Projects / United States · Construction
Kairos Hermes 1
Non-power fluoride-salt-cooled test reactor in the Oak Ridge area of Tennessee; it is not an electrical generator.
Current status
- How current
- General record check . Bounded evidence review . 9 of 14 listed sources have a publication or document date recorded here; the newest is 15 Sep 2026. Stage (construction) confirmed against NRC Kairos Hermes construction permit materials.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: Kairos Hermes 1 construction permit (14 Dec 2023). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- 1 May 2025 · Construction start: Hermes nuclear safety-related construction begins. Kairos's 8 May 2025 release says safety-related construction started on 1 May 2025, focused on the building foundation. Source: Kairos Power: Kairos Power Begins Nuclear Safety-Related Construction of Hermes Low-Power Demonstration Reactor (published 8 May 2025); Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227) (dated 1 May 2025). Updates entry
More on this development
Its letter to the NRC dated 1 May 2025, required by permit condition 3.D, says excavation for the first drilled pier of the safety-related foundation began that day. Company statements; the first safety-related concrete is a separate event.
- Next dated milestone
- Planned step: 2028 (target). Kairos expects to complete Hermes construction in 2028. This is not an achieved milestone. Source: World Nuclear News: Regulator extends Hermes 1 reactor construction deadline (published 22 Apr 2026); Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Operation or first-criticality target (non-power reactor) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 2 tracked: 2 construction. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Fluoride salt-cooled high-temperature reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The NRC issued construction permit CPTR-6 on 14 December 2023, and a May 2026 order extended the latest construction completion date to 30 April 2029. Kairos notified the NRC that excavation for the first drilled pier of the safety-related foundation began on 1 May 2025, and reported its first safety-related concrete in May 2025. Operation needs a separate NRC operating license; none is recorded.
Key facts
- Design
- Hermes / KP-FHR (SMR)
- Technology
- Fluoride-salt-cooled high-temperature reactor (FHR) · molten salt
- Intended operator(s)
- Kairos Power
- Vendor for linked design
- Kairos Power
- Location
- Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Hermes unit 1 (KP-FHR) in the East Tennessee Technology Park area (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. Replaces an earlier hand-placed point about 1.6 km away. - Coordinates
- 35.9377806, -84.4032804 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: module
- Thermal capacity
- 35 MWth (nameplate; basis unspecified)
- Purpose
- Research or test reactor
- Construction start
- 1 May 2025Hermes nuclear safety-related construction begins
- Inclusion basis
- SMR by regulator classification
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Status confirmed on against NRC Kairos Hermes construction permit materials. This confirms the recorded status only; the general record check date remains separate.
Site and capacity notes
Kairos Hermes 1 is recorded at Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area), Tennessee, United States. Intended operator: Kairos Power. Recorded vendor: Kairos Power. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Kairos Hermes 2.
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'hermes-nuclear-power-plant-1' (35.9377806, -84.4032804)
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 35 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- Intended operatorKairos Power
- Intended licensed ownerKairos Power · source
- Reactor supplier
- Vendor for the linked designKairos Power
- Contractor
- Planned construction contractorBarnard Construction Company · source
Source-backed project statement
Kairos Power's 17 April 2026 Hermes 2 groundbreaking release says Barnard Construction Company is serving as the general contractor for both Hermes reactor projects. Hermes 1 safety-related construction has been under way since May 2025, so Barnard is the working general contractor for this unit. No contract value is stated. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026)
- Funding and government decisions
- Funder or lender named for this projectU.S. Department of Energy · sourceARDP risk-reduction award (Dec 2020): DOE share $303 million of a $629 million cost-shared total over seven years; amount disbursed not stated.
Source-backed project statement
DOE announced on 16 December 2020 an Advanced Reactor Demonstration Program risk-reduction award for Kairos's Hermes reduced-scale test reactor, with a DOE share of 303 million dollars of a 629 million dollar cost-shared total over seven years. Kairos said on 20 January 2026 that DOE is investing up to 303 million dollars in the project under a performance-based milestone contract. The amount disbursed is not stated. DOE: Advanced Reactor Demonstration Program awards $30 million in initial funding for risk reduction projects; Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor
- Fuel
- Fuel supplier named for this projectU.S. Department of Energy · sourceContract finalized (announced 20 Jan 2026) for Kairos to receive HALEU from DOE material for Hermes 1 startup and operation; delivery not stated.
- Fuel supplier named for this projectLos Alamos National Laboratory · sourcePartner with Kairos in producing the HALEU TRISO fuel pebbles for Hermes 1 (announced 20 Jan 2026).
- Fuel form stated for Hermes / KP-FHRTRISO fuel particles in carbon-matrix pebbles
- Enrichment stated for Hermes / KP-FHRHigh Assay Low Enriched Uranium (HALEU)
Source-backed project statement
Kairos Power said on 20 January 2026 that it had finalized a contract with DOE to receive HALEU from DOE material for Hermes 1's startup and operation, and that it will use the material to produce TRISO fuel pebbles in partnership with Los Alamos National Laboratory. The supply contract is signed. Fabrication and delivery to the reactor are not yet reported. Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor
- Comparable schedule revision
Source-backed project statement Kairos Power's 16 July 2021 release scheduled Hermes to be 'operational' in 2026; its 30 July 2024 release targeted 'operational' in 2027. This is a change in the company's own forecast wording for the same Oak Ridge demonstration reactor. Neither release defines operational as a specific startup milestone, so the dates are not converted into first criticality, electricity generation or commercial operation. The later reported 2028 construction estimate means the historical 2027 forecast is not presented as current; it does not establish a replacement operation date. The separate permit-completion deadline extension from 31 December 2026 to 30 April 2029 is a legal deadline change, not this company forecast revision. World Nuclear News: Regulator extends Hermes 1 reactor construction deadline; Governor Lee, Commissioner Rolfe Announce Kairos Power to Establish Low-Power Demonstration Reactor in Oak Ridge | Kairos Power; Kairos Power Begins Construction on Hermes Low-Power Demonstration Reactor | Kairos Power
Not found in the sources we checked (1): Customer or offtaker
- Customer or offtaker
The Nuclear Regulatory Commission Hermes page, last reviewed on 15 September 2026, describes Hermes 1 as a low-power test reactor supporting Kairos Power’s own KP-FHR development and states that it will not produce electricity. Kairos Power’s 20 January 2026 release says the reactor provides learning for Kairos’s future fleet, and its 17 April 2026 release names the Tennessee Valley Authority and Google only for Hermes 2 power. Those pages and World Nuclear News on 22 April 2026 do not name a research user, test beneficiary, or service customer for Hermes 1. The developer, the Department of Energy as funder, and the regulator are not treated as customers. NRC Kairos Hermes construction permit materials; Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor; Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); World Nuclear News: Regulator extends Hermes 1 reactor construction deadline
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Construction start
Hermes nuclear safety-related construction begins - · First concrete
First nuclear safety-related concrete at Hermes - · Groundbreaking
Kairos breaks ground at the Hermes site - · Construction permission recorded
Construction permission recorded: Kairos Hermes 1 construction permit - · Regulatory step
NRC dockets Hermes construction permit application
Earlier developments (1)
- · Application submitted
Application for the Hermes 1 construction permit
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Kairos expects Hermes test reactor construction to be complete in 2028
Dates on the project record: Construction permit: 14 Dec 2023.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- Kairos Hermes 1 construction permit
Construction permission · Issued / approved · NRC · decided 14 Dec 2023 · submitted 29 Sep 2021 · permit CPTR-6 · docket 50-7513 · ADAMS ML23338A258 · 88 FR 88137 · 91 FR 28629
The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.
Sources: Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit; Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 1 construction permit
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. The NRC describes Hermes as a low-power test reactor supporting Kairos Power's fluoride-salt-cooled high-temperature reactor (KP-FHR) technology, with a power level of 35 MW thermal, TRISO pebble fuel, and no electricity production. The NRC issued the Hermes construction permit to Kairos Power LLC on 14 December 2023 on an application submitted on 29 September 2021; World Nuclear News (22 April 2026) places the reactor at the Heritage Center Industrial Park in Oak Ridge, Tennessee, and says the permit's latest completion date of 31 December 2026 has been extended by 28 months, to 30 April 2029, at Kairos's request. A construction permit is not an operating license, and no opened source records an operating-license application or approval. Site preparation is kept apart from nuclear construction: Kairos broke ground in July 2024 and finished excavation in October 2024; Kairos's letter to the NRC of 1 May 2025 says excavation for the first drilled pier of the safety-related foundation began that day, and its release of 8 May 2025 says the first nuclear safety-related concrete had been placed, marking the start of nuclear construction. Kairos's 17 April 2026 release says foundation work for Hermes 1 was in progress, with Barnard Construction as general contractor for both Hermes projects. World Nuclear News reported on 22 April 2026 that Kairos expected construction to finish in 2028. The separately reported extension of the permit's latest construction-completion date from 31 December 2026 to 30 April 2029 concerns a legal deadline, not an operation forecast; the 2028 construction estimate does not establish a replacement operation date. Stored values (one 35 MWth thermal-only unit, Kairos as developer, the 14 December 2023 permit and the 2025 construction evidence) match the sources; the two Federal Register notices attached to the stored permit now return an unblock page, so the permit number CPTR-6 and the 13 May 2026 extension order were not re-read from them. Last checked 19 Oct 2026. NRC Kairos Hermes construction permit materials; World Nuclear News: Regulator extends Hermes 1 reactor construction deadline; Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227); Kairos Power: Kairos Power Begins Nuclear Safety-Related Construction of Hermes Low-Power Demonstration Reactor; Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit
What would change this
Kairos files an operating license application for Hermes 1 with the NRC, or Kairos or the NRC states a fuel-loading or first-criticality date. Next scheduled check: 19 Jan 2027.
- Operation or grid target (type stated): Not disclosed in the reviewed evidence. Kairos's July 2021 announcement targeted Hermes operation in 2026; its July 2024 announcement targeted operation in 2027. These are historical operation forecasts. The accepted April 2026 evidence instead anticipates construction completion in 2028, which is a different milestone; a current operation or first-criticality target remains unestablished. The permit's latest construction-completion date is 30 April 2029, not an operation target. Last checked 26 Oct 2026. Governor Lee, Commissioner Rolfe Announce Kairos Power to Establish Low-Power Demonstration Reactor in Oak Ridge | Kairos Power; Kairos Power Begins Construction on Hermes Low-Power Demonstration Reactor | Kairos Power; World Nuclear News: Regulator extends Hermes 1 reactor construction deadline
What would change this
Kairos files an operating license application for Hermes or states a fuel-load, criticality or startup date. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. The Commission Hermes page, last reviewed on 15 September 2026, records the construction permit issued on 14 December 2023 and does not name a pending decision or its prerequisites. World Nuclear News on 22 April 2026 reports action on the construction-completion date rather than an authorization to operate. The sources read do not state the next decision for Hermes 1. Last checked 23 Oct 2026. NRC Kairos Hermes construction permit materials; World Nuclear News: Regulator extends Hermes 1 reactor construction deadline
What would change this
A Commission schedule or Kairos filing that names the next required authorization for Hermes 1 and the prerequisites for that decision. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Nuclear Regulatory Commission Hermes page, last reviewed on 15 September 2026, states that a construction permit for the Hermes test reactor was issued to Kairos Power on 14 December 2023, after a 29 September 2021 application, public meetings on the draft environmental impact statement, and a hearing dated 19 October 2023. Kairos’s 1 May 2025 letter cites that permit as CPTR-6. World Nuclear News reported on 22 April 2026 an environmental assessment and finding of no significant impact on a completion-date amendment. The page does not show an operating license. Last checked 23 Oct 2026. NRC Kairos Hermes construction permit materials; Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227); World Nuclear News: Regulator extends Hermes 1 reactor construction deadline
What would change this
A Commission notice of an operating-license application or decision for Hermes 1, or the text of the construction-permit amendment order. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Kairos Power said on 17 April 2026 that it acquired the former K-33 land and the adjacent K-31 site in 2021 for its Oak Ridge reactor demonstration campus, and that Hermes 1 began nuclear construction at that site. World Nuclear News on 22 April 2026 places Hermes 1 at the Heritage Center Industrial Park in Oak Ridge. The Commission page says the test reactor will not produce electricity, and these sources do not state a grid interconnection or a water arrangement for Hermes 1. Last checked 23 Oct 2026. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); World Nuclear News: Regulator extends Hermes 1 reactor construction deadline; NRC Kairos Hermes construction permit materials
What would change this
A Kairos or Commission environmental document stating Hermes 1 water use, or a site instrument tying this unit to the 2021 land purchase. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. Kairos's Hermes environmental report describes used-fuel canisters cooled in a pool, then transferred to air-cooled storage, with exterior dry casks if needed. It proposes eventual truck or rail transfer to a repository or regional storage facility, without fixing a destination. The NRC's 2023 final EIS says a requested binding commitment to store fuel outside Oak Ridge was outside that environmental review's scope. These documents do not establish an executed offsite storage agreement. Last checked 23 Oct 2026. Kairos Power Hermes Environmental Report, Revision 0 (Chapters 2 and 4); NUREG-2263, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor
What would change this
Recheck at the Hermes operating license application or an updated environmental report, or if a disposal or offsite storage agreement is announced. Next scheduled check: 21 Jan 2027.
Evidence dates
(9 of 14 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(14)
- NRC Kairos Hermes construction permit materials (regulator, accessed 14 Oct 2026)
- U.S. NRC: Kairos Hermes 1 construction permit (regulator, published 15 Sep 2026, accessed 18 Oct 2026)
- Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit (regulator, accessed 3 Oct 2026)
- Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension (regulator, accessed 3 Oct 2026)
- Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227) (company, dated 1 May 2025, accessed 16 Oct 2026)
- Kairos Power: Kairos Power Begins Nuclear Safety-Related Construction of Hermes Low-Power Demonstration Reactor (company, published 8 May 2025, accessed 14 Oct 2026)
- Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026) (company, accessed 18 Oct 2026)
- World Nuclear News: Regulator extends Hermes 1 reactor construction deadline (news report, published 22 Apr 2026, accessed 18 Oct 2026)
- DOE: Advanced Reactor Demonstration Program awards $30 million in initial funding for risk reduction projects (government, published 16 Dec 2020, accessed 21 Oct 2026)
- Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor (company, published 20 Jan 2026, accessed 21 Oct 2026)
- Kairos Power Hermes Environmental Report, Revision 0 (Chapters 2 and 4) (company, accessed 23 Oct 2026)
- NUREG-2263, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (regulator, published Aug 2023, accessed 23 Oct 2026)
- Governor Lee, Commissioner Rolfe Announce Kairos Power to Establish Low-Power Demonstration Reactor in Oak Ridge | Kairos Power (company, published 16 Jul 2021, accessed 24 Oct 2026)
- Kairos Power Begins Construction on Hermes Low-Power Demonstration Reactor | Kairos Power (company, published 30 Jul 2024, accessed 24 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Kairos Hermes 1 — https://smrmap.com/projects/kairos-hermes-1/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Kairos Hermes 1”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/kairos-hermes-1/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.