Projects / United States · Construction

Kairos Hermes 1

Non-power fluoride-salt-cooled test reactor in the Oak Ridge area of Tennessee; it is not an electrical generator.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 9 of 14 listed sources have a publication or document date recorded here; the newest is 15 Sep 2026. Stage (construction) confirmed against NRC Kairos Hermes construction permit materials.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: Kairos Hermes 1 construction permit (14 Dec 2023). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
1 May 2025 · Construction start: Hermes nuclear safety-related construction begins. Kairos's 8 May 2025 release says safety-related construction started on 1 May 2025, focused on the building foundation. Source: Kairos Power: Kairos Power Begins Nuclear Safety-Related Construction of Hermes Low-Power Demonstration Reactor (published 8 May 2025); Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227) (dated 1 May 2025). Updates entry
More on this development

Its letter to the NRC dated 1 May 2025, required by permit condition 3.D, says excavation for the first drilled pier of the safety-related foundation began that day. Company statements; the first safety-related concrete is a separate event.

Next dated milestone
Planned step: 2028 (target). Kairos expects to complete Hermes construction in 2028. This is not an achieved milestone. Source: World Nuclear News: Regulator extends Hermes 1 reactor construction deadline (published 22 Apr 2026); Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Operation or first-criticality target (non-power reactor) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
Same design
2 tracked: 2 construction. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Fluoride salt-cooled high-temperature reactor. How it works, with a 3D view.
Schematic of KP-FHR commercial plant, this type's example. On the left, a reactor vessel holds a graphite reflector around a bed of fuel pebbles, with control and shutdown elements coming down from above and pebble tubes at the top and bottom.
Schematic of KP-FHR commercial plant, this type's example.

Description

The NRC issued construction permit CPTR-6 on 14 December 2023, and a May 2026 order extended the latest construction completion date to 30 April 2029. Kairos notified the NRC that excavation for the first drilled pier of the safety-related foundation began on 1 May 2025, and reported its first safety-related concrete in May 2025. Operation needs a separate NRC operating license; none is recorded.

Key facts

Design
Hermes / KP-FHR (SMR)
Technology
Fluoride-salt-cooled high-temperature reactor (FHR) · molten salt
Intended operator(s)
Kairos Power
Vendor for linked design
Kairos Power
Location
Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Hermes unit 1 (KP-FHR) in the East Tennessee Technology Park area (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. Replaces an earlier hand-placed point about 1.6 km away.
Coordinates
35.9377806, -84.4032804 · site-area point (approximate)
Electrical capacity
thermal only (no MWe) · scope: module
Thermal capacity
35 MWth (nameplate; basis unspecified)
Modules planned
1
Purpose
Research or test reactor
Construction start
1 May 2025Hermes nuclear safety-related construction begins
Inclusion basis
SMR by regulator classification
Confidence
high
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.

Status confirmed on against NRC Kairos Hermes construction permit materials. This confirms the recorded status only; the general record check date remains separate.

Site and capacity notes

Kairos Hermes 1 is recorded at Kairos Hermes site (East Tennessee Technology Park / Oak Ridge area), Tennessee, United States. Intended operator: Kairos Power. Recorded vendor: Kairos Power. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Kairos Hermes 2.

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'hermes-nuclear-power-plant-1' (35.9377806, -84.4032804)

This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 35 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Contractor
Source-backed project statement

Kairos Power's 17 April 2026 Hermes 2 groundbreaking release says Barnard Construction Company is serving as the general contractor for both Hermes reactor projects. Hermes 1 safety-related construction has been under way since May 2025, so Barnard is the working general contractor for this unit. No contract value is stated. Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026)

Funding and government decisions
  • Funder or lender named for this projectU.S. Department of Energy · sourceARDP risk-reduction award (Dec 2020): DOE share $303 million of a $629 million cost-shared total over seven years; amount disbursed not stated.
Source-backed project statement

DOE announced on 16 December 2020 an Advanced Reactor Demonstration Program risk-reduction award for Kairos's Hermes reduced-scale test reactor, with a DOE share of 303 million dollars of a 629 million dollar cost-shared total over seven years. Kairos said on 20 January 2026 that DOE is investing up to 303 million dollars in the project under a performance-based milestone contract. The amount disbursed is not stated. DOE: Advanced Reactor Demonstration Program awards $30 million in initial funding for risk reduction projects; Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor

Fuel
  • Fuel supplier named for this projectU.S. Department of Energy · sourceContract finalized (announced 20 Jan 2026) for Kairos to receive HALEU from DOE material for Hermes 1 startup and operation; delivery not stated.
  • Fuel supplier named for this projectLos Alamos National Laboratory · sourcePartner with Kairos in producing the HALEU TRISO fuel pebbles for Hermes 1 (announced 20 Jan 2026).
  • Fuel form stated for Hermes / KP-FHRTRISO fuel particles in carbon-matrix pebbles
  • Enrichment stated for Hermes / KP-FHRHigh Assay Low Enriched Uranium (HALEU)
Source-backed project statement

Kairos Power said on 20 January 2026 that it had finalized a contract with DOE to receive HALEU from DOE material for Hermes 1's startup and operation, and that it will use the material to produce TRISO fuel pebbles in partnership with Los Alamos National Laboratory. The supply contract is signed. Fabrication and delivery to the reactor are not yet reported. Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor

Comparable schedule revision

Source-backed project statement Kairos Power's 16 July 2021 release scheduled Hermes to be 'operational' in 2026; its 30 July 2024 release targeted 'operational' in 2027. This is a change in the company's own forecast wording for the same Oak Ridge demonstration reactor. Neither release defines operational as a specific startup milestone, so the dates are not converted into first criticality, electricity generation or commercial operation. The later reported 2028 construction estimate means the historical 2027 forecast is not presented as current; it does not establish a replacement operation date. The separate permit-completion deadline extension from 31 December 2026 to 30 April 2029 is a legal deadline change, not this company forecast revision. World Nuclear News: Regulator extends Hermes 1 reactor construction deadline; Governor Lee, Commissioner Rolfe Announce Kairos Power to Establish Low-Power Demonstration Reactor in Oak Ridge | Kairos Power; Kairos Power Begins Construction on Hermes Low-Power Demonstration Reactor | Kairos Power

Not found in the sources we checked (1): Customer or offtaker
Customer or offtaker

The Nuclear Regulatory Commission Hermes page, last reviewed on 15 September 2026, describes Hermes 1 as a low-power test reactor supporting Kairos Power’s own KP-FHR development and states that it will not produce electricity. Kairos Power’s 20 January 2026 release says the reactor provides learning for Kairos’s future fleet, and its 17 April 2026 release names the Tennessee Valley Authority and Google only for Hermes 2 power. Those pages and World Nuclear News on 22 April 2026 do not name a research user, test beneficiary, or service customer for Hermes 1. The developer, the Department of Energy as funder, and the regulator are not treated as customers. NRC Kairos Hermes construction permit materials; Kairos Power: U.S. Department of Energy to provide HALEU for Hermes demonstration reactor; Kairos Power: Kairos Power Breaks Ground on Hermes 2 Demonstration Plant (17 April 2026); World Nuclear News: Regulator extends Hermes 1 reactor construction deadline

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Earlier developments (1)

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Construction permit: 14 Dec 2023.

Permissions and applications

Construction applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)

Evidence dates

(9 of 14 sources with a publication or document date)
Latest dated listed source publication: U.S. NRC: Kairos Hermes 1 construction permit: 15 Sep 2026.Latest dated listed source document: Kairos Power letter KP-NRC-2505-001 to the NRC: notification of excavations for Hermes safety-related structures (ML25121A227): 1 May 2025.Latest dated recorded event: First nuclear safety-related concrete at Hermes: May 2025; Hermes nuclear safety-related construction begins: 1 May 2025; overlapping date precision — latest not uniquely established.5 of 14 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(14)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Kairos Hermes 1 — https://smrmap.com/projects/kairos-hermes-1/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Kairos Hermes 1”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/kairos-hermes-1/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.