Transformational Challenge Reactor microreactor test proposal at ORNL (2019)
ORNL’s Transformational Challenge Reactor was proposed as a helium-cooled microreactor with an additively manufactured core, to be built and tested at Oak Ridge National Laboratory.
Current status
- How current
- General record check . Bounded evidence review . 2 of 4 listed sources have a publication or document date recorded here; the newest is Aug 2022. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
ORNL’s August 2019 safety design strategy proposed designing, building and briefly testing the microreactor in Building 7709 on Copper Ridge. Its under-6-MWth operating envelope is not a selected nameplate. A 2022 ORNL conference-paper abstract describes the test-reactor concept. The former program URL redirects to that paper; it is not a current program-status page. A copy of the program page saved on 3 October 2026, itself undated, describes the program in the past tense as now being joined with two other initiatives; it names the reactor only in the program's title and says nothing about building or testing it. The reviewed sources do not establish achieved reactor construction or operation, or that the proposal ended, and later status has not been traced.
Key facts
- Design
- Design profile not linked (Microreactor)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Not recorded
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Building 7709, Copper Ridge, Oak Ridge National Laboratory · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Laboratory point from the Wikipedia article for Oak Ridge National Laboratory; the strategy names Building 7709 on Copper Ridge, which is not separately located here, so this is a laboratory-area point. - Coordinates
- 35.93, -84.31 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 3 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Transformational Challenge Reactor microreactor test proposal at ORNL (2019) is recorded at Building 7709, Copper Ridge, Oak Ridge National Laboratory, Tennessee, United States. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Wikipedia: Oak Ridge National Laboratory (article coordinates), Article coordinate 35.93, -84.31 on 'Oak Ridge National Laboratory', read 30 October 2026
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerOak Ridge National Laboratory · source
- Funding and government decisions
Source-backed project statement ORNL's August 2019 safety design strategy says the DOE Office of Nuclear Energy was embarking on the Transformational Challenge Reactor program, carried out by ORNL under its DOE management contract. That makes DOE-NE the program sponsor, but no amount, budget or appropriation for the reactor is stated, and no construction or operation is established. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
- Customer or offtaker
ORNL's August 2019 safety design strategy describes the Transformational Challenge Reactor as a DOE program to design, manufacture and briefly operate a small test reactor at Oak Ridge to demonstrate advanced manufacturing, and the 2022 ORNL paper calls it a 3 MWt test reactor. Neither names a recipient of power or heat. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
- Contractor
ORNL's August 2019 safety design strategy says ORNL, managed by UT-Battelle for DOE, would design and manufacture the reactor, specify conventional equipment and start long-lead procurement as design constraints were finalised. No engineering, manufacturing or construction contractor for the reactor is named. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
ORNL's August 2019 safety design strategy gives a pre-conceptual envelope of HALEU fuel as uranium carbide, oxide, nitride or mixtures, and says TRISO fuel might be selected. That is an open design choice. No fuel supplier, fabrication or delivery for the test reactor is named. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
- Comparable schedule revision
Comparable schedule revision not established. ORNL's August 2019 safety design strategy says the program targeted beginning start-up activities in 2023. The 2022 ORNL paper read gives no date, so no earlier and later date for the same milestone is shown, and no start-up is established. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019); ORNL: TCR Central Shutdown Rod Fine Motion Control (August 2022)
Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. ORNL’s August 2019 safety design strategy says the Transformational Challenge Reactor program at Oak Ridge will design, build, and conduct a short operational test of a microreactor, with a proposed location in Building 7709 on Copper Ridge. Power below 6 MWth is an operational envelope in that strategy, not a stored nameplate. The strategy says DOE authorization will be sought before assembly and operation. The capture attached as the program page is a conference paper, TCR Central Shutdown Rod Fine Motion Control, with publication date August 2022, whose abstract calls TCR a helium-cooled 3 MWt test reactor. That 3 MWt figure is not stored, and the paper is not a program-status page. No operator is named. The record stays an announced test proposal with no thermal rating. Last checked 19 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019); ORNL: TCR Central Shutdown Rod Fine Motion Control (August 2022)
What would change this
An ORNL or DOE program-status page, not this conference paper, stating whether the Building 7709 test was authorized, built, or ended. Next scheduled check: 19 Jan 2027.
- Design identified: Not disclosed in the reviewed evidence. The strategy gives a pre-conceptual envelope, including fuel options and power below 6 MWth. It does not select a design version or a single rating. Last checked 19 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
A design selection that replaces the 2019 pre-conceptual envelope with one fuel form and one rating. Next scheduled check: 19 Jan 2027.
- Developer or proposer. The safety design strategy is for the TCR program at Oak Ridge National Laboratory, and that program is to design, build, and test the microreactor. Last checked 19 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
A later document naming a different developer or an operating contractor for the test. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. The strategy names Building 7709 on Copper Ridge as the proposed reactor location. It does not give a surveyed pad, and the later program-status page was not captured. Last checked 19 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019); ORNL: TCR Central Shutdown Rod Fine Motion Control (August 2022)
What would change this
A program-status page saying whether Building 7709 remained the test location. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. ORNL's 2019 safety design strategy said the program was targeting an aggressive timeline to begin start-up activities in 2023; that target has passed. Neither that document nor ORNL's August 2022 paper on the reactor's shutdown-rod control records a later decision to build, defer or end the test reactor, so the next decision is not disclosed in these sources. Last checked 23 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
An ORNL or DOE statement on the status of the Transformational Challenge Reactor. Next scheduled check: 23 Apr 2027.
- Permissions and public process. ORNL's August 2019 safety design strategy for the Transformational Challenge Reactor says it sets safety-design requirements so that the Department of Energy can ultimately authorize operation of the facility, and that National Environmental Policy Act assessments would be completed before the building was made ready. This describes a planned DOE authorization path, not an NRC license; the document records no completed authorization or environmental assessment. Last checked 23 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
A record of a DOE authorization or NEPA document for the TCR at ORNL. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). ORNL's 2019 safety design strategy names Building 7709 on Copper Ridge, across Melton Valley from the main ORNL campus and formerly home to the Health Physics Research Reactor, as the proposed reactor location, with a control room in a remote building. It says a structural evaluation of Building 7709 would be needed and assumes existing structures do not meet the current design basis. This is a proposed location in an existing DOE facility, not a completed site readiness. Last checked 23 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
A record of Building 7709 being prepared for, or released from, the TCR project. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. ORNL's August 2019 safety design strategy for the Transformational Challenge Reactor says that after the short operational test the reactor would be deactivated and decommissioned, and the core removed for characterization and transport after a cooldown period, with no long-term management of the irradiated core anticipated at the test site. It names no receiving facility, storage arrangement or disposal route. The reviewed sources do not show that the reactor was built or operated, so no spent fuel is recorded in these sources. Last checked 23 Oct 2026. ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019)
What would change this
A DOE authorization, environmental review or program record naming where the irradiated core would go, or showing the reactor was built, would change this answer. Next scheduled check: 22 Oct 2027.
Evidence dates
(2 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- ORNL: Safety Design Strategy for the Transformational Challenge Reactor (ORNL/SPR-2019/1254, August 2019) (government, accessed 3 Oct 2026)
- ORNL: Transformational Challenge Reactor programme page (government, accessed 3 Oct 2026)
- ORNL: TCR Central Shutdown Rod Fine Motion Control (August 2022) (government, published Aug 2022, accessed 19 Oct 2026)
- ORNL: TCR Central Shutdown Rod Fine Motion Control (August 2022) (government, published Aug 2022, accessed 19 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Transformational Challenge Reactor microreactor test proposal at ORNL (2019) — https://smrmap.com/projects/ornl-transformational-challenge-reactor/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Transformational Challenge Reactor microreactor test proposal at ORNL (2019)”. Record reviewed 3 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/ornl-transformational-challenge-reactor/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.