Projects / France · Licensing
Jimmy Cristanol Bazancourt heat microreactor proposal
Jimmy's proposed Bazancourt Fermi reactor is rated 20 MWth by ASNR; Jimmy's separate 10 MW figure describes proposed heat supplied to Cristanol, not reactor power.
Current status
- How current
- General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 11 Oct 2024. A listed page was last updated 14 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: Jimmy Bazancourt creation-authorization application. An application under review is not a permit. All permissions and applications
- Latest development
- 23 Jul 2026 · Recorded development: Jimmy submits an updated Bazancourt creation-authorization file. ASNR states that Jimmy filed an updated design and the remaining answers on 23 July 2026, and that MSNR referred that file to ASNR for review on 24 July 2026. Source: ASNR, PRM projects and their fuel-fabrication plants. Updates entry
More on this development
The update is not a creation authorization.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- State or province is not recorded.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
ASNR's PRM page says a creation-authorization application was filed for industrial heat at a Cristal Union factory in Bazancourt, that the ministry requested further information on 13 February 2025, that Jimmy filed an updated design and remaining answers on 23 July 2026, and that ASNR was asked on 24 July 2026 to review the updated file. The 2024 filing day differs between sources (29 April in Jimmy's release, 3 May in ASN's annual report, 27 May on ASNR's project page), so only the year is asserted. Jimmy describes its solution as one of the options Cristal Union is studying; no heat-supply contract is recorded. No creation authorization is recorded. Le Creusot is the fuel-assembly facility, not this deployment site.
Key facts
- Design
- Jimmy Fermi heat microreactor (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Reactor vessel of this design
- 5 m tall, 5 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 241.the reactor-vessel subsection says the reactor vessel is 5x5m the pressure-tube sentence gives no size footprint 6000 is not this cellSMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Jimmy
- Vendor for linked design
- Jimmy
- Location
- Cristanol industrial site, Bazancourt · France · precision: site area (named plant, laboratory, base, port, campus or parcel)
OSM industrial-landuse centroid for the Cristanol site, the named host industrial site; the generator's footprint within it is not published. Geocode: Query 'Cristanol, Bazancourt' -> landuse=industrial 'Cristanol, Bazancourt, Reims, Marne, Grand Est, France métropolitaine, 51110, France'. - Coordinates
- 49.346536, 4.172828 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: module
- Thermal capacity
- 20 MWth (nameplate; basis unspecified)
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Jimmy Cristanol Bazancourt heat microreactor proposal is recorded at Cristanol industrial site, Bazancourt, state or province not recorded, France. Operator: Jimmy. Recorded vendor: Jimmy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Cristanol, Bazancourt' (landuse=industrial), Marne
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 20 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorJimmy
- Reactor supplier
- Vendor for the linked designJimmy
- Customer or offtaker
Source-backed project statement On 29 April 2024 Jimmy said a thermal generator could be installed at the Cristanol site in Bazancourt and could supply 10 MW, and that the proposal is one of the options Cristal Union is studying. The nuclear safety authority's project page, updated 14 October 2026, says the Fermi reactor is intended to supply industrial heat to a Cristal Union factory. No heat-supply contract or price is stated. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants
- Fuel
- Fuel supplier named for this projectUrenco · sourceContract announced 11 October 2024 to supply LEU+ enrichment (up to 10%) for Jimmy's first micro reactor, applied for in the Marne area; first delivery planned for 2026; delivery not recorded.
- Fuel form stated for Jimmy Fermi heat microreactorUCO TRISO particles packed into pellets
Source-backed project statement
On 11 October 2024 Urenco said it signed a contract to supply low-enriched uranium plus, enriched up to 10 percent, for Jimmy's first high-temperature gas-cooled microreactor, with first delivery to be made in 2026 from Eunice, New Mexico. The same release ties Jimmy's first project to an industrial customer in the Marne, the area where Bazancourt lies, though it does not name the site, and it describes a later shift to higher-assay uranium as a prospect, not a second contract. Delivery in 2026 is stated as planned, not as a completed shipment or loading. Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
Jimmy's 29 April 2024 release says its generators are assembled at Le Creusot, which the safety authority lists as a separate fuel-assembly installation, not the Bazancourt reactor. Neither that release, the 11 October 2024 fuel release, nor the authority's Fermi entry names an engineering or construction firm for the Bazancourt installation. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants
- Funding and government decisions
Jimmy's 29 April 2024 release says the company received a 32 million euro subsidy under France 2030. The release does not say that subsidy is money for the Bazancourt installation. The safety-authority page reviewed states no project funding. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants
- Comparable schedule revision
Comparable schedule revision not established. The pages reviewed give no two dated forecasts for operation or heat supply at Bazancourt. The 29 April 2024 and 27 May 2024 dates are different statements of when the creation-authorization application was filed, not two forecasts of the same construction milestone. The planned 2026 fuel delivery is a supply date, not a reactor-operation date. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants; Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)
Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Jimmy submits an updated Bazancourt creation-authorization file - · Regulatory step
Ministry requests more information on Jimmy's Bazancourt reactor application - · Application submitted
Application submitted: Jimmy Bazancourt creation-authorization application
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- Jimmy Bazancourt creation-authorization application
Construction permission sought · Under review · ASNR · submitted 2024
ASNR records Jimmy's 2024 creation-authorization application for an industrial-heat reactor at a Cristal Union factory in Bazancourt. Published filing dates differ across the project sources, so the stored submission date remains at year precision. MSNR requested further information on 13 February 2025. Jimmy submitted an updated design and the remaining answers on 23 July 2026, and MSNR referred that updated file to ASNR for review on 24 July 2026. These sources do not record an issued creation authorization.
Sources: ASNR, PRM projects and their fuel-fabrication plants; ASN 2024 annual report: Bazancourt Fermi application and reactor rating
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. ASNR's small modular reactor page (updated 14 October 2026) says Jimmy Energy applied to the minister responsible for nuclear safety for authorization to create a basic nuclear installation named Fermi in the commune of Bazancourt, with a reactor to supply industrial heat to a Cristal Union group factory, and lists Fermi as an industrial demonstrator reactor of 20 MWth among high-temperature reactors. ASN's 2024 annual report describes it as an HTR of 20 MWth using TRISO fuel, about 15 km from Reims. The filing day differs between sources: 29 April 2024 in Jimmy's release, 3 May 2024 in the annual report and 27 May 2024 on ASNR's page. The ministry's nuclear-safety mission requested further information on 13 February 2025; Jimmy sent an updated file with reactor design changes on 23 July 2026, and ASNR was asked on 24 July 2026 to carry out the technical review of that file. This is an application under review, not a creation authorization; Jimmy's release says the review includes an environmental study and a public inquiry and that the generator could be installed only if it passes every review and authorization step. No opened source reports site preparation or nuclear construction at Bazancourt, and no target date for construction or operation is published. Jimmy says its solution could supply 10 MW to the Cristanol site, which is heat delivered, separate from the 20 MWth reactor rating, and that it is one of the options Cristal Union is studying; Jimmy's release says the authorities must confirm that Jimmy can build and operate this generator. The licensing stage, one unit, 20 MWth heat-only rating and Jimmy as intended operator stay stored. Last checked 19 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update); ASN 2024 annual report: Bazancourt Fermi application and reactor rating; Jimmy deployment announcement
What would change this
ASNR's technical review opinion on Jimmy's updated Fermi file, the environmental study or public inquiry notice, or the minister's decision on the creation authorization. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next recorded step is ASNR's technical examination of the updated Fermi file, referred on 24 July 2026, ahead of a ministerial decision on the creation authorization. No date for that decision is given, and the redesign means earlier review answers apply only where still relevant. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
An ASNR opinion or ministerial decree on the Fermi creation authorization. Next scheduled check: 21 Jan 2027.
- Permissions and public process. ASNR records a 2024 application to the minister for authorization to create the Fermi nuclear installation at Bazancourt, ministry requests for further information, an updated file with design changes on 23 July 2026, and ASNR's referral to examine that file from 24 July 2026. This is an application under review, not an authorization. The opened ASNR page records no public inquiry, local consultation outcome or decision. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
An ASNR opinion, public-inquiry notice or ministerial decision on the Fermi creation authorization. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. ASNR places the installation in the commune of Bazancourt to supply industrial heat to a Cristal Union factory. The opened regulator page names no land, heat-supply, water or other infrastructure agreement. A heat-only reactor has no grid-connection question. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
A heat-supply, land or site agreement between Jimmy Energy and Cristal Union or Cristanol for Bazancourt. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Jimmy's 29 April 2024 release says the authorization review considers the generator's life through final shutdown and dismantling. That is the scope of the review, not a spent-fuel or waste arrangement for Fermi. The safety authority's Fermi entry and the 11 October 2024 fuel release do not state one. Last checked 23 Oct 2026. Jimmy deployment announcement; ASNR, PRM projects and their fuel-fabrication plants; Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy)
What would change this
A Fermi document that states spent-fuel storage, waste disposition, or dismantling arrangements. Next scheduled check: 21 Jan 2027.
Evidence dates
(1 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- Jimmy deployment announcement (company, accessed 18 Oct 2026)
- ASNR, PRM projects and their fuel-fabrication plants (regulator, accessed 3 Nov 2026)
- ASN 2024 annual report: Bazancourt Fermi application and reactor rating (regulator, accessed 9 Oct 2026)
- ASNR, PRM projects and technical exchanges (14 October 2026 update) (regulator, page updated 14 Oct 2026, accessed 3 Nov 2026)
- Urenco signs advanced fuels contract with technology developer Jimmy (Jimmy newsroom copy) (company, published 11 Oct 2024, accessed 21 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Jimmy Cristanol Bazancourt heat microreactor proposal — https://smrmap.com/projects/jimmy-bazancourt/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Jimmy Cristanol Bazancourt heat microreactor proposal”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/jimmy-bazancourt/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.