Jimmy Cristanol Bazancourt heat microreactor proposal

Jimmy's proposed Bazancourt Fermi reactor is rated 20 MWth by ASNR; Jimmy's separate 10 MW figure describes proposed heat supplied to Cristanol, not reactor power.

Current status

Stage
Licensing
How current
General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 11 Oct 2024. A listed page was last updated 14 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Under review: Jimmy Bazancourt creation-authorization application. An application under review is not a permit. All permissions and applications
Latest development
23 Jul 2026 · Recorded development: Jimmy submits an updated Bazancourt creation-authorization file. ASNR states that Jimmy filed an updated design and the remaining answers on 23 July 2026, and that MSNR referred that file to ASNR for review on 24 July 2026. Source: ASNR, PRM projects and their fuel-fabrication plants. Updates entry
More on this development

The update is not a creation authorization.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
  • State or province is not recorded.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
High-temperature gas-cooled reactor. How it works, with a 3D view.
Schematic of HTR-PM, this type's example. On the left, a tall reactor vessel holds a bed of fuel spheres inside a graphite reflector, with fuel tubes above and below.
Schematic of HTR-PM, this type's example.

Description

ASNR's PRM page says a creation-authorization application was filed for industrial heat at a Cristal Union factory in Bazancourt, that the ministry requested further information on 13 February 2025, that Jimmy filed an updated design and remaining answers on 23 July 2026, and that ASNR was asked on 24 July 2026 to review the updated file. The 2024 filing day differs between sources (29 April in Jimmy's release, 3 May in ASN's annual report, 27 May on ASNR's project page), so only the year is asserted. Jimmy describes its solution as one of the options Cristal Union is studying; no heat-supply contract is recorded. No creation authorization is recorded. Le Creusot is the fuel-assembly facility, not this deployment site.

Key facts

Design
Jimmy Fermi heat microreactor (Microreactor)
Technology
High-temperature gas-cooled reactor (HTGR) · helium
Reactor vessel of this design
5 m tall, 5 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 241.the reactor-vessel subsection says the reactor vessel is 5x5m the pressure-tube sentence gives no size footprint 6000 is not this cellSMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Jimmy
Vendor for linked design
Jimmy
Location
Cristanol industrial site, Bazancourt · France · precision: site area (named plant, laboratory, base, port, campus or parcel)
OSM industrial-landuse centroid for the Cristanol site, the named host industrial site; the generator's footprint within it is not published. Geocode: Query 'Cristanol, Bazancourt' -> landuse=industrial 'Cristanol, Bazancourt, Reims, Marne, Grand Est, France métropolitaine, 51110, France'.
Coordinates
49.346536, 4.172828 · site-area point (approximate)
Electrical capacity
thermal only (no MWe) · scope: module
Thermal capacity
20 MWth (nameplate; basis unspecified)
Modules planned
1
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Jimmy Cristanol Bazancourt heat microreactor proposal is recorded at Cristanol industrial site, Bazancourt, state or province not recorded, France. Operator: Jimmy. Recorded vendor: Jimmy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Cristanol, Bazancourt' (landuse=industrial), Marne

This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 20 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
  • Vendor for the linked designJimmy
Customer or offtaker

Source-backed project statement On 29 April 2024 Jimmy said a thermal generator could be installed at the Cristanol site in Bazancourt and could supply 10 MW, and that the proposal is one of the options Cristal Union is studying. The nuclear safety authority's project page, updated 14 October 2026, says the Fermi reactor is intended to supply industrial heat to a Cristal Union factory. No heat-supply contract or price is stated. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants

Fuel
  • Fuel supplier named for this projectUrenco · sourceContract announced 11 October 2024 to supply LEU+ enrichment (up to 10%) for Jimmy's first micro reactor, applied for in the Marne area; first delivery planned for 2026; delivery not recorded.
  • Fuel form stated for Jimmy Fermi heat microreactorUCO TRISO particles packed into pellets
Source-backed project statement

On 11 October 2024 Urenco said it signed a contract to supply low-enriched uranium plus, enriched up to 10 percent, for Jimmy's first high-temperature gas-cooled microreactor, with first delivery to be made in 2026 from Eunice, New Mexico. The same release ties Jimmy's first project to an industrial customer in the Marne, the area where Bazancourt lies, though it does not name the site, and it describes a later shift to higher-assay uranium as a prospect, not a second contract. Delivery in 2026 is stated as planned, not as a completed shipment or loading. Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)

Site host or owner
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
Contractor

Jimmy's 29 April 2024 release says its generators are assembled at Le Creusot, which the safety authority lists as a separate fuel-assembly installation, not the Bazancourt reactor. Neither that release, the 11 October 2024 fuel release, nor the authority's Fermi entry names an engineering or construction firm for the Bazancourt installation. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants

Funding and government decisions

Jimmy's 29 April 2024 release says the company received a 32 million euro subsidy under France 2030. The release does not say that subsidy is money for the Bazancourt installation. The safety-authority page reviewed states no project funding. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants

Comparable schedule revision

Comparable schedule revision not established. The pages reviewed give no two dated forecasts for operation or heat supply at Bazancourt. The 29 April 2024 and 27 May 2024 dates are different statements of when the creation-authorization application was filed, not two forecasts of the same construction milestone. The planned 2026 fuel delivery is a supply date, not a reactor-operation date. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants; Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)

Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Construction applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes)
  • Evidence review. ASNR's small modular reactor page (updated 14 October 2026) says Jimmy Energy applied to the minister responsible for nuclear safety for authorization to create a basic nuclear installation named Fermi in the commune of Bazancourt, with a reactor to supply industrial heat to a Cristal Union group factory, and lists Fermi as an industrial demonstrator reactor of 20 MWth among high-temperature reactors. ASN's 2024 annual report describes it as an HTR of 20 MWth using TRISO fuel, about 15 km from Reims. The filing day differs between sources: 29 April 2024 in Jimmy's release, 3 May 2024 in the annual report and 27 May 2024 on ASNR's page. The ministry's nuclear-safety mission requested further information on 13 February 2025; Jimmy sent an updated file with reactor design changes on 23 July 2026, and ASNR was asked on 24 July 2026 to carry out the technical review of that file. This is an application under review, not a creation authorization; Jimmy's release says the review includes an environmental study and a public inquiry and that the generator could be installed only if it passes every review and authorization step. No opened source reports site preparation or nuclear construction at Bazancourt, and no target date for construction or operation is published. Jimmy says its solution could supply 10 MW to the Cristanol site, which is heat delivered, separate from the 20 MWth reactor rating, and that it is one of the options Cristal Union is studying; Jimmy's release says the authorities must confirm that Jimmy can build and operate this generator. The licensing stage, one unit, 20 MWth heat-only rating and Jimmy as intended operator stay stored. Last checked 19 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update); ASN 2024 annual report: Bazancourt Fermi application and reactor rating; Jimmy deployment announcement
    What would change this

    ASNR's technical review opinion on Jimmy's updated Fermi file, the environmental study or public inquiry notice, or the minister's decision on the creation authorization. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The next recorded step is ASNR's technical examination of the updated Fermi file, referred on 24 July 2026, ahead of a ministerial decision on the creation authorization. No date for that decision is given, and the redesign means earlier review answers apply only where still relevant. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
    What would change this

    An ASNR opinion or ministerial decree on the Fermi creation authorization. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. ASNR records a 2024 application to the minister for authorization to create the Fermi nuclear installation at Bazancourt, ministry requests for further information, an updated file with design changes on 23 July 2026, and ASNR's referral to examine that file from 24 July 2026. This is an application under review, not an authorization. The opened ASNR page records no public inquiry, local consultation outcome or decision. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
    What would change this

    An ASNR opinion, public-inquiry notice or ministerial decision on the Fermi creation authorization. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. ASNR places the installation in the commune of Bazancourt to supply industrial heat to a Cristal Union factory. The opened regulator page names no land, heat-supply, water or other infrastructure agreement. A heat-only reactor has no grid-connection question. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
    What would change this

    A heat-supply, land or site agreement between Jimmy Energy and Cristal Union or Cristanol for Bazancourt. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Jimmy's 29 April 2024 release says the authorization review considers the generator's life through final shutdown and dismantling. That is the scope of the review, not a spent-fuel or waste arrangement for Fermi. The safety authority's Fermi entry and the 11 October 2024 fuel release do not state one. Last checked 23 Oct 2026. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants; Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)
    What would change this

    A Fermi document that states spent-fuel storage, waste disposition, or dismantling arrangements. Next scheduled check: 21 Jan 2027.

Evidence dates

(1 of 5 sources with a publication or document date)
Latest dated listed source publication: Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy): 11 Oct 2024.Latest dated recorded event: Jimmy submits an updated Bazancourt creation-authorization file: 23 Jul 2026.4 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Jimmy Cristanol Bazancourt heat microreactor proposal — https://smrmap.com/projects/jimmy-bazancourt/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Jimmy Cristanol Bazancourt heat microreactor proposal”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/jimmy-bazancourt/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.