Projects / India · Siting

Tarapur SMR-55 lead proposal

The Tarapur SMR-55 lead is separate from the BSMR-200 proposal and operating units.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 2 of 5 listed sources have a publication or document date recorded here; the newest is 16 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 4 Feb 2026 · Announcement: Tarapur SMR-55 lead proposal documented. DAE's SMR-55 lead proposal at Tarapur is separate in capacity and stage from the BSMR-200 proposal and the operating conventional units. Source: DAE parliamentary answer naming lead sites. Updates entry
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR, this type's example. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR, this type's example.

Description

World Nuclear News reported in March 2025 that two lead units were planned at a DAE site by 2033; its December 2025 report described an SMR-55 lead unit proposed at Tarapur. A selected unit count remains unrecorded. DAE's 5 August 2026 written answer states in-principle approval for engineering and construction of SMR-55 and Atomic Energy Commission approval of Tarapur as the site, but gives no SMR-55 unit count or project cost. World Nuclear News reports that NPCIL announced the Detailed Project Report, co-developed with BARC, on 1 October 2026. The report does not establish financial sanction or construction commencement.

Key facts

Design
BARC SMR-55 (SMR)
Technology
Pressurized water reactor (PWR) · unknown. India's Department of Atomic Energy says the SMR-55 is based on a pressurized water reactor design.
Operator(s)
Not recorded
Vendor for linked design
Bhabha Atomic Research Centre
Location
Tarapur · India · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates of the named Tarapur nuclear power plant from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker); BSMR-200 lead proposal at Tarapur.
Coordinates
19.8294, 72.6617 · site-area point (approximate)
Electrical capacity
55 MWe (gross/net unspecified) · scope: module
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Tarapur SMR-55 lead proposal is recorded at Tarapur, Maharashtra, India. Operator: No operator is recorded. Recorded vendor: Bhabha Atomic Research Centre. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Tarapur BSMR-200 lead proposal.

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'tarapur-nuclear-power-plant-5' (19.8294, 72.6617)

Recorded electrical output is 55 MWe (gross/net unspecified), scope module. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
Contractor

Source-backed project statement World Nuclear News reported on 16 October 2026 that NPCIL announced on 1 October 2026 the release of the SMR-55 Detailed Project Report, co-developed by NPCIL and BARC, for the lead unit proposed at Tarapur. DAE's 5 August 2026 answer records in-principle approval for engineering and construction and AEC approval of Tarapur as the site. Co-developing a project report is preparatory work, not an engineering, procurement and construction award or a financial sanction. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026); World Nuclear News: India's project milestones and SMR-55 report

Not found in the sources we checked (4): Customer or offtaker; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

World Nuclear News reported on 16 October 2026 that NPCIL envisages the SMR-55 serving remote and off-grid electrification, data centers and captive industrial power. Those are intended applications. Neither that report nor DAE's 5 August 2026 Lok Sabha answer names a buyer or agreement for the Tarapur SMR-55's output. World Nuclear News: India's project milestones and SMR-55 report

Funding and government decisions

DAE's 5 August 2026 Lok Sabha answer records in-principle approval for engineering and construction of the SMR-55 and AEC approval of Tarapur, but no financial sanction or amount for it. A Rs 20,000 crore Nuclear Energy Mission provision in the same answer covers small modular reactors as a class, not this unit. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026)

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

World Nuclear News' 16 October 2026 report on the SMR-55 project report and DAE's 5 August 2026 answer name no fuel supplier, contract or delivery for the Tarapur SMR-55. A Nuclear Fuels Complex item in the same report concerns the heavy-water reactor fleet. World Nuclear News: India's project milestones and SMR-55 report

Comparable schedule revision

Comparable schedule revision not established. The checked sources do not provide two dated statements revising the same Tarapur SMR-55 milestone. Earlier reporting of two lead units and a program target is retained separately; a later source’s omission of a unit count does not establish a schedule change. WNN: Maharashtra and Andhra Pradesh proposed for first Indian SMRs

Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(4 notes, 1 not yet reviewed)
  • Evidence review. The Department of Atomic Energy says BARC has undertaken the design, development and deployment of the 55 MWe SMR-55 as a demonstration reactor, and its written Lok Sabha answer of 5 August 2026 states that in-principle approval for engineering and construction has been received and that the Atomic Energy Commission has approved Tarapur, Maharashtra as the site. World Nuclear News reported on 12 March 2025 that the first two lead units would be built at a DAE site by 2033, and on 10 December 2025 that the SMR-55 lead unit is also proposed for Tarapur, so the sources differ between one lead unit and twin lead units. WNN reported on 16 October 2026 that NPCIL announced the release of the SMR-55 Detailed Project Report on 1 October 2026 and that the reactor was co-developed by NPCIL and BARC; NPCIL's own release was not opened. A project report is not sanction: the DAE answer reports no financial approval for the SMR-55, and construction is estimated at 60 to 72 months from that approval. The saved DAE answer does not contain the stored cost of about Rs 7,000 crore or the 'two lead units' wording, and the PIB answer page returned an access refusal (HTTP 403). The stored 55 MWe module rating, BARC as vendor, empty operator list, unstored module count and siting stage stay. The next documentary decision is administrative and financial sanction for the SMR-55 lead project. Last checked 19 Oct 2026. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026); WNN: Minister updates parliament on Indian SMR project; WNN: Maharashtra and Andhra Pradesh proposed for first Indian SMRs; World Nuclear News: India's project milestones and SMR-55 report
    What would change this

    A DAE or Cabinet administrative and financial sanction for the SMR-55 lead units (stating the unit count), NPCIL's Detailed Project Report release, or an AERB siting consent for Tarapur would change this record. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The next consequential step is financial approval of the SMR-55: DAE's August 2026 answer estimates construction at 60 to 72 months from receipt of financial approval, and the detailed project report was released on 1 October 2026, according to World Nuclear News. Unlike the BSMR-200, whose sanction proposal the answer says has been cleared by the Atomic Energy Commission, no sanction step is reported for the SMR-55. Last checked 23 Oct 2026. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026); World Nuclear News: India's project milestones and SMR-55 report
    What would change this

    Administrative and financial sanction or start of construction for the SMR-55 at Tarapur. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. DAE's written answer of 5 August 2026 says the SMR-55 has in-principle approval for engineering and construction and that the Atomic Energy Commission has approved Tarapur, Maharashtra, as its site. World Nuclear News reported that NPCIL released the SMR-55 detailed project report on 1 October 2026. These are internal government approvals and planning documents; regulator consent and financial sanction are not reported in the sources reviewed. Last checked 23 Oct 2026. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026); World Nuclear News: India's project milestones and SMR-55 report
    What would change this

    Administrative and financial sanction for the SMR-55, or an AERB siting consent. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). DAE's August 2026 answer says the Atomic Energy Commission approved Tarapur, Maharashtra, as the SMR-55 site, and World Nuclear News reported in December 2025 that the lead unit is proposed at the Tarapur Atomic Power Station site. The sources reviewed do not describe the plot, grid connection or cooling arrangements for the SMR-55 at Tarapur. Last checked 23 Oct 2026. Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026); WNN: Maharashtra and Andhra Pradesh proposed for first Indian SMRs
    What would change this

    An environmental impact assessment, AERB siting consent or NPCIL project document describing the SMR-55 plot and connections. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(2 of 5 sources with a publication or document date)
Latest dated listed source publication: World Nuclear News: India's project milestones and SMR-55 report: 16 Oct 2026.Latest dated listed source document: Department of Atomic Energy: written answers in Parliament on small reactors (posted May to September 2026): 5 Aug 2026.Latest dated recorded event: Tarapur SMR-55 lead proposal documented: 4 Feb 2026.3 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Tarapur SMR-55 lead proposal — https://smrmap.com/projects/tarapur-smr-55/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Tarapur SMR-55 lead proposal”. Record reviewed 6 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/tarapur-smr-55/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.