Kairos Hermes 2

Kairos Power's Hermes 2 demonstration at Oak Ridge, in the United States, is a test reactor project under construction.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 6 of 14 listed sources have a publication or document date recorded here; the newest is 1 Oct 2026. A listed page was last updated 29 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: Kairos Hermes 2 construction permit (21 Nov 2024). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
17 Apr 2026 · Groundbreaking: Hermes 2 groundbreaking. Groundbreaking reported for Hermes 2. Source: EnergyNote 2026 SMR licensing map; Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026). Updates entry
Next dated milestone
Planned step: 2030 (target). Kairos target: Hermes 2 to begin operations in 2030. This is not a commitment and is not an achieved milestone. Source: Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025).
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
Same design
2 tracked: 2 construction. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Fluoride salt-cooled high-temperature reactor. How it works, with a 3D view.
Schematic of KP-FHR commercial plant, this type's example. On the left, a reactor vessel holds a graphite reflector around a bed of fuel pebbles, with control and shutdown elements coming down from above and pebble tubes at the top and bottom.
Schematic of KP-FHR commercial plant, this type's example.

Description

The NRC construction permits CPTR-7 and CPTR-8, issued 21 November 2024, authorize a non-power test reactor facility of two low-power test reactors of 35 MWth each; the NRC’s Hermes 2 page, dated 29 October 2026, still describes that two-unit configuration and lists no amendment. Kairos Power announced groundbreaking on 17 April 2026 and states the plant will supply up to 50 MW to the TVA grid; that output and the groundbreaking are company statements. No operating license is recorded. Kairos stated on 18 August 2025 that it would raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor. The IAEA’s 2026 reactor tables (data to 31 December 2025) still list Hermes 2 as two units of 25 MWe each; the single-reactor configuration, which this record’s one planned module follows, is a company statement not reflected in that listing or in the NRC permits. The main numeric electrical field is left unknown because the company's up-to-50-MW statement is qualified and differs from the permitted two-reactor configuration, with no net basis established. An October 2026 company newsletter also reports a proposed Samsung C&T investment and engineering package of up to $100 million, subject to regulatory approvals, supporting Hermes 2 and future plants; its cash/in-kind split is unspecified. Kairos retains nuclear-island scope, while Samsung supports power-generation and balance-of-plant readiness. The same report describes phase-one testing of a non-nuclear, reduced-scale reactor-cavity mock-up for shielding and remote maintenance, and removal of legacy site materials. These delivery-readiness activities establish no new reactor configuration or permission. ORNL's February 2026 partnership scope includes development of a spent-fuel-pebble management plan covering on-site cask storage, transport and final disposition. Kairos's May 2026 newsletter places that work at Hermes-series and future-reactor level. This is planning work, not a completed or approved Hermes 2 waste arrangement, and does not resolve the reactor-configuration difference. The NRC's final environmental assessment ML24240A034, completed in August 2024 for the two-reactor configuration and predating the company's single-reactor statement, says spent fuel would stay on site during the expected 11-year operating license period and afterwards would be stored further at the East Tennessee Technology Park or shipped to an interim storage facility or a permanent geologic repository. It names no selected facility or agreement. It does not describe a single-reactor plant, so it does not settle the configuration difference. The stored 2030 target follows Kairos's 18 August 2025 statement that the single reactor is scheduled to begin operations in 2030.

Key facts

Design
Hermes / KP-FHR (SMR)
Technology
Fluoride-salt-cooled high-temperature reactor (FHR) · molten salt
Intended operator(s)
Kairos Power
Vendor for linked design
Kairos Power
Location
Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Hermes unit 1 (KP-FHR) in the East Tennessee Technology Park area (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. Replaces an earlier hand-placed point about 1.6 km away.
Coordinates
35.9377806, -84.4032804 · site-area point (approximate)
Electrical capacity
Not recorded · scope: module
Thermal capacity
Not recorded
Modules planned
1
Purpose
Research or test reactor
Construction start
Not recorded
Inclusion basis
SMR by regulator classification
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Kairos Hermes 2 is recorded at Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area), Tennessee, United States. Intended operator: Kairos Power. Recorded vendor: Kairos Power. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Kairos Hermes 1.

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'hermes-nuclear-power-plant-1' (35.9377806, -84.4032804)

Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 35 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Customer or offtaker
  • Customer / offtakerTennessee Valley Authority · source
  • Customer / offtakerGoogle · sourceReceives the plant's clean energy attributes through the TVA system under the August 2025 agreement; the electricity purchase agreement is with TVA.
Source-backed project statement

Kairos Power announced a signed power purchase agreement with TVA on 18 August 2025 for up to 50 MW from Hermes 2, with Google receiving the clean-energy attributes. Its 28 May 2026 newsletter characterizes the PPA as binding. That is the company's characterization; the contract text, price, term and conditions were not reviewed. It establishes an announced electricity-purchase arrangement, not delivered power or completion of the plant. The company's single-reactor description remains distinct from the NRC's two-reactor permits. Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); Kairos Power: The Time is Now (28 May 2026 newsletter); NRC: Hermes 2 – Kairos Application (page updated 15 September 2026)

Contractor
  • Planned construction contractorBarnard Construction Company · source
  • Planned construction contractorSamsung C&T · sourceAgreed (binding term sheet, Sep 2026) to join Kairos Power's integrated EPC team for Hermes 2, initially for power-generation and balance-of-plant scope.
Source-backed project statement

On 17 April 2026 Kairos Power said it will fabricate Hermes 2 reactor equipment modules in Albuquerque and ship them to Oak Ridge for assembly. That is the company's own fabrication plan, and the page names no outside construction contractor. Hermes 1 nuclear construction at the same campus is a different reactor. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026)

Funding and government decisions

Source-backed project statement World Nuclear News reported a binding term sheet for Samsung C&T to invest up to USD 100 million in Kairos Power through direct investment and in-kind engineering services, subject to regulatory approvals, to enable Hermes 2. This is company-level investment linked to the project; closing, disbursement and a project financing allocation are not established. WNN: Samsung C&T invests in Kairos Power

Fuel
  • Fuel form stated for Hermes / KP-FHRTRISO fuel particles in carbon-matrix pebbles
  • Enrichment stated for Hermes / KP-FHRHigh Assay Low Enriched Uranium (HALEU)
No project-specific fuel supply arrangement is recorded as a structured fact.

Kairos and BWXT's 3 September 2025 collaboration explores commercial TRISO manufacture, possible fuel supply for Hermes 2 and subsequent reactors, and a possible jointly developed fabrication facility. Kairos's 28 May 2026 newsletter describes continuing manufacturing-development collaboration. These sources establish exploratory fuel-development work, not a firm Hermes 2 supply commitment, completed fabrication or delivery. The NRC page's fuel-form description is not a supply arrangement. No supplier role is inferred from the collaboration. Kairos Power and BWXT: commercial TRISO manufacturing collaboration; Kairos Power: The Time is Now (28 May 2026 newsletter)

Programs and agreements naming the project
Not found in the sources we checked (1): Comparable schedule revision
Comparable schedule revision

Comparable schedule revision not established. On 18 August 2025 Kairos said the single-reactor Hermes 2 description was scheduled to begin operations in 2030. That operations date is stated once. NRC construction-permit issuance on 21 November 2024 is a completed and different milestone, and the pages do not give two forecasts of the 2030 operations date. The NRC's August 2024 final environmental assessment reports the applicant's earliest projected completion of mid-2027 for Unit 1 and mid-2028 for Unit 2. Those are approximate completion dates for the two-reactor configuration, so they are not paired with the 2030 operations date as a revision. Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034)

Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner

Timeline

Recorded developments

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Planned commercial operation: 2030 (planned); Construction permit: 21 Nov 2024.

Permissions and applications

Construction applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)

Evidence dates

(6 of 14 sources with a publication or document date)
Latest dated listed source publication: WNN: Samsung C&T invests in Kairos Power: 22 Sep 2026.Latest dated listed source document: Kairos Power: The Path to Deployment (October 2026 newsletter): 1 Oct 2026.Latest dated recorded event: Hermes 2 groundbreaking: 17 Apr 2026.8 of 14 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(14)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Kairos Hermes 2 — https://smrmap.com/projects/kairos-hermes-2/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Kairos Hermes 2”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/kairos-hermes-2/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.