Projects / South Africa · Announced

Stratek Global HTMR-100 at Zilkaats Estate

Stratek Global announced in July 2025 that the owners of Zilkaats Estate, near De Wildt, had offered land for an HTMR-100 pebble-bed reactor (100 MWt, 35 MWe).

Current status

Stage
Announced
How current
General record check . Bounded evidence review . None of the 2 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • No operator is recorded.
  • No map pin is shown for this record.
  • State or province is not recorded.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
High-temperature gas-cooled reactor. How it works, with a 3D view.
Schematic of HTR-PM, this type's example. On the left, a tall reactor vessel holds a bed of fuel spheres inside a graphite reflector, with fuel tubes above and below.
Schematic of HTR-PM, this type's example.

Description

Environmental assessment and licensing had not begun; Stratek said construction could start within two years pending approval and financing.

Key facts

Design
HTMR-100 (SMR)
Technology
High-temperature gas-cooled reactor (HTGR) · helium
Reactor vessel of this design
15.7 m tall, 5.6 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 211.flange outer diameter not an unqualified diameter the parenthesis wraps onto the next printed line Diameter is measured at the outer flange.SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Not recorded
Vendor for linked design
Stratek Global
Location
Zilkaats Estate, De Wildt · South Africa · precision: site area (named plant, laboratory, base, port, campus or parcel)
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Named site, no map pin
Electrical capacity
35 MWe (gross/net unspecified) · scope: module
Thermal capacity
100 MWth (nameplate; basis unspecified)
Modules planned
1
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Stratek Global HTMR-100 at Zilkaats Estate is recorded at Zilkaats Estate, De Wildt, state or province not recorded, South Africa. Operator: No operator is recorded. Recorded vendor: Stratek Global. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.

Recorded electrical output is 35 MWe (gross/net unspecified), scope module. Modules planned: 1. Recorded thermal output is 100 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Fuel
  • Fuel form stated for HTMR-100 (catalog profile as of 14 Feb 2025)TRISO particles in pebbles; LEU/Th
No project-specific fuel supply arrangement is recorded as a structured fact.

Stratek Global's July 2025 article says the development could potentially host a nuclear fuel facility and shows an HTMR-100 fuel ball, but it names no fuel manufacturer, quantity or supply commitment for the Zilkaats reactor. Koeberg fuel in another article of the same issue is unrelated. Stratek Global: Nuclear Network Africa, July 2025

Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
Customer or offtaker

Stratek Global's July 2025 Nuclear Network Africa article says Zilkaats Estate offered a site for one HTMR-100, and its chairman calls the plan more than a power solution for the Zilkaats development, but no buyer, quantity or supply agreement is stated. The estate is the land offeror, and nearby Necsa at Pelindaba is mentioned only as location context. Stratek Global: Nuclear Network Africa, July 2025

Contractor

Stratek Global's July 2025 article says Stratek, the vendor, will establish an SMR at Zilkaats Estate on a site the estate offered, with construction pending regulatory approval and financing. No engineering or construction contractor is named, no environmental assessment or license application is reported, and the JKDA Architects credit is for a design image, not a stated engineering contract. Stratek Global: Nuclear Network Africa, July 2025

Funding and government decisions

Stratek Global's July 2025 article says construction could begin within two years pending regulatory approval and financing, which shows financing was not yet in place. It states no reactor cost, funder or amount, and the R5.7 billion figure is the value of the privately owned estate. Stratek Global: Nuclear Network Africa, July 2025

Comparable schedule revision

Comparable schedule revision not established. Stratek Global's July 2025 article gives one conditional statement, that construction could begin within two years pending regulatory approval and financing, and no calendar start date. No later source restates it, so no schedule revision is shown. Stratek Global: Nuclear Network Africa, July 2025

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes, 1 not yet reviewed)
  • Evidence review. A July 2025 article says Stratek Global announced an SMR at Zilkaats Estate on the Gauteng–North West border, and that the estate offered a site for one HTMR-100 reactor delivering 35 MW of electricity from 100 MW of heat. Those ratings and the singular reactor match the stored values and are not changed. Construction could begin within two years pending regulatory approval and financing. That is a condition, not a start. A second saved source returned a server error (HTTP 503) and is not used. The nearby Necsa facility at Pelindaba is context, not this site. Last checked 20 Oct 2026. Stratek Global: Nuclear Network Africa, July 2025
    What would change this

    A National Nuclear Regulator application or decision for the Zilkaats HTMR-100, or a notice that the land offer lapsed. Next scheduled check: 20 Jan 2027.

  • Site location recorded as disclosed. The article names Zilkaats Estate, on the Gauteng–North West border, as the place offered for the reactor. It gives no coordinates. The nearby Pelindaba reference is not used as the site. Last checked 20 Oct 2026. Stratek Global: Nuclear Network Africa, July 2025
    What would change this

    A surveyed plot inside Zilkaats Estate. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. Stratek Global's July 2025 newsletter says that, pending regulatory approval and financing, construction at Zilkaats Estate could begin within two years, that is by about mid-2027. Regulatory approval and financing are the named prerequisites; neither is reported as obtained, and the date is a company estimate. Last checked 23 Oct 2026. Stratek Global: Nuclear Network Africa, July 2025
    What would change this

    An NNR license application, a financing announcement or a revised Stratek schedule. Next scheduled check: 23 Apr 2027.

  • Permissions and public process: Not disclosed in the reviewed evidence. Stratek Global's July 2025 newsletter announcing the HTMR-100 at Zilkaats Estate says construction is pending regulatory approval and financing, and that both partners are committed to safety and public engagement in line with National Nuclear Regulator and IAEA standards. It names no NNR license application, environmental authorization or public participation process under way. Last checked 23 Oct 2026. Stratek Global: Nuclear Network Africa, July 2025
    What would change this

    An NNR license application or environmental authorization process for the Zilkaats reactor. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Stratek Global's July 2025 newsletter says the owners of Zilkaats Estate, a private development on the Gauteng-North West border near Necsa's Pelindaba facility, have offered a site for the HTMR-100, a helium-cooled design that it says needs no large water source. An offered site is not a lease or transfer, and no grid connection or exact plot is described. Last checked 23 Oct 2026. Stratek Global: Nuclear Network Africa, July 2025
    What would change this

    A signed land agreement between Stratek and Zilkaats Estate or an environmental application naming the plot. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 2 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.2 of 2 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(2)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Stratek Global HTMR-100 at Zilkaats Estate — https://smrmap.com/projects/stratek-zilkaats/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Stratek Global HTMR-100 at Zilkaats Estate”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/stratek-zilkaats/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.