Projects / Slovakia · Siting
newcleo / JAVYS LFR-AS-200 study at Bohunice V1
JAVYS and newcleo formed the CVP joint venture in June 2025 to prepare a feasibility study for one to four LFR-AS-200 units (200-800 MW) on the decommissioned V1 site at Jaslovské Bohunice.
Current status
- How current
- General record check . Bounded evidence review . None of the 2 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The range is not stored as a plant total. No license application is established.
Key facts
- Design
- LFR-AS-200 (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead
- Operator(s)
- Not recorded
- Vendor for linked design
- newcleo
- Design origin
- France: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Bohunice V1 site · Slovakia · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates of the Bohunice nuclear site from the NuclearChain reactors export (CC BY 4.0), whose unit points derive from GEM's Global Nuclear Power Tracker; the V1 site lies within that complex. Site-area point. - Coordinates
- 48.4968, 17.6907 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
newcleo / JAVYS LFR-AS-200 study at Bohunice V1 is recorded at Bohunice V1 site, Trnava, Slovakia. Operator: No operator is recorded. Recorded vendor: newcleo. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'bohunice-nuclear-power-plant-1' (48.4968, 17.6907)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designnewcleo
- Funding and government decisions
Source-backed project statement JAVYS's 4 June 2025 press release says the project's first phase, a 12-month feasibility study, is funded exclusively by newcleo. No amount is stated. Financing for later phases is left to the feasibility decision, and the Slovak Republic is not obliged to proceed if the study is negative. JAVYS and newcleo sign major shareholder agreement
- Fuel
- Fuel form stated for LFR-AS-200 (catalog profile as of 14 Feb 2025)MOX
JAVYS's 4 June 2025 press release says the lead-cooled reactors would reuse and reprocess spent nuclear fuel, so Slovakia would depend less on fresh-fuel imports. That is the project's stated purpose. The release names no fuel fabricator, reprocessing arrangement, quantity or allocated spent-fuel inventory for the Bohunice units. JAVYS and newcleo sign major shareholder agreement
- Programs and agreements naming the project
- Feasibility or siting study; completedUS Project Phoenix coal-to-SMR feasibility study for Slovakia (four sites found suitable)
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
JAVYS's 4 June 2025 press release says the Slovak Republic would gain a stable long-term source of electricity and that the units would support the stability of the transmission system, but it names no utility, buyer, quantity or agreement for power from the Bohunice units. The ČEZ item on the site menu is a separate JAVYS project, not part of this release. JAVYS and newcleo sign major shareholder agreement
- Contractor
JAVYS's 4 June 2025 press release says JAVYS and newcleo, the vendor, set up the CVP joint venture, with JAVYS holding 51% and managerial control, to prepare a 12-month feasibility study for one to four LFR-AS-200 units at the Bohunice V1 site. The release names no engineering firm, study author or construction contractor, and says Slovak companies could be involved later without naming any. JAVYS and newcleo sign major shareholder agreement
- Comparable schedule revision
Comparable schedule revision not established. JAVYS's 4 June 2025 press release gives one timetable, a feasibility study over the next 12 months followed by a feasibility decision, and lists later phases without dates. No source read restates or moves that timetable. JAVYS and newcleo sign major shareholder agreement
Not recorded in SMRMap's reviewed evidence (2): Operator or intended licensed owner; Site host or owner
- Operator or intended licensed owner
- Site host or owner
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. JAVYS's press release of 4 June 2025 says JAVYS and newcleo, s.r.o. signed a shareholders' agreement in Rome on 3 June 2025 establishing the joint venture Centre for the Development of Spent Nuclear Fuel Utilization, a.s. (CVP), which will work on developing and deploying newcleo's LFR-AS-200 lead-cooled fast reactor. The project envisages one to four LFR-AS-200 units with a total capacity of 200 to 800 MW on the site of the decommissioned V1 nuclear power plant at Jaslovské Bohunice, Slovakia. JAVYS will hold 51% of CVP and managerial control over CVP's operations; the first phase, funded by newcleo, is a feasibility study over 12 months, after which a feasibility decision will confirm or reject the project, and Slovakia is not obliged to proceed if the study is negative. No source names an intended reactor operator: JAVYS's managerial control is over the joint venture, not reactor operation, so the stored JAVYS operator is not supported by the opened source. The next documentary decision is the feasibility decision on CVP's study, due around mid-2026 on the release's 12-month timetable, which no opened source reports. The stored LFR-AS-200 design, newcleo as vendor, the Bohunice V1 site, the siting stage and the unstored 200-800 MW range stay. newcleo's SEC prospectus (424B3) could not be opened because SEC EDGAR requires a declared contact identity for automated access. Last checked 19 Oct 2026. JAVYS and newcleo sign major shareholder agreement
What would change this
The CVP feasibility study's result and the feasibility decision by JAVYS and newcleo (or the Slovak government), which would confirm, change or stop the Bohunice V1 project. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The June 2025 joint-venture release says newcleo alone funds a feasibility study expected to take about 12 months, after which a feasibility decision will confirm or reject the project's technical and economic case, including financing, design, schedule and cost. Slovakia is not obliged to proceed if the study is negative. Site preparation and construction are later phases. Whether that decision has been taken is not recorded here. Last checked 23 Oct 2026. JAVYS and newcleo sign major shareholder agreement
What would change this
A JAVYS, newcleo or government statement of the feasibility decision or of a later licensing step. Next scheduled check: 21 Jan 2027.
- Permissions and public process: Not disclosed in the reviewed evidence. The June 2025 release describes a feasibility phase only. It names no siting or construction license application, environmental impact assessment or public consultation for new units. The separate EIA listed on the JAVYS site concerns decommissioning of the V1 plant, not this project. Last checked 23 Oct 2026. JAVYS and newcleo sign major shareholder agreement
What would change this
A Slovak regulator, environmental-assessment or consultation notice naming new LFR-AS-200 units at Bohunice. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. The release places one to four units on the decommissioned V1 plant site at Jaslovské Bohunice and says new units would support the Slovak transmission system. It names no grid-connection study or agreement, cooling-water arrangement or land agreement for the new units. Last checked 23 Oct 2026. JAVYS and newcleo sign major shareholder agreement
What would change this
A feasibility-study summary, grid or site agreement naming the Bohunice LFR-AS-200 units. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The release says the joint venture, named for spent-fuel utilization, aims to run the reactors on reprocessed Slovak spent nuclear fuel and to reduce the volume and radiotoxicity of resulting waste. This is a stated project purpose, not an existing reprocessing facility, fuel-fabrication contract, waste agreement or disposal arrangement. Last checked 23 Oct 2026. JAVYS and newcleo sign major shareholder agreement
What would change this
A fuel-cycle, reprocessing or waste-management agreement for the Bohunice units. Next scheduled check: 21 Jan 2027.
Evidence dates
(0 of 2 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(2)
- JAVYS and newcleo sign major shareholder agreement (company, accessed 2 Oct 2026)
- newcleo prospectus (SEC 424B3) (company, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: newcleo / JAVYS LFR-AS-200 study at Bohunice V1 — https://smrmap.com/projects/newcleo-bohunice/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “newcleo / JAVYS LFR-AS-200 study at Bohunice V1”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/newcleo-bohunice/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.