Projects / China · Operating

TMSR-LF1 thorium molten-salt experimental reactor, Wuwei

Experimental reactor (2 MWt), no electricity on the earlier project sources.

Current status

Stage
Operating
How current
General record check . Bounded evidence review . 2 of 8 listed sources have a publication or document date recorded here; the newest is 13 Jan 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: TMSR-LF1 operating license 2307 (7 Jun 2023). All permissions and applications
Latest development
1 Nov 2025 · Recorded development: SINAP announces first thorium-to-uranium fuel conversion. Source: WNN: Chinese MSR achieves conversion of thorium-uranium fuel. Updates entry
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Molten salt reactor. How it works, with a 3D view.
Schematic of IMSR (Integral Molten Salt Reactor), this type's example. On the left, a tall reactor vessel holds graphite with fuel channels low down and primary heat exchangers above it, with pump motors and shutdown drives on top.
Schematic of IMSR (Integral Molten Salt Reactor), this type's example.

Description

Construction began in 2018; NNSA operating license 2307 was issued to SINAP on 7 June 2023, valid through 6 June 2033 and subject to separate commissioning hold points. The license itself does not establish release of those points. Earlier project reporting dates first criticality to 11 October 2023 and thorium-fuel addition to 2024. The IAEA Research Reactor Database lists TMSR-LF1 as operational, with construction from September 2018 and first criticality on 11 October 2023, in an entry last updated 7 November 2025; it names SINAP as operator and gives no power figure. Economic Daily reported in January 2026 that the reactor first reached full power in June 2024.

Key facts

Design
TMSR-LF1 experimental molten-salt reactor (SMR)
Technology
Molten salt reactor (MSR) · molten salt
Operator(s)
Shanghai Institute of Applied Physics
Vendor for linked design
Shanghai Institute of Applied Physics
Location
Hongshagang industrial cluster, Minqin county · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Point from the Wikipedia article for TMSR-LF1, which places the reactor in the Hongshagang industrial park in Minqin county; it lies about 0.3 km from the site coordinate in SINAP's separate 2026 environmental assessment for the planned research reactor on the same campus. Campus-area point, not a surveyed reactor position.
Coordinates
38.9602, 102.6122 · site-area point (approximate)
Electrical capacity
thermal only (no MWe) · scope: plant
Thermal capacity
2 MWth (nameplate; basis unspecified)
Modules planned
1
Purpose
Research or test reactor
Construction start
Sep 2018TMSR-LF1 construction begins
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

TMSR-LF1 thorium molten-salt experimental reactor, Wuwei is recorded at Hongshagang industrial cluster, Minqin county, Gansu, China. Operator: Shanghai Institute of Applied Physics. Recorded vendor: Shanghai Institute of Applied Physics. Stage: Operating. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: Wikipedia: TMSR-LF1 (article coordinates), Article coordinate 38.9602, 102.6122 on 'TMSR-LF1', read 30 October 2026

This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 2 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Funding and government decisions

Source-backed project statement World Nuclear News reported that in January 2011 the Chinese Academy of Sciences launched a 3 billion yuan research program on liquid-fluoride thorium reactors. That figure is the program, not a stated payment for construction of TMSR-LF1. No project-specific amount paid for this reactor was stated. WNN: Chinese molten-salt reactor cleared for start-up

Fuel
  • Fuel form stated for TMSR-LF1 experimental molten-salt reactorliquid fuel, thorium-based molten salt
  • Enrichment stated for TMSR-LF1 experimental molten-salt reactorHALEU (initial load); enriched to under 20% U-235
Project fuel information is described in the source-backed statement below.
Source-backed project statement

The Shanghai Institute of Applied Physics said, as reported on 4 November 2025, that thorium was added to TMSR-LF1 in October 2024 and that thorium-uranium conversion was then achieved. The same report describes fuel enriched to under 20 percent uranium-235, about 50 kilograms of thorium, and uranium tetrafluoride. No fuel supplier or fabrication contract is named. WNN: Chinese MSR achieves conversion of thorium-uranium fuel; CPPCC News (reprinting Economic Daily): In the depths of the Gansu Gobi (13 January 2026)

Programs and agreements naming the project
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
Customer or offtaker

The operating license names the Shanghai Institute of Applied Physics as the operator of a 2 megawatt-thermal experimental reactor. Later institute statements reported by World Nuclear News say the reactor has been generating heat and is a research platform. No buyer of heat or electricity, and no external research-service customer, is named. NNSA: TMSR-LF1 operating licence 2307; WNN: Chinese MSR achieves conversion of thorium-uranium fuel

Contractor

The license and the news reports say construction began in September 2018 and was reportedly completed in August 2021. They do not name an engineering or construction contractor. WNN: Chinese MSR achieves conversion of thorium-uranium fuel

Comparable schedule revision

Comparable schedule revision not established. World Nuclear News says construction was scheduled to finish in 2024 and was reportedly finished in August 2021. A reported completion set against an earlier target is not two forecasts of the same future milestone. No later pair of forecasts for one milestone of this reactor was stated. A 2035 demonstration aim refers to a larger reactor. WNN: Chinese MSR achieves conversion of thorium-uranium fuel

Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner

Timeline

Recorded developments

Earlier developments (2)

Permissions and applications

Operating-license applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. TMSR-LF1 is the 2 MWt liquid-fueled thorium molten-salt experimental reactor of the Chinese Academy of Sciences' Shanghai Institute of Applied Physics (SINAP). It is at Hongshagang town, Minqin county, Wuwei, Gansu (NNSA license; China Daily, 1 November 2025). World Nuclear News (4 November 2025) and the Generation IV International Forum page say construction began in September 2018. WNN says it was reportedly completed in August 2021. No opened source separates site preparation from nuclear construction. On 2 August 2022 the Ministry of Ecology and Environment approved SINAP's commissioning plan, version V1.3 (WNN, 9 August 2022). That approved the plan; it was not an operating license. NNSA operating license 国核安证字第2307号 was issued to SINAP on 7 June 2023 and is valid to 6 June 2033. It covers the 2 MWt reactor and a radioactive-waste treatment center, and names SINAP as the operating organization with full nuclear-safety responsibility. It sets two commissioning hold points after first fuel loading, the first approach to criticality and leaving 90% of rated power, to be released by the Northwest regional station. No release document was opened. First criticality was on 11 October 2023 (WNN; IAEA Research Reactor Database). Economic Daily (13 January 2026) says the reactor first reached full power in June 2024 and first added thorium in October 2024. SINAP announced thorium-to-uranium conversion on 1 November 2025. The reactor produces heat for research. No opened source describes electricity generation, grid connection or commercial service. The latest evidence of operation is SINAP's statement, relayed by WNN in November 2025, that it has been generating heat continuously since criticality. The RRDB entry, updated 7 November 2025, lists it as operational under SINAP. The license requires any extension application five years before the 2033 expiry. Stored values match the sources. No source gives coordinates. Last checked 19 Oct 2026. NNSA: TMSR-LF1 operating licence 2307; China Daily: thorium reactor in Minqin county; WNN: Chinese MSR achieves conversion of thorium-uranium fuel; WNN: Chinese molten-salt reactor cleared for start-up; CPPCC News (reprinting Economic Daily): In the depths of the Gansu Gobi (13 January 2026); GIF: molten-salt reactor history and TMSR-LF1; IAEA Research Reactor Database: TMSR-LF1 (list entry)
    What would change this

    An NNSA notice on TMSR-LF1 (license amendment, extension application or a long-term shutdown), or a SINAP report that changes its operating status. Next scheduled check: 19 Jan 2027.

  • Map coordinates: Not disclosed in the reviewed evidence. The NNSA operating license gives the project address as Hongshagang town, Minqin county, Wuwei, Gansu, and China Daily names the Hongshagang industrial cluster. Neither gives coordinates. The IAEA Research Reactor Database entry, updated 7 November 2025, has empty latitude and longitude fields and lists Shanghai, SINAP's home city, as the closest city. No opened source gives a point for the reactor; the map uses the reactor's Wikipedia article coordinate as a campus-area point. The coordinates of the separate planned research-reactor campus noted in the earlier review are not transferred. Last checked 19 Oct 2026. IAEA Research Reactor Database: TMSR-LF1 (list entry); NNSA: TMSR-LF1 operating licence 2307
    What would change this

    A SINAP, MEE or NNSA document stating TMSR-LF1's own coordinates or placing it within surveyed campus coordinates. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. License 2307 says that if operation is to continue after it expires on 6 June 2033, the institute must apply at least five years before expiry. The press accounts name no nearer pending decision for this reactor. A 100 megawatt-thermal demonstration aimed at 2035 is a later, different project. Last checked 23 Oct 2026. NNSA: TMSR-LF1 operating licence 2307; WNN: Chinese MSR achieves conversion of thorium-uranium fuel
    What would change this

    A continuation application for license 2307, or another decision that names TMSR-LF1. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The National Nuclear Safety Administration issued operating license 2307 to the Shanghai Institute of Applied Physics on 7 June 2023, valid through 6 June 2033. The license sets hold points, after the first fuel load, at the first approach to criticality and at leaving 90 percent of rated power, to be released by the northwest supervision station. The license does not itself record those releases. A ministry letter quoted on 9 August 2022 had approved the commissioning plan. World Nuclear News later reported first criticality on 11 October 2023. Last checked 23 Oct 2026. NNSA: TMSR-LF1 operating licence 2307; WNN: Chinese molten-salt reactor cleared for start-up; WNN: Chinese MSR achieves conversion of thorium-uranium fuel
    What would change this

    The supervision station's release letters for the two hold points, if they are to be added. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). Operating license 2307 places the reactor at Hongshagang Town, Minqin County, Wuwei, Gansu. The license does not state a water withdrawal or a grid connection. A design statement that this reactor type does not need cooling water is not a water right. Last checked 23 Oct 2026. NNSA: TMSR-LF1 operating licence 2307
    What would change this

    A water withdrawal or grid connection for TMSR-LF1. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. License 2307 names a radioactive-waste treatment center as an auxiliary facility. It requires a radioactive-waste management program and effluent monitoring, and it requires early study of decommissioning and disposal arrangements, including financial arrangements. It does not name a disposal site or a disposal contract. A 2022 design description of discharging fuel salt after five to eight years is not an executed arrangement. Last checked 23 Oct 2026. NNSA: TMSR-LF1 operating licence 2307
    What would change this

    A disposal contract or a selected disposal site for TMSR-LF1 waste. Next scheduled check: 21 Jan 2027.

Evidence dates

(2 of 8 sources with a publication or document date)
Latest dated listed source publication: CPPCC News (reprinting Economic Daily): In the depths of the Gansu Gobi (13 January 2026): 13 Jan 2026.Latest dated listed source document: NNSA: TMSR-LF1 operating licence 2307: 7 Jun 2023.Latest dated recorded event: SINAP announces first thorium-to-uranium fuel conversion: 1 Nov 2025.6 of 8 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(8)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: TMSR-LF1 thorium molten-salt experimental reactor, Wuwei — https://smrmap.com/projects/tmsr-lf1-wuwei/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “TMSR-LF1 thorium molten-salt experimental reactor, Wuwei”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/tmsr-lf1-wuwei/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.