Policy and licensing / Tennessee
Tennessee: SMR policy and licensing
Selected federal, state, territory, and national measures whose official text was opened. This is not a complete list of laws, rules, programs or guidance for any jurisdiction. A jurisdiction without a page here is not a finding that it has no policy, and these pages do not rate or prefer any jurisdiction. Nothing here implies that a project is eligible for, or approved under, any measure.
89 projects in United States →
Federal measures apply in Tennessee as everywhere in the United States and are listed once on the federal page. They are not counted here.
Where licensing stands
Built only from the records on this page. It is not a complete account of the law and not legal advice.
- Authorities named in recorded applications, reviews and decisions
- NRC (4 records)
- Licensing law or framework in the record
- NRC licensing measures are recorded once, on the federal page (10 records).
- Latest recorded step
- Construction permission recorded : Clinch River Unit 1 construction permit
- Open coverage gaps
- Governor or energy instruments (access blocked); Commission or siting instruments (access blocked). What the review of 5 Oct 2026 read.
Laws, rules and executive directives
- Tennessee Public Chapter 530: nuclear supply-chain carry-forward · In effect
2025 Tenn. Pub. Acts ch. 530 (House Bill 1409) · Tennessee General Assembly · affects: Project funding
Tennessee Public Chapter 530 passed on 16 April 2025. Item 90, in Section 36, lets an unexpended nuclear energy supply-chain balance of up to $60,000,000 be carried forward, and that section takes effect upon becoming law. The governor's approval line shows 2025, and the day and month are not legible, so no calendar effective day is stored. Section 64's 1 July 2025 date is the general act date. The act records no award.
Not approved or pending: The approval day and month are not legible, so only the year 2025 is stored for the signature and no calendar effective day is stored. Section 36 takes effect upon becoming a law, so Section 64's 1 July 2025 general date is not this item's effective date. The carry-forward is subject to funding available at 30 June 2025 and to commissioner approval, and those conditions were not opened as a balance or an approval. The $60,000,000 figure is a cap on carrying forward an unexpended balance. It is not recorded as a new award or as a named recipient. Item 76 states no dollar amount. No project is linked. Two other Tennessee PDFs returned an access refusal (HTTP 403) and are not this record. (Record checked .)
Bills, proposed rules and consultations
- None recorded.
Funding and support programs
- None recorded.
Regulatory guidance and inspector policies
- None recorded.
Recorded permissions and applications for tracked projects located in Tennessee
Listed by project location only, with each action's issuing authority recorded. The jurisdiction measures above do not themselves authorize reactor construction or operation.
Site applications and decisions
- Clinch River Nuclear Site early site permit ESP-006 — TVA Clinch River BWRX-300
Site permission · Issued / approved · NRC · decided 19 Dec 2019 · submitted 12 May 2016 · permit ESP-006
NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.
Sources: U.S. NRC: Clinch River Nuclear Site early site permit ESP-006
Construction applications and decisions
- Clinch River Unit 1 construction permit — TVA Clinch River BWRX-300
Construction permission · Issued / approved · NRC · decided 28 Sep 2026 · submitted 28 Apr 2025 · permit CPAR-2 · docket 50-615 · ADAMS ML26244A257, ML26243A056 · 91 FR 63311
The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: Federal Register 91 FR 63311 (5 Oct 2026): Clinch River Nuclear Unit 1 construction permit and record of decision; TVA construction permit announcement; NRC: TVA Clinch River construction permit application; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056) - Kairos Hermes 2 construction permit — Kairos Hermes 2
Construction permission · Issued / approved · NRC · decided 21 Nov 2024 · submitted 14 Jul 2023 · permit CPTR-7, CPTR-8 · docket 50-611, 50-612 · ADAMS ML24324A021, ML24324A022 · 89 FR 94767
The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.
Sources: Federal Register 89 FR 94767 (29 Nov 2024): Hermes 2 test reactor facility construction permits; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 2 construction permit - Kairos Hermes 1 construction permit — Kairos Hermes 1
Construction permission · Issued / approved · NRC · decided 14 Dec 2023 · submitted 29 Sep 2021 · permit CPTR-6 · docket 50-7513 · ADAMS ML23338A258 · 88 FR 88137 · 91 FR 28629
The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.
Sources: Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit; Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 1 construction permit
What this review has read for Tennessee
As of 5 Oct 2026. Bounded review concluded with access gaps. A published record above is separate from research coverage: a class can be blocked or unreviewed even where records are published. Coverage for every state and territory.
- Statutes, session laws and bills: Evidence read. Senate Joint Resolution 887 (adopted by the Senate 29 to 1 on 2 April 2026, supporting the state's response to a federal nuclear-lifecycle request) was read. It is a resolution, not a statute; the history then shows a referral to the Delayed Bills Committee and no House vote. Public-chapter files on the Secretary of State's site returned an access refusal (HTTP 403).
- Governor or energy instruments: Access blocked. The Secretary of State's copy of Executive Order 101 (signed 16 May 2023, per the state's nuclear council report) returned an access refusal (HTTP 403) on 4 October 2026. On 5 October 2026 the Secretary of State's executive-orders page returned an access refusal (HTTP 403) and the governor's executive-orders page returned a not-found error (HTTP 404). Governor's news releases were read; they are not the order.
- Commission or siting instruments: Access blocked. A radiation-control rule file returned an access refusal (HTTP 403) and a rulemaking file's connection was reset.
- Funding measures and awards: Evidence read. Public Chapter No. 530 (2025 appropriations act) was read: a nuclear supply-chain carry-forward capped at $60,000,000. The approval day is not legible on the copy. The appropriation text for a later addition to the Nuclear Energy Fund was not located.
Sources read (7):
- www.tn.gov/governor/news/2023/5/16/gov--lee-issues-executive-order-to-advan… · checked 4 Oct 2026
- www.tn.gov/environment/program-areas/energy/tneac.html · checked 4 Oct 2026
- www.tn.gov/ecd/resources/openecd/nuclear-fund-project-database0.html · checked 4 Oct 2026
- capitol.tn.gov/Archives/Joint/staff/budget-analysis/appropriationbills/2025… · checked 4 Oct 2026
- www.capitol.tn.gov/Bills/114/Bill/SJR0887.pdf · checked 5 Oct 2026
- wapp.capitol.tn.gov/apps/BillInfo/Default?BillNumber=SJR0887&ga=114 · checked 5 Oct 2026
- www.tn.gov/governor/news/2026/4/23/gov--lee-marks-the-close-of-the-2026-leg… · checked 5 Oct 2026
Sources that could not be read (9):
- www.capitol.tn.gov/Bills/114/Chapter/PC0517.pdf · checked 4 Oct 2026 · a not-found error (HTTP 404)
- www.tn.gov/content/dam/tn/environment/radiation/documents/rulemaking-notice… · checked 4 Oct 2026 · connection reset
- publications.tnsosfiles.com/rules_all/2018/0400-20-10.20240303.pdf · checked 4 Oct 2026 · an access refusal (HTTP 403)
- publications.tnsosfiles.com/acts/113/pub/pc0981.pdf · checked 4 Oct 2026 · an access refusal (HTTP 403)
- publications.tnsosfiles.com/pub/execorders/exec-orders-lee101.pdf · checked 4 Oct 2026 · an access refusal (HTTP 403)
- www.capitol.tn.gov/Bills/113/Chapter/PC0418.pdf · checked 4 Oct 2026 · a not-found error (HTTP 404)
- publications.tnsosfiles.com/acts/114/pub/pc1142.pdf · checked 5 Oct 2026 · an access refusal (HTTP 403)
- sos.tn.gov/products/division-publications/executive-orders-governor-bill-lee · checked 5 Oct 2026 · an access refusal (HTTP 403)
- www.tn.gov/governor/executive-orders.html · checked 5 Oct 2026 · a not-found error (HTTP 404)