Projects / United States · Construction
Kairos Hermes 2
Kairos Power's Hermes 2 demonstration at Oak Ridge, in the United States, is a test reactor project under construction.
Current status
- How current
- General record check . Bounded evidence review . 6 of 14 listed sources have a publication or document date recorded here; the newest is 1 Oct 2026. A listed page was last updated 29 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: Kairos Hermes 2 construction permit (21 Nov 2024). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- 17 Apr 2026 · Groundbreaking: Hermes 2 groundbreaking. Groundbreaking reported for Hermes 2. Source: EnergyNote 2026 SMR licensing map; Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026). Updates entry
- Next dated milestone
- Planned step: 2030 (target). Kairos target: Hermes 2 to begin operations in 2030. This is not a commitment and is not an achieved milestone. Source: Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025).
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 2 tracked: 2 construction. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Fluoride salt-cooled high-temperature reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The NRC construction permits CPTR-7 and CPTR-8, issued 21 November 2024, authorize a non-power test reactor facility of two low-power test reactors of 35 MWth each; the NRC’s Hermes 2 page, dated 29 October 2026, still describes that two-unit configuration and lists no amendment. Kairos Power announced groundbreaking on 17 April 2026 and states the plant will supply up to 50 MW to the TVA grid; that output and the groundbreaking are company statements. No operating license is recorded. Kairos stated on 18 August 2025 that it would raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor. The IAEA’s 2026 reactor tables (data to 31 December 2025) still list Hermes 2 as two units of 25 MWe each; the single-reactor configuration, which this record’s one planned module follows, is a company statement not reflected in that listing or in the NRC permits. The main numeric electrical field is left unknown because the company's up-to-50-MW statement is qualified and differs from the permitted two-reactor configuration, with no net basis established. An October 2026 company newsletter also reports a proposed Samsung C&T investment and engineering package of up to $100 million, subject to regulatory approvals, supporting Hermes 2 and future plants; its cash/in-kind split is unspecified. Kairos retains nuclear-island scope, while Samsung supports power-generation and balance-of-plant readiness. The same report describes phase-one testing of a non-nuclear, reduced-scale reactor-cavity mock-up for shielding and remote maintenance, and removal of legacy site materials. These delivery-readiness activities establish no new reactor configuration or permission. ORNL's February 2026 partnership scope includes development of a spent-fuel-pebble management plan covering on-site cask storage, transport and final disposition. Kairos's May 2026 newsletter places that work at Hermes-series and future-reactor level. This is planning work, not a completed or approved Hermes 2 waste arrangement, and does not resolve the reactor-configuration difference. The NRC's final environmental assessment ML24240A034, completed in August 2024 for the two-reactor configuration and predating the company's single-reactor statement, says spent fuel would stay on site during the expected 11-year operating license period and afterwards would be stored further at the East Tennessee Technology Park or shipped to an interim storage facility or a permanent geologic repository. It names no selected facility or agreement. It does not describe a single-reactor plant, so it does not settle the configuration difference. The stored 2030 target follows Kairos's 18 August 2025 statement that the single reactor is scheduled to begin operations in 2030.
Key facts
- Design
- Hermes / KP-FHR (SMR)
- Technology
- Fluoride-salt-cooled high-temperature reactor (FHR) · molten salt
- Intended operator(s)
- Kairos Power
- Vendor for linked design
- Kairos Power
- Location
- Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Hermes unit 1 (KP-FHR) in the East Tennessee Technology Park area (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. Replaces an earlier hand-placed point about 1.6 km away. - Coordinates
- 35.9377806, -84.4032804 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- Not recorded
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- SMR by regulator classification
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Kairos Hermes 2 is recorded at Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area), Tennessee, United States. Intended operator: Kairos Power. Recorded vendor: Kairos Power. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Kairos Hermes 1.
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'hermes-nuclear-power-plant-1' (35.9377806, -84.4032804)
Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 35 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- Intended operatorKairos Power
- Intended licensed ownerKairos Power · source
- Reactor supplier
- Vendor for the linked designKairos Power
- Customer or offtaker
- Customer / offtakerTennessee Valley Authority · source
- Customer / offtakerGoogle · sourceReceives the plant's clean energy attributes through the TVA system under the August 2025 agreement; the electricity purchase agreement is with TVA.
Source-backed project statement
Kairos Power announced a signed power purchase agreement with TVA on 18 August 2025 for up to 50 MW from Hermes 2, with Google receiving the clean-energy attributes. Its 28 May 2026 newsletter characterizes the PPA as binding. That is the company's characterization; the contract text, price, term and conditions were not reviewed. It establishes an announced electricity-purchase arrangement, not delivered power or completion of the plant. The company's single-reactor description remains distinct from the NRC's two-reactor permits. Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); Kairos Power: The Time is Now (28 May 2026 newsletter); NRC: Hermes 2 – Kairos Application (page updated 15 September 2026)
- Contractor
- Planned construction contractorBarnard Construction Company · source
- Planned construction contractorSamsung C&T · sourceAgreed (binding term sheet, Sep 2026) to join Kairos Power's integrated EPC team for Hermes 2, initially for power-generation and balance-of-plant scope.
Source-backed project statement
On 17 April 2026 Kairos Power said it will fabricate Hermes 2 reactor equipment modules in Albuquerque and ship them to Oak Ridge for assembly. That is the company's own fabrication plan, and the page names no outside construction contractor. Hermes 1 nuclear construction at the same campus is a different reactor. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026)
- Funding and government decisions
Source-backed project statement World Nuclear News reported a binding term sheet for Samsung C&T to invest up to USD 100 million in Kairos Power through direct investment and in-kind engineering services, subject to regulatory approvals, to enable Hermes 2. This is company-level investment linked to the project; closing, disbursement and a project financing allocation are not established. WNN: Samsung C&T invests in Kairos Power
- Fuel
- Fuel form stated for Hermes / KP-FHRTRISO fuel particles in carbon-matrix pebbles
- Enrichment stated for Hermes / KP-FHRHigh Assay Low Enriched Uranium (HALEU)
Kairos and BWXT's 3 September 2025 collaboration explores commercial TRISO manufacture, possible fuel supply for Hermes 2 and subsequent reactors, and a possible jointly developed fabrication facility. Kairos's 28 May 2026 newsletter describes continuing manufacturing-development collaboration. These sources establish exploratory fuel-development work, not a firm Hermes 2 supply commitment, completed fabrication or delivery. The NRC page's fuel-form description is not a supply arrangement. No supplier role is inferred from the collaboration. Kairos Power and BWXT: commercial TRISO manufacturing collaboration; Kairos Power: The Time is Now (28 May 2026 newsletter)
- Programs and agreements naming the project
- Research program; status not establishedKairos Power and BWXT commercial TRISO fuel development collaboration
Not found in the sources we checked (1): Comparable schedule revision
- Comparable schedule revision
Comparable schedule revision not established. On 18 August 2025 Kairos said the single-reactor Hermes 2 description was scheduled to begin operations in 2030. That operations date is stated once. NRC construction-permit issuance on 21 November 2024 is a completed and different milestone, and the pages do not give two forecasts of the 2030 operations date. The NRC's August 2024 final environmental assessment reports the applicant's earliest projected completion of mid-2027 for Unit 1 and mid-2028 for Unit 2. Those are approximate completion dates for the two-reactor configuration, so they are not paired with the 2030 operations date as a revision. Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034)
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
Timeline
Recorded developments
- · Groundbreaking
Hermes 2 groundbreaking - · Construction permission recorded
Construction permission recorded: Kairos Hermes 2 construction permit - · Regulatory step
NRC dockets Hermes 2 construction permit application - · Application submitted
Application for the Hermes 2 construction permits
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Kairos target: Hermes 2 to begin operations in 2030
Dates on the project record: Planned commercial operation: 2030 (planned); Construction permit: 21 Nov 2024.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- Kairos Hermes 2 construction permit
Construction permission · Issued / approved · NRC · decided 21 Nov 2024 · submitted 14 Jul 2023 · permit CPTR-7, CPTR-8 · docket 50-611, 50-612 · ADAMS ML24324A021, ML24324A022 · 89 FR 94767
The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.
Sources: Federal Register 89 FR 94767 (29 Nov 2024): Hermes 2 test reactor facility construction permits; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 2 construction permit
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. The NRC issued construction permits for the Hermes 2 test reactor facility to Kairos Power LLC on 21 November 2024, on an application submitted on 14 July 2023; its Hermes 2 page (updated 15 September 2026) describes two low-power test reactors of 35 MW thermal each with a shared Rankine-cycle steam conversion system and lists no amendment, and the IAEA's 2026 tables still list Hermes 2 Unit 1 and Unit 2. Kairos said on 18 August 2025 that, under a power purchase agreement with TVA, the Hermes 2 plant in Oak Ridge will deliver up to 50 MW to the TVA grid serving Google data centers, and that it will raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor, scheduled to begin operations in 2030; that single-reactor configuration is a company statement not reflected in the permits. Kairos broke ground on 17 April 2026 on the former K-33 Oak Ridge Gaseous Diffusion Plant footprint, with Barnard as general contractor and reactor equipment modules to be fabricated in Albuquerque. Its October 2026 newsletter (heading dated 1 October 2026) shows crews removing legacy lead and copper from the Hermes 2 footprint to prepare for site excavation and describes a non-nuclear reduced-scale reactor-cavity mock-up; no opened source reports excavation for safety-related structures, safety-related concrete or other nuclear construction. The permits authorize construction, not operation, and no operating-license application is recorded. Samsung C&T is to join the EPC team for power-generation and balance-of-plant readiness while Kairos keeps the nuclear island. Stored values: the one planned module follows the company's single-reactor statement and conflicts with the two-reactor permits; no rating is stored; the 2030 target matches Kairos's 'begin operations in 2030'; and the construction stage rests on the permits and groundbreaking, not on documented nuclear construction. Last checked 19 Oct 2026. NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); U.S. NRC: Kairos Hermes 2 construction permit; IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); Kairos Power: The Path to Deployment (October 2026 newsletter)
What would change this
An NRC amendment of the Hermes 2 permits to a single reactor, an operating-license application, or a Kairos or NRC report of safety-related excavation or concrete at the K-33 site. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified): Sources conflict. The NRC construction permits and the NRC Hermes 2 page (dated 29 October 2026) describe two low-power test reactors of 35 MW thermal each with a shared steam conversion system, and the IAEA's 2026 tables list two Hermes 2 units. The NRC's August 2024 final environmental assessment also describes two test reactors, each with a maximum thermal power of 35 MWt, sharing one power generation system. It predates Kairos's statement and gives no electrical rating for Hermes 2, so it does not resolve the difference. Kairos stated on 18 August 2025 that it would raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor, and its 17 April 2026 release says the plant will supply up to 50 MW to the TVA grid. The NRC's document table for the application, updated 15 September 2026, stops at the construction permits; the full ADAMS docket listing was not read. No NRC document reviewed reflects the single-reactor configuration, the 50 MW is an upper bound, and no net or gross basis is stated, so no rating is stored. Last checked 4 Nov 2026. U.S. NRC: Kairos Hermes 2 construction permit; NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034); NRC: Hermes 2 construction permit application review documents (page updated 15 September 2026)
What would change this
NRC amendment of CPTR-7/CPTR-8 or an operating license application stating the single-reactor rating. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. The NRC issued the Hermes 2 construction permits on 21 November 2024 and Kairos reported groundbreaking on 17 April 2026. The NRC page, dated 29 October 2026, names no pending decision or operating-license application, and the company's later one-reactor description is not shown there as an approved change. Last checked 4 Nov 2026. NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); U.S. NRC: Kairos Hermes 2 construction permit
What would change this
An NRC operating-license decision for Hermes 2, or an NRC action on the single-reactor description. Next scheduled check: 21 Jan 2027.
- Permissions and public process. On 21 November 2024 the NRC issued construction permits for the Hermes 2 test reactor facility to Kairos Power. The NRC page, dated 29 October 2026, still describes two low-power test reactors at 35 megawatts thermal each and shows no operating-license decision. The later company statement of one 50 MW reactor is not shown on that page as a permit amendment. NRC staff's final environmental assessment ML24240A034, listed on that page as issued on 30 August 2024, covered two non-power test reactors and reached a finding of no significant impact. Its comment appendix records the City of Oak Ridge saying it does not support indefinite onsite storage of spent fuel. The assessment says Kairos would need a separate operating-license application and that another environmental review would follow. Last checked 4 Nov 2026. NRC: Hermes 2 – Kairos Application (page updated 15 September 2026); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034); U.S. NRC: Kairos Hermes 2 construction permit
What would change this
An NRC operating-license decision, or an NRC action changing the two-reactor permit. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). On 17 April 2026 Kairos said Hermes 2 will stand on the former K-33 site in Oak Ridge and that the company acquired that land and the adjacent K-31 site in 2021. The 18 August 2025 announcement says the plant would deliver electricity to the TVA grid, which is not shown as an interconnection agreement. Neither page states a water right. The NRC's August 2024 final environmental assessment, for the two-reactor configuration, says water would come from municipal sources or truck deliveries and that there would be no cooling water system, with heat rejected to air-cooled condensers. It places the facilities within the former K-33 footprint, permanently disturbing about 30 acres. These are plans assessed for the permits, not a water right or service agreement. Last checked 23 Oct 2026. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034)
What would change this
A recorded deed, a grid interconnection agreement, or a water right for the Oak Ridge site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The reviewed sources do not establish spent-fuel and waste arrangements for the single-reactor configuration represented by this record's one planned module; the assessed arrangements below apply to the permitted two-reactor configuration. ORNL's 19 February 2026 partnership scope includes completing a spent-fuel-pebble management plan covering on-site cask storage, transportation and final disposition. Kairos's 28 May 2026 newsletter links that work to the Hermes series and future reactors. These sources establish planned development of a management plan, not a completed Hermes 2 arrangement, selected destination or disposal agreement. The NRC's final environmental assessment ML24240A034, completed in August 2024, covers the permitted two-reactor configuration and predates the company's single-reactor statement, so it does not describe a single-reactor plant. It says spent TRISO fuel would be stored in the reactor building over the life of the facilities, with removed pebbles placed in canisters for onsite canister storage and, if necessary, in dry storage casks on an exterior pad. It estimates about 776,000 used pebbles between the two units. It says the facility would not ship spent fuel offsite during the expected 11-year operating license period; after operations the fuel would be further stored at the East Tennessee Technology Park or shipped to an interim storage facility or a permanent geologic repository. No facility or agreement is selected. FLiBe salt would be stored on site until decommissioning and then disposed of as solid radioactive waste. NRC staff said any Kairos contract with DOE on waste storage was outside the scope of the environmental review, and said another environmental review would follow an operating-license application. These are arrangements assessed for the construction permits, not approved or executed arrangements. Last checked 3 Nov 2026. ORNL: Kairos partnership scope including spent-fuel management planning (19 February 2026); Kairos Power: The Time is Now (28 May 2026 newsletter); NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034)
What would change this
A completed Hermes 2 management plan, an operating-license application or NRC environmental review stating Hermes 2 spent-fuel arrangements, or an NRC amendment changing the two-reactor configuration the final environmental assessment covers. Next scheduled check: 3 Feb 2027.
Evidence dates
(6 of 14 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(14)
- NRC Kairos Hermes construction permit materials (regulator, accessed 14 Oct 2026)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026) (company, accessed 18 Oct 2026)
- Kairos Power: Google, Kairos Power, TVA Collaborate to Meet America’s Growing Energy Needs (18 August 2025) (company, accessed 18 Oct 2026)
- IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026) (IAEA/NEA, accessed 9 Oct 2026)
- NRC: Hermes 2 – Kairos Application (page updated 15 September 2026) (regulator, accessed 10 Oct 2026)
- U.S. NRC: Kairos Hermes 2 construction permit (regulator, page updated 29 Oct 2026, accessed 4 Nov 2026)
- Kairos Power: The Path to Deployment (October 2026 newsletter) (company, dated 1 Oct 2026, accessed 18 Oct 2026)
- WNN: Samsung C&T invests in Kairos Power (news report, published 22 Sep 2026, accessed 21 Oct 2026)
- Kairos Power and BWXT: commercial TRISO manufacturing collaboration (company, published 3 Sep 2025, accessed 19 Oct 2026)
- ORNL: Kairos partnership scope including spent-fuel management planning (19 February 2026) (government, published 19 Feb 2026, accessed 27 Oct 2026)
- Kairos Power: The Time is Now (28 May 2026 newsletter) (company, published 28 May 2026, accessed 27 Oct 2026)
- NRC: Environmental Assessment and Finding of No Significant Impact for the Construction Permits and Environmental Review Exemptions for the Kairos Hermes 2 Test Reactors, Final Report (ML24240A034) (regulator, dated Aug 2024, accessed 24 Oct 2026)
- NRC: Hermes 2 construction permit application review documents (page updated 15 September 2026) (regulator, page updated 15 Sep 2026, accessed 4 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Kairos Hermes 2 — https://smrmap.com/projects/kairos-hermes-2/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Kairos Hermes 2”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/kairos-hermes-2/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.