured on 19 October 2026, says the reactor will produce heat for education, research and testing rather than grid electricity, that DOE will regulate it through Launch Pad USA with approvals needed before construction and operation, and that the project is in planning and subject to federal review, licensing and approvals. The next documentary decision is DOE's Launch Pad authorization (and any environmental review) for the reactor at the Business and Research Park. The stored siting stage, heat-only basis and ISU as operator stay, although no source names the licensed operator in terms. No opened source states the reactor's rating or a criticality date, so the stored 2029-2030 criticality target is not supported by any opened source; it came from an East Idaho News page that could not be opened when checked (access refused). The design and vendor fields are empty although the sources name NuCube as designer, and the park is named without coordinates. Last checked 19 Oct 2026. ISU and NuCube selected for DOE Launch Pad; ISU: site revealed for Advanced Research and Test Reactor; Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
DOE's Launch Pad USA authorization or environmental review document for the Advanced Research and Test Reactor at ISU's Business and Research Park, stating its rating, location and schedule. Next scheduled check: 19 Jan 2027.
- Design identified. ISU's spring 2026 announcement names NuCube Energy as designer and describes the reactor as an adaptation of NuCube's commercial 4 MWth microreactor using TRISO fuel and heat-pipe cooling; the FAQ repeats TRISO fuel, heat-pipe cooling and passive safety. No model name or test-reactor rating is given, and the 4 MWth figure belongs to the commercial microreactor, not this reactor. No NuCube design record exists, so a new design record and NuCube as vendor are proposed. The FAQ's mention of NuCube's NuSun platform is not stated to be this reactor. Last checked 19 Oct 2026. ISU and NuCube selected for DOE Launch Pad; Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
A DOE authorization document or NuCube design description giving the Advanced Research and Test Reactor's model name and thermal rating, so the design record can carry a sourced rating. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. ISU's 16 September 2026 release places the reactor at ISU's Business and Research Park, and the FAQ says it will be located at ISU's Research and Business Park in Pocatello (word order differs). No parcel or coordinate is published, so the map shows a town-level point for Pocatello. Last checked 19 Oct 2026. ISU: site revealed for Advanced Research and Test Reactor; Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
A DOE environmental review or authorization document giving the parcel or coordinates within the park, which would allow a map point. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Idaho State University's project FAQ says the project is in early planning and must complete engineering, environmental review as applicable, regulatory approvals and licensing, including a used-fuel disposition path, before construction can begin; the construction schedule depends on those steps. DOE's Launch Pad approval is the decision that would allow construction. No date for that decision is given in these sources. Last checked 23 Oct 2026. Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
A DOE Launch Pad authorization decision or a published construction schedule. Next scheduled check: 23 Apr 2027.
- Permissions and public process. Idaho State University's April 2026 release says it requested authorization to host NuCube's Advanced Research and Test Reactor after DOE selected it for the Launch Pad USA program. The university's project FAQ, read on 19 October 2026, says DOE will regulate the reactor through Launch Pad and that approvals are needed before construction and operation. The FAQ says public information sessions will be announced, and invites questions through a community feedback survey. No DOE approval has been reported. Last checked 23 Oct 2026. ISU and NuCube selected for DOE Launch Pad; Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
A DOE authorization decision or environmental review for the ISU reactor, or announced public information sessions. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Idaho State University's September 2026 release and project FAQ place the reactor at the university's Business and Research Park in Pocatello, on university land. The FAQ says the reactor produces heat for education, research and testing and is not intended to supply electricity to the grid, so no grid connection is planned. The sources give no plot boundary, cooling-water or other utility arrangement. Last checked 23 Oct 2026. Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
A DOE environmental document or site plan describing the reactor's footprint and utilities at the park. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. Idaho State University's project FAQ, read on 19 October 2026, says ISU and NuCube are evaluating several options to ensure used fuel is removed at the end of reactor life, and that those arrangements have not been finalised. It says identifying the used-fuel disposition path is required before construction can begin. This is a stated intention; no storage or disposal arrangement exists yet. Last checked 23 Oct 2026. Idaho State University: Advanced Research and Test Reactor project FAQ
What would change this
An ISU, NuCube or DOE statement fixing the used-fuel disposition path. Next scheduled check: 23 Apr 2027.
Evidence dates
(1 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- ISU and NuCube selected for DOE Launch Pad (company, accessed 2 Oct 2026)
- East Idaho News: site chosen for ISU's Advanced Research and Test Reactor (news report, accessed 2 Oct 2026)
- ISU: site revealed for Advanced Research and Test Reactor (company, published 16 Sep 2026, accessed 13 Oct 2026)
- Idaho State University: Advanced Research and Test Reactor project FAQ (company, accessed 19 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Idaho State University / NuCube Advanced Research and Test Reactor — https://smrmap.com/projects/isu-nucube-art/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Idaho State University / NuCube Advanced Research and Test Reactor”. Record reviewed 13 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/isu-nucube-art/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.