Projects / France · Licensing
Stellaria Alvin experimental reactor (INB Alpha) at Cadarache
Stellaria's Alvin at CEA Cadarache in France is an experimental molten-salt reactor of 200 kWth, not a power plant, in licensing as part of INB Alpha.
Current status
- How current
- General record check . Bounded evidence review . 1 of 6 listed sources has a publication or document date recorded here: 23 Apr 2026. A listed page was last updated 14 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: Stellaria INB Alpha creation-authorization application. An application under review is not a permit. All permissions and applications
- Latest development
- 16 Jun 2026 · Regulatory step: Ministry requests more information on Stellaria's INB Alpha application. Following ASNR's analysis, the ministry asked Stellaria on 16 June 2026 to complete its INB Alpha file. Source: ASNR, PRM projects and technical exchanges (14 October 2026 update) (page updated 14 Oct 2026). Updates entry
More on this development
ASNR's technical review is suspended until that information arrives. A request for information, not a refusal or an authorization.
- Next dated milestone
- First criticality: 2030 (target). Alvin: company target for first criticality. This is not an achieved milestone. Source: Stellaria: INB Alpha programme and experimental configurations (published 23 Apr 2026).
- Selected limitations
- Electrical output is not recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Molten salt reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
ASNR's PRM list, fetched 5 October 2026, describes ALVIN as a 200 kWth experimental molten-salt reactor. Earlier secondary reports said 100 kW; the stored rating is the ASNR list figure. Stellaria filed the creation-authorization application for INB Alpha on 19 December 2025. MSNR referred the file to ASNR on 22 December 2025 and, after ASNR's analysis, requested further information on 16 June 2026; technical review is suspended until it is provided. The same application covers GLENN, a molten-salt fuel synthesis workshop on the site. No creation authorization is recorded. A 2030 start in the earlier reports is a plan, not an ASNR date. Stellaria’s 23 April 2026 description targets Alvin criticality in 2030 and a later modified MegAlvin configuration in 2032; those are company targets, not ASNR decisions.
Key facts
- Design
- Alvin experimental molten-salt reactor (SMR)
- Technology
- Molten salt reactor (MSR) · molten salt
- Operator(s)
- Stellaria
- Vendor for linked design
- Stellaria
- Location
- CEA Cadarache · France · precision: site area (named plant, laboratory, base, port, campus or parcel)
OpenStreetMap Nominatim point for 'Center d'Études Nucléaires de Cadarache'; center point, not a facility plot. - Coordinates
- 43.6876, 5.7556 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- 0.2 MWth (nameplate; basis unspecified)
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Stellaria Alvin experimental reactor (INB Alpha) at Cadarache is recorded at CEA Cadarache, Provence-Alpes-Côte d'Azur, France. Operator: Stellaria. Recorded vendor: Stellaria. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Calogena nuclear heating plant at CEA Cadarache.
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Center d'Études Nucléaires de Cadarache'
Electrical output is not recorded on this project. Modules planned: 1. Recorded thermal output is 0.2 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorStellaria
- Reactor supplier
- Vendor for the linked designStellaria
- Contractor
Source-backed project statement On 23 April 2026 Stellaria said it had signed a letter of intent with the CEA for a feasibility study of an ALPHA installation at Cadarache. The described installation would house the Alvin test, a demonstration reactor and a salt fabrication facility. This is a preparatory study arrangement, not an awarded construction contract. Stellaria: INB Alpha programme and experimental configurations
- Funding and government decisions
Source-backed project statement Stellaria's 23 April 2026 page says a 23 million euro round had closed and would complement 10 million euros of non-dilutive France 2030 Innovative Reactors funding. The page says that money will finance the technical and regulatory studies. It does not say construction costs have been paid. Stellaria: INB Alpha programme and experimental configurations
- Fuel
- Project fuel information is described in the source-backed statement below.
Source-backed project statement The 23 April 2026 letter of intent describes a salt fabrication facility at Cadarache intended to supply the prototype and the demonstration reactor. ASNR records a 19 December 2025 application to create an ALPHA installation including a molten-salt fuel workshop named GLENN at CEA Cadarache, and ministry requests for more information on 16 June 2026. The workshop is applied for, not approved, and no fuel delivery is stated. Stellaria: INB Alpha programme and experimental configurations; ASNR, PRM projects and their fuel-fabrication plants
Not found in the sources we checked (2): Customer or offtaker; Comparable schedule revision
- Customer or offtaker
Stellaria's 23 April 2026 page says the company signed a commercial contract with Equinix, described there as a pre-order so Equinix data centers can use energy autonomy from a nuclear reactor with renewable fuel. That sentence does not name Alvin or MegAlvin. No research user or electricity buyer is named for the Cadarache experiment. Stellaria: INB Alpha programme and experimental configurations
- Comparable schedule revision
- A documented comparable revision is recorded. It is not a completed source review.
Comparable schedule revision not established. The 23 April 2026 page gives one date for each of three different machines: Alvin scheduled for 2030, MegAlvin by 2032 after the Alvin program, and the commercial Stellarium in 2035. Those are not two forecasts of the same milestone for the same unit. No later change to the Alvin 2030 date is stated. Stellaria: INB Alpha programme and experimental configurations
Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
- Programs and agreements naming the project
Timeline
Recorded developments
- · Regulatory step
Ministry requests more information on Stellaria's INB Alpha application - · Recorded development
Stellaria and CEA sign letter of intent on INB Alpha feasibility at Cadarache - · Recorded development
MSNR asks ASNR to review the Stellaria INB Alpha application - · Application submitted
Application submitted: Stellaria INB Alpha creation-authorization application
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · First criticality
Alvin: company target for first criticality - Target · Planned step
INB Alpha: company target to convert the facility to MegAlvin
Schedule changes
The same milestone as stated at two dates. A revised target is still a target; the earlier target is kept for comparison and no longer counts as upcoming.
- Alvin: company target for first criticality
2029 (stated 12 Mar 2025) → 2030 (stated 23 Apr 2026) · Moved later
Source: Stellaria: APS, Alvin, MegAlvin and Stellarium (published 12 Mar 2025); Stellaria: INB Alpha programme and experimental configurations (published 23 Apr 2026).
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- Stellaria INB Alpha creation-authorization application
Construction permission sought · Under review · ASNR · submitted 19 Dec 2025
ASNR states that Stellaria filed a creation-authorization application on 19 December 2025 for INB Alpha, including the ALVIN research reactor at CEA Cadarache. MSNR referred it to ASNR on 22 December 2025. Following ASNR analysis, MSNR requested further information on 16 June 2026. The page updated 14 October says technical review is suspended pending that information; it does not separately date the suspension. No creation authorization is recorded.
Sources: ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update)
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. The source review uses the ASNR list for a 19 December 2025 creation-authorization application for INB ALPHA and the ALVIN research reactor, rated 200 kWth, the stored 0.2 MWth, and it keeps GLENN off this reactor. The 14 October 2026 ASNR page says Stellaria filed that application with the nuclear-safety minister for INB ALPHA, containing the ALVIN research reactor on the Cadarache site of the CEA. After ASNR's analysis, MSNR sent requests for further information on 16 June 2026 and technical review is suspended until the information arrives. The same page has a separate row for INB ALPHA / GLENN, a molten-salt fuel synthesis workshop, which is not this reactor. Stellaria's 23 April 2026 page targets the Alvin critical experiment in 2030 and a later modification to MegAlvin in 2032. Those are company targets. World Nuclear News in January 2026 called Alvin a 100 kW reactor aimed at 2030. That 100 kW figure is not stored. No creation authorization is stated. The NEA dashboard capture is a challenge page and is not quoted. Last checked 20 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update); Stellaria: INB Alpha programme and experimental configurations; WNN: Stellaria seeks permission to build experimental reactor
What would change this
Stellaria's response to the requests for further information of 16 June 2026, or an ASNR or ministerial decision on the ALVIN creation authorization. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. The next recorded step is Stellaria's reply to the ministry's 16 June 2026 requests for further information on the INB Alpha application, after which the technical review and a ministerial decision can follow. Stellaria's 2030 criticality aim is a company target, not a regulatory date. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
Stellaria's reply to the requests, an ASNR opinion or a ministerial decision on INB Alpha. Next scheduled check: 21 Jan 2027.
- Permissions and public process. ASNR records Stellaria's 19 December 2025 application to the minister to create INB Alpha, including the ALVIN research reactor on CEA's Cadarache site, and the ministry's requests for further information on 16 June 2026. This is an application under review, not an authorization. The opened ASNR page records no public inquiry or decision. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
An ASNR opinion, public-inquiry notice or ministerial decision on the INB Alpha creation authorization. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Stellaria's 23 April 2026 page says a site has been identified to study whether the ALPHA installation can be placed at the CEA Cadarache center in Saint-Paul-Lez-Durance. ASNR records the 19 December 2025 application as locating the ALVIN research reactor on the CEA Cadarache site. No lease, water right or grid connection is stated. Last checked 23 Oct 2026. Stellaria: INB Alpha programme and experimental configurations; ASNR, PRM projects and their fuel-fabrication plants
What would change this
A lease, water right or grid connection for the ALPHA installation at Cadarache. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The 23 April 2026 page lists fission-gas handling as a MegAlvin design topic to be tested. It does not state a spent-fuel storage, transport or waste arrangement for Alvin or MegAlvin. Last checked 23 Oct 2026. Stellaria: INB Alpha programme and experimental configurations
What would change this
A spent-fuel or radioactive-waste arrangement for the ALPHA installation. Next scheduled check: 21 Jan 2027.
Evidence dates
(1 of 6 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(6)
- WNN: Stellaria seeks permission to build experimental reactor (news report, accessed 2 Oct 2026)
- Sfen RGN: Stellaria's DAC filed (news report, accessed 2 Oct 2026)
- ASNR, PRM projects and their fuel-fabrication plants (regulator, accessed 3 Nov 2026)
- NEA SMR Digital Dashboard edition 4.0 (per-design siting entries) (IAEA/NEA, accessed 2 Oct 2026)
- Stellaria: INB Alpha programme and experimental configurations (company, published 23 Apr 2026, accessed 18 Oct 2026)
- ASNR, PRM projects and technical exchanges (14 October 2026 update) (regulator, page updated 14 Oct 2026, accessed 3 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Stellaria Alvin experimental reactor (INB Alpha) at Cadarache — https://smrmap.com/projects/stellaria-alvin-cadarache/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Stellaria Alvin experimental reactor (INB Alpha) at Cadarache”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/stellaria-alvin-cadarache/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.