Projects / United States · Announced
NANO Nuclear microreactors for Digihost's North Tonawanda power plant (2024 MOU)
NANO Nuclear and Digihost signed a non-binding MOU in December 2024 to advance the integration of NANO's microreactors at Digihost's power plant in upstate New York.
Current status
- How current
- General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Digihost identifies the plant as its 60 MW power plant at North Tonawanda. The MOU covers site assessment, site preparation, a roadmap and eventual definitive agreements, with reactor integration targeted by NANO for 2031. This is a labeled microreactor proposal. The 60 MW figure is the existing plant, not nuclear capacity. No definitive agreement, licensing or design selection is established.
Key facts
- Design
- Design profile not linked (Microreactor)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Not recorded
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Digihost 60 MW power plant, North Tonawanda, New York · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Maryland’s official air-modeling attachment lists Fortistar North Tonawanda Inc., ORIS 54131, NTCT 1 at 43.0483,−78.8539 (PDF p.71). New York DPS links Fortistar and Digihost; Digihost’s acquisition release and NANO’s MOU connect the proposal to this existing plant. The point identifies the host facility only. No reactor pad, selected design or nuclear permission is implied. - Coordinates
- 43.0483, -78.8539 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- low
- Record reviewed
- 13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
NANO Nuclear microreactors for Digihost's North Tonawanda power plant (2024 MOU) is recorded at Digihost 60 MW power plant, North Tonawanda, New York, New York, United States. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Maryland air petition: Fortistar North Tonawanda facility coordinates, Maryland air-modeling attachment, PDF page 71: Fortistar North Tonawanda, ORIS 54131, NTCT 1 at 43.0483, −78.8539
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerNANO Nuclear Energy · source
- Customer or offtaker
Source-backed project statement NANO Nuclear's 13 December 2024 announcement says the non-binding memorandum aims to use NANO's microreactors to provide reliable baseload power for Digihost's own data center operations at its 60 MW upstate New York power plant, replacing its existing gas infrastructure. The intended user is Digihost, the host. This is a non-binding memorandum, not a power purchase agreement, and definitive agreements are still to come. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
Not found in the sources we checked (4): Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Contractor
NANO Nuclear's 13 December 2024 announcement says NANO will provide consulting services to Digihost, including regulatory advice, site assessment, roadmap development and stakeholder engagement, under a non-binding memorandum. NANO is the reactor developer, so this is not a separate contractor appointment, and no engineering or construction contractor is named. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
- Funding and government decisions
NANO Nuclear's 13 December 2024 announcement describes a non-binding memorandum and future definitive agreements but states no funder, amount or payment for the Digihost microreactor project. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
NANO Nuclear's 13 December 2024 announcement names its ZEUS and ODIN microreactor designs but no fuel supplier, quantity or delivery for the Digihost site. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
- Comparable schedule revision
Comparable schedule revision not established. NANO Nuclear's 13 December 2024 announcement gives one target, reactor integration within Digihost's operations in 2031, aligned with NANO's licensing expectations. One target stated once is not a revision. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes, 1 not yet reviewed)
- Evidence review. NANO and Digihost's 13 December 2024 non-binding memorandum concerns potential microreactor integration at Digihost's existing gas-fired power facility. The cited 60 MW describes that host facility, not nuclear output. NANO's ZEUS and ODIN technologies are discussed without a selected model or unit count. Site assessment, preparation, licensing work and definitive agreements remain future steps; integration targeted for 2031 is not an achieved deployment. NANO is a project collaborator and adviser, not an appointed reactor operator. Last checked 19 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
A definitive project agreement or licensing application identifying the selected design, reactor operator, nuclear rating and deployment obligations. Next scheduled check: 19 Jan 2027.
- Design identified: Not disclosed in the reviewed evidence. The non-binding MOU discusses ZEUS and ODIN without selecting a design; no model is assigned. Last checked 19 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
A definitive project agreement or licensing application identifying the selected design, reactor operator, nuclear rating and deployment obligations. Next scheduled check: 19 Jan 2027.
- Developer or proposer. NANO Nuclear is a named project collaborator providing consulting and deployment support; this is a proposer role, not a selected vendor or operator. Last checked 19 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
A definitive project agreement or licensing application identifying the selected design, reactor operator, nuclear rating and deployment obligations. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Under the December 2024 non-binding MOU, the next steps are NANO's consulting work: regulatory advice, site assessment, a roadmap and stakeholder engagement. No binding agreement, date or licensing step is set. Last checked 23 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
A binding agreement, site assessment result or NRC filing for the Digihost plant. Next scheduled check: 21 Jan 2027.
- Permissions and public process: Not disclosed in the reviewed evidence. The December 2024 non-binding MOU sets a framework for public understanding and community support and for NANO to give regulatory advice and stakeholder engagement. It names no NRC application, state permit or consultation held. Last checked 23 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
An NRC pre-application record or a New York permit filing for reactors at the Digihost plant. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The MOU concerns Digihost's existing 60 MW power plant in upstate New York, where NANO would assist with the existing gas infrastructure meanwhile and carry out a site assessment. No reactor plot, grid arrangement or water source is described. Last checked 23 Oct 2026. NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024)
What would change this
A site assessment or license filing describing the reactor location at the Digihost plant. Next scheduled check: 21 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- NANO Nuclear and Digihost announce microreactor collaboration (13 Dec 2024) (company, accessed 3 Oct 2026)
- Digihost completes acquisition of its 60 MW power plant (8 Feb 2023) (company, accessed 3 Oct 2026)
- New York DPS: Fortistar North Tonawanda and Digihost (government, accessed 13 Oct 2026)
- Maryland air petition: Fortistar North Tonawanda facility coordinates (government, accessed 13 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: NANO Nuclear microreactors for Digihost's North Tonawanda power plant (2024 MOU) — https://smrmap.com/projects/nano-digihost-north-tonawanda/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “NANO Nuclear microreactors for Digihost's North Tonawanda power plant (2024 MOU)”. Record reviewed 13 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/nano-digihost-north-tonawanda/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.