Projects / United Kingdom · Siting

Rolls-Royce SMR Wylfa

The UK selected Wylfa in November 2025, where three Rolls-Royce SMRs totalling 1,410 MWe are planned, with the project still at the siting stage.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 5 of 10 listed sources have a publication or document date recorded here; the newest is 24 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
13 Apr 2026 · Contract: Wylfa program design contract signed. Contract initiates site-specific design and planning before a future investment decision. Source: GBE Nuclear and Rolls-Royce SMR contract. Updates entry
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
Same design
6 tracked: 5 siting. Separately: 1 suspended. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR.

Description

GBE-N's 13 April 2026 contract covers three Rolls-Royce SMRs and site-specific design/planning before an investment decision. The proposed plant was named Gwyndod in June 2026. GBE-N's March 2026 supplier Q&A separates RRSMR's nuclear/civil-island scope from GBE-N's other station works, integrated by a delivery partner. Its 24 September newsletter announcement reports launch of Delivery Partner procurement. Its pipeline forecasts investigations and archaeology, without committing implementation. No partner award or nuclear construction start is established. GOV.UK separately states £2.5bn of program funding, a £2.6bn Spending Review allocation for the contract and wider delivery, and over £2.5bn of investment into the site in the naming announcement. These differently scoped statements are not additive or proof of disbursement.

Key facts

Design
Rolls-Royce SMR (SMR)
Technology
Pressurized water reactor (PWR) · light water. The 2024 SMR Technology Catalogue describes a three-loop pressurized water reactor, so no integral layout is recorded.
Reactor vessel of this design
7.82 m tall, 4.2 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 79.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Not recorded
Vendor for linked design
Rolls-Royce SMR
Location
Wylfa Newydd site · United Kingdom · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Wylfa Rolls-Royce SMR entry (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); existing nuclear site area selected for Rolls-Royce SMR. No nuclear concrete is claimed here.
Coordinates
53.4168183, -4.4837327 · site-area point (approximate)
Electrical capacity
1410 MWe (net) · scope: plant
Thermal capacity
Not recorded
Modules planned
3
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
6 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Rolls-Royce SMR Wylfa is recorded at Wylfa Newydd site, Wales, United Kingdom. Operator: No operator is recorded. Recorded vendor: Rolls-Royce SMR. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'wylfa-rolls-royce-smr-nuclear-power-plant-1' (53.4168183, -4.4837327)

Recorded electrical output is 1410 MWe (net), scope plant. Modules planned: 3. Thermal output is not recorded on this project. The linked design record states 1358 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 470 MWe (net); the project figure is kept separate.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Contractor

Source-backed project statement Great British Energy – Nuclear's 13 April 2026 release says it signed a contract with Rolls-Royce SMR that begins technology design and requires site-specific design, regulatory engagement and planning ahead of a future final investment decision. That is an explicit preparatory design contract with the reactor vendor, not a construction award. No construction or delivery-partner award is shown in the releases read. GBE Nuclear and Rolls-Royce SMR contract

Funding and government decisions
  • Funder or lender named for this projectUK Government · sourceThe 2025 Spending Review allocated £2.6bn for the contract and wider program delivery. This is not a Wylfa-only plant budget, closed financing or evidence of disbursement.
Source-backed project statement

GOV.UK's 13 April 2026 contract announcement says 2.6 billion pounds was allocated in the 2025 Spending Review to enable the Great British Energy - Nuclear and Rolls-Royce SMR contract and wider program delivery. The November 2025 site announcement says the SMR program is backed by 2.5 billion pounds of government funding. These are program allocations, not a Wylfa plant budget, closed financing or disbursement, and no investment decision has been taken. GBE Nuclear and Rolls-Royce SMR contract; Wylfa selected for UK SMRs

Fuel
  • Fuel form stated for Rolls-Royce SMRUO2
No project-specific fuel supply arrangement is recorded as a structured fact.

Great British Energy – Nuclear's 13 April 2026 contract release limits the contract to design, regulatory engagement and planning, and neither it nor the 13 November 2025 site announcement names a fuel supplier, fuel contract or delivery for the Wylfa units. GBE Nuclear and Rolls-Royce SMR contract; Wylfa selected for UK SMRs

Not found in the sources we checked (2): Customer or offtaker; Comparable schedule revision
Customer or offtaker

Great British Energy – Nuclear's 13 November 2025 site announcement and 13 April 2026 contract release say the Wylfa project would deliver up to 1.5 GW to the grid, and at least 1.4 GWe for around three million homes, but neither names a buyer, contracted quantity or power purchase agreement. Wylfa selected for UK SMRs; GBE Nuclear and Rolls-Royce SMR contract

Comparable schedule revision

Comparable schedule revision not established. World Nuclear News reported on 13 November 2025 that Great British Energy - Nuclear would start site activity in 2026 with the aim of Wylfa's SMRs supplying power from the mid-2030s. The same article's early-2030s phrase describes earlier site-assessment criteria, not a Wylfa target, and the record's events hold no revision pair. WNN: UK selects Wylfa for at least three Rolls-Royce SMRs

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Assessments of the design (not of this site)

(2)
  • Rolls-Royce SMR Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.
    Sources: ONR Generic Design Assessment: Rolls-Royce SMR

    Status confirmed on against ONR Generic Design Assessment: Rolls-Royce SMR. This confirms the recorded status only; the general record check date remains separate.

  • Rolls-Royce SMR UK Generic Design Assessment, Step 2 — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 30 Jul 2024
    The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR Generic Design Assessment: Rolls-Royce SMR; Environment Agency and Natural Resources Wales: GDA Step 2 of the Rolls-Royce SMR

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(4 notes, 1 not yet reviewed)
  • Evidence review. The opened GOV.UK page is mostly Welsh, that Wylfa on Anglesey was chosen, and that the project will supply up to 1.5 GW. It says that page does not name Rolls-Royce or three units. The stored 1,410 MWe and three modules stay. The English text on the same page repeats the selection and the up-to-1.5 GW ceiling. A separate World Nuclear News article names three Rolls-Royce reactors at Wylfa, an at-least-three headline, a potential of up to eight, and a 470 MWe design rating. Those figures are not used to overwrite the stored plant rating or count. The 13 April 2026 contract page does not contain the word Wylfa, so its three-unit sentence is not attached to this site. Last checked 20 Oct 2026. Wylfa selected for UK SMRs; WNN: UK selects Wylfa for at least three Rolls-Royce SMRs; GOV.UK: Local community names new Wylfa power station (26 June 2026); GBE-N: September Spark newsletter announcement
    What would change this

    A permission or final investment decision that states this plant's committed unit count and output, rather than a ceiling. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. The April 2026 contract says Rolls-Royce SMR will begin site-specific design, regulatory engagement and planning work for Wylfa ahead of a future final investment decision, which is the consequential decision still to come. Before construction, planning consent through the national infrastructure process, ONR licensing and environmental permits are also needed. No date for the investment decision or a consent application is given in the sources reviewed. Last checked 23 Oct 2026. GBE Nuclear and Rolls-Royce SMR contract; New nuclear at Wylfa: what happens next?
    What would change this

    A final investment decision, a development consent application, or a published consenting timetable for Wylfa. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The April 2026 GBE-N contract with Rolls-Royce SMR starts site-specific design, regulatory engagement and planning processes ahead of a future final investment decision. Senedd Research (December 2025) says building needs ONR site licensing and consent, Natural Resources Wales environmental permits and planning permission, which for a plant this size would go through the UK Nationally Significant Infrastructure Project process. No application for these consents is shown in the sources reviewed. Last checked 23 Oct 2026. GBE Nuclear and Rolls-Royce SMR contract; New nuclear at Wylfa: what happens next?
    What would change this

    Launch of statutory consultation, a development consent application, or an ONR licensing application for the Wylfa SMR plant. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). World Nuclear News reports that in March 2024 the government agreed to buy Hitachi's former new-nuclear land at Wylfa. Senedd Research says Wylfa already holds a nuclear site license for the old station, but ONR expects new installations to need relicensing, and the UK Government aims for the SMRs to connect to the grid by the mid-2030s. The grid date is an ambition; the sources reviewed do not describe a grid connection agreement or cooling-water arrangement. Last checked 23 Oct 2026. WNN: UK selects Wylfa for at least three Rolls-Royce SMRs; New nuclear at Wylfa: what happens next?
    What would change this

    A GBE-N grid connection offer, consultation documents describing cooling water, or an ONR relicensing decision. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(5 of 10 sources with a publication or document date)
Latest dated listed source publication: GBE-N: September Spark newsletter announcement: 24 Sep 2026.Latest dated recorded event: Wylfa program design contract signed: 13 Apr 2026.5 of 10 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(10)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Rolls-Royce SMR Wylfa — https://smrmap.com/projects/rolls-royce-smr-wylfa/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Rolls-Royce SMR Wylfa”. Record reviewed 6 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/rolls-royce-smr-wylfa/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.