Projects / United States · Licensing

TVA Clinch River BWRX-300

Tennessee Valley Authority proposes one BWRX-300 at the Clinch River Nuclear Site.

Current status

Stage
LicensingConstruction permit issued; physical construction is not recorded as started.
How current
General record check . Bounded evidence review . 7 of 15 listed sources have a publication or document date recorded here; the newest is 28 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: Clinch River Unit 1 construction permit (28 Sep 2026); Clinch River Nuclear Site early site permit ESP-006 (19 Dec 2019). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
Announced 29 Sep 2026 · Announcement: TVA announces NRC construction permit for Clinch River Unit 1. TVA announced that the NRC had issued a construction permit for Clinch River Unit 1. Source: TVA construction permit announcement. Updates entry
More on this development

The announcement is not a construction start.

Next dated milestone
No upcoming target date is recorded. Most recent target: Planned step: Jun 2026 (target). NRC target: final safety evaluation for the Clinch River construction permit. Met on . Source: NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308) (dated 18 Jun 2026).
Selected limitations
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

The NRC issued construction permit CPAR-2 on 28 September 2026. TVA announced the permit on 29 September 2026. The Federal Register published the notice on 5 October 2026 at 91 FR 63311. The permit authorizes construction of Clinch River Nuclear Unit 1 in Roane County, Tennessee, sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, and expires on that latest date. It is not an operating license, which needs a final safety analysis report and further Commission findings. The permit does not restate an output rating; the recorded 300 MWe net comes from the IAEA's 2026 reactor tables. The announcement is not a construction start. On 2 December 2025 DOE selected TVA for $400 million in federal cost-shared funding to advance a BWRX-300 at the Clinch River site, one of two Gen III+ SMR first-mover selections. TVA's permit announcement of 29 September 2026 says no construction date has been announced. The NRC safety evaluation issued in June 2026 describes the application's GNF2 fuel-assembly design, unchanged from GNF2 used in existing boiling-water reactors. That specification does not establish a fuel-supply, fabrication or delivery contract for Unit 1.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Intended operator(s)
Tennessee Valley Authority
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Location
Clinch River Nuclear Site · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Clinch River SMR unit 1 (BWRX-300) at TVA's Clinch River site (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot.
Coordinates
35.88944, -84.3793 · site-area point (approximate)
Electrical capacity
300 MWe (net) · scope: module
The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure.
Thermal capacity
Not recorded
Modules planned
1
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

TVA Clinch River BWRX-300 is recorded at Clinch River Nuclear Site, Tennessee, United States. Intended operator: Tennessee Valley Authority. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: B&W mPower plan at TVA's Clinch River site (2013-2017).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'clinch-river-smr-nuclear-power-plant-1' (35.88944, -84.3793)

Recorded electrical output is 300 MWe (net), scope module. The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Contractor

Source-backed project statement World Nuclear News reported on 24 January 2025 that TVA named Bechtel, Sargent & Lundy and GE Hitachi as collaborative contractors in an integrated project team to plan, design and potentially procure, construct and commission Clinch River Unit 1, with Sargent & Lundy leading site-specific detailed design. The first phase was planning and validation. Construction was a potential later scope in that announcement, not an unconditional construction award. TVA names contractors for Clinch River SMR project - World Nuclear News

Funding and government decisions
Source-backed project statement

DOE announced on 2 December 2025 that it selected TVA for 400 million dollars of federal cost-shared funding to advance a BWRX-300 at Clinch River; no signed award or disbursement is shown. World Nuclear News and POWER reported in August 2024 that TVA's board approved a further 150 million dollars, for a total of 350 million dollars approved for development of potential SMRs at Clinch River, supporting planning, design and regulatory work through fiscal 2026; that is not a construction decision. After the September 2026 permit, TVA said it continues negotiations with industry partners on cost sharing; the report names no partner agreement. DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025); TVA approves further funding for Clinch River SMR; TVA Boosts Nuclear Funding with $150M for SMR Development at Clinch River; WNN: First construction permit issued for BWRX-300 SMR in US

Site host or owner
Comparable schedule revision
A documented comparable revision is recorded. It is not a completed source review.

Source-backed project statement The NRC's 18 June 2026 letter says staff had planned in July 2025 to issue the final safety evaluation for TVA's Clinch River construction permit application by November 2026 and now planned to issue it by 30 June 2026. This is an accelerated regulator-review target for the same document, not a construction or operation date and not proof that the target was achieved. NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308)

Not found in the sources we checked (2): Customer or offtaker; Fuel
Customer or offtaker

TVA's 29 September 2026 permit announcement describes TVA as a federal utility that sells electricity and says no construction date has been announced for Clinch River Unit 1. It names no buyer or allocation of the unit's output beyond TVA's general role as a power supplier. TVA construction permit announcement

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

The NRC construction permit, TVA's 29 September 2026 announcement, DOE's December 2025 selection and World Nuclear News' January 2025 contractor report name no fuel supplier, fabrication contract or delivery for Clinch River Unit 1. TVA construction permit announcement

Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
Programs and agreements naming the project

Timeline

Recorded developments

Earlier developments (6)

Targets

Planned, target and estimated dates are not achievements or commitments.

Schedule changes

The same milestone as stated at two dates. A revised target is still a target; the earlier target is kept for comparison and no longer counts as upcoming.

Dates on the project record: Construction permit: 28 Sep 2026.

Permissions and applications

Site applications and decisions

Construction applications and decisions

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. Construction Permit No. CPAR-2, dated 28 September 2026, is issued to the Tennessee Valley Authority for Clinch River Nuclear Unit 1, a facility owned by TVA in Roane County, Tennessee, on an application that references early site permit ESP-006; TVA's release of 29 September 2026 says Unit 1 is a GE Vernova Hitachi BWRX-300 at its Clinch River Nuclear Site near Oak Ridge. The NRC page (updated 30 September 2026) lists the environmental report (Part One) submitted on 28 April 2025, the preliminary safety analysis report acceptance on 9 July 2025, the final safety evaluation report on 25 June 2026, the mandatory hearing on 13 August 2026 and the permit decision on 28 September 2026. The permit authorizes construction of one unit; it is not an operating license, which needs a final safety analysis report and further Commission findings. TVA says no construction date has been announced and it continues negotiating cost sharing with partners, so no nuclear construction start is documented; the NRC page lists a granted exemption allowing excavation before the permit, which is site work, and no opened source says when or whether excavation began. The permit sets earliest construction completion on 1 October 2031 and latest on 30 September 2032; these are permit limits, not achieved dates. The permit states no output; World Nuclear News (30 September 2026) calls the BWRX-300 design a 300 MWe reactor, and the stored 300 MWe net per unit rests on the IAEA 2026 table reading. DOE's 2 December 2025 release selected TVA for $400 million to advance a BWRX-300 at Clinch River; a funding selection is not a construction decision. The licensing stage stays because a permit alone is not documented nuclear construction. World Nuclear News dates TVA's application to May 2025, while the NRC page shows Part One on 28 April 2025 and Part Two on 20 May 2025. Last checked 19 Oct 2026. IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); TVA construction permit announcement; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056); NRC: TVA Clinch River construction permit application; WNN: First construction permit issued for BWRX-300 SMR in US; DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025)
    What would change this

    A TVA construction-start or investment decision for Clinch River Unit 1, an NRC inspection or TVA notice of safety-related construction, or an operating license application. Next scheduled check: 19 Jan 2027.

  • Plant capacity (scope qualified). The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure. Construction permit CPAR-2 incorporates the application by reference and does not restate an output rating, so the recorded figure is not a permit rating. Last checked 16 Oct 2026. IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)
    What would change this

    TVA applies for an operating license, or the NRC or IAEA publishes a different output for Clinch River Unit 1. Next scheduled check: 14 Jan 2027.

  • Next decision and prerequisites. Construction permit CPAR-2, issued 28 September 2026, sets the earliest date for completing construction of Clinch River Unit 1 as 1 October 2031 and the latest as 30 September 2032. The permit also anticipates a later operating license or combined license application referencing it, which TVA would need before operating the unit. No filing date for that application is given in these sources; the construction dates are permit bounds, not achieved events. Last checked 23 Oct 2026. NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)
    What would change this

    TVA's operating license application, a construction-start announcement, or a permit amendment changing the completion dates. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The NRC issued construction permit CPAR-2 for Clinch River Unit 1 on 28 September 2026; the permit states it follows a public hearing and references TVA's 2019 early site permit. The NRC and Army Corps' April 2026 final supplemental environmental impact statement records a public comment period on the draft from 7 November to 22 December 2025. The same document says TVA had not yet applied for the Army Corps permit needed for fill or dredging in waters of the U.S. Operation needs a separate NRC operating license, which has not been issued. Last checked 23 Oct 2026. NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056); Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
    What would change this

    TVA's Army Corps permit application, an operating license application, or a challenge to CPAR-2. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The April 2026 final supplemental environmental impact statement says TVA would build Clinch River Unit 1 on 1,200 acres of its own Clinch River property in Roane County, Tennessee. TVA proposes a new 161 kV switchyard looping in two existing TVA 161 kV lines, including a relocated line through a new corridor, and a closed-cycle cooling tower with makeup water from the Clinch River arm of Watts Bar Reservoir. These are TVA's proposals as reviewed for the permit; the Army Corps permit for in-water work had not been applied for. Last checked 23 Oct 2026. Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
    What would change this

    Completion of the switchyard and line relocation, or the Army Corps permit decision for the intake and discharge works. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. TVA's representations for Clinch River Unit 1, summarized in the April 2026 final supplemental environmental impact statement, say the fuel pool can hold eight years of spent fuel plus a full core offload, after which spent fuel would be stored onsite in dry casks at an independent spent fuel storage installation. This is TVA's stated plan reviewed for the construction permit, not a built or licensed storage installation, and no offsite disposal arrangement is named. Last checked 23 Oct 2026. Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
    What would change this

    An operating license application or ISFSI filing that changes or confirms the onsite storage plan. Next scheduled check: 23 Apr 2027.

Evidence dates

(7 of 15 sources with a publication or document date)
Latest dated listed source publication: NRC safety evaluation for Clinch River Nuclear Unit 1, ML26168A505: Jun 2026.Latest dated listed source document: NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056): 28 Sep 2026.Latest dated recorded event: TVA announces Clinch River Unit 1 construction permit: 29 Sep 2026.8 of 15 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(15)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: TVA Clinch River BWRX-300 — https://smrmap.com/projects/clinch-river-bwrx-300/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “TVA Clinch River BWRX-300”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/clinch-river-bwrx-300/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.