TVA Clinch River BWRX-300
Tennessee Valley Authority proposes one BWRX-300 at the Clinch River Nuclear Site.
Current status
- How current
- General record check . Bounded evidence review . 7 of 15 listed sources have a publication or document date recorded here; the newest is 28 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: Clinch River Unit 1 construction permit (28 Sep 2026); Clinch River Nuclear Site early site permit ESP-006 (19 Dec 2019). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- Announced 29 Sep 2026 · Announcement: TVA announces NRC construction permit for Clinch River Unit 1. TVA announced that the NRC had issued a construction permit for Clinch River Unit 1. Source: TVA construction permit announcement. Updates entry
More on this development
The announcement is not a construction start.
- Next dated milestone
- No upcoming target date is recorded. Most recent target: Planned step: Jun 2026 (target). NRC target: final safety evaluation for the Clinch River construction permit. Met on . Source: NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308) (dated 18 Jun 2026).
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The NRC issued construction permit CPAR-2 on 28 September 2026. TVA announced the permit on 29 September 2026. The Federal Register published the notice on 5 October 2026 at 91 FR 63311. The permit authorizes construction of Clinch River Nuclear Unit 1 in Roane County, Tennessee, sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, and expires on that latest date. It is not an operating license, which needs a final safety analysis report and further Commission findings. The permit does not restate an output rating; the recorded 300 MWe net comes from the IAEA's 2026 reactor tables. The announcement is not a construction start. On 2 December 2025 DOE selected TVA for $400 million in federal cost-shared funding to advance a BWRX-300 at the Clinch River site, one of two Gen III+ SMR first-mover selections. TVA's permit announcement of 29 September 2026 says no construction date has been announced. The NRC safety evaluation issued in June 2026 describes the application's GNF2 fuel-assembly design, unchanged from GNF2 used in existing boiling-water reactors. That specification does not establish a fuel-supply, fabrication or delivery contract for Unit 1.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Intended operator(s)
- Tennessee Valley Authority
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Location
- Clinch River Nuclear Site · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Clinch River SMR unit 1 (BWRX-300) at TVA's Clinch River site (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. - Coordinates
- 35.88944, -84.3793 · site-area point (approximate)
- Electrical capacity
- 300 MWe (net) · scope: module
The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure. - Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
TVA Clinch River BWRX-300 is recorded at Clinch River Nuclear Site, Tennessee, United States. Intended operator: Tennessee Valley Authority. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: B&W mPower plan at TVA's Clinch River site (2013-2017).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'clinch-river-smr-nuclear-power-plant-1' (35.88944, -84.3793)
Recorded electrical output is 300 MWe (net), scope module. The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Application filing entityTennessee Valley Authority · source
- Operator or intended licensed owner
- Intended operatorTennessee Valley Authority
- Intended licensed ownerTennessee Valley Authority · source
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
- Contractor
Source-backed project statement World Nuclear News reported on 24 January 2025 that TVA named Bechtel, Sargent & Lundy and GE Hitachi as collaborative contractors in an integrated project team to plan, design and potentially procure, construct and commission Clinch River Unit 1, with Sargent & Lundy leading site-specific detailed design. The first phase was planning and validation. Construction was a potential later scope in that announcement, not an unconditional construction award. TVA names contractors for Clinch River SMR project - World Nuclear News
- Funding and government decisions
- Public award or selection; not a disbursement; selected — award terms not recorded as finalGen III+ SMR selection: TVA (Clinch River BWRX-300) · sourceDOE names the BWRX-300 at TVA's Clinch River site.
Source-backed project statement
DOE announced on 2 December 2025 that it selected TVA for 400 million dollars of federal cost-shared funding to advance a BWRX-300 at Clinch River; no signed award or disbursement is shown. World Nuclear News and POWER reported in August 2024 that TVA's board approved a further 150 million dollars, for a total of 350 million dollars approved for development of potential SMRs at Clinch River, supporting planning, design and regulatory work through fiscal 2026; that is not a construction decision. After the September 2026 permit, TVA said it continues negotiations with industry partners on cost sharing; the report names no partner agreement. DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025); TVA approves further funding for Clinch River SMR; TVA Boosts Nuclear Funding with $150M for SMR Development at Clinch River; WNN: First construction permit issued for BWRX-300 SMR in US
- Site host or owner
- Current site ownerTennessee Valley Authority · source
- Comparable schedule revision
- A documented comparable revision is recorded. It is not a completed source review.
Source-backed project statement The NRC's 18 June 2026 letter says staff had planned in July 2025 to issue the final safety evaluation for TVA's Clinch River construction permit application by November 2026 and now planned to issue it by 30 June 2026. This is an accelerated regulator-review target for the same document, not a construction or operation date and not proof that the target was achieved. NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308)
Not found in the sources we checked (2): Customer or offtaker; Fuel
- Customer or offtaker
TVA's 29 September 2026 permit announcement describes TVA as a federal utility that sells electricity and says no construction date has been announced for Clinch River Unit 1. It names no buyer or allocation of the unit's output beyond TVA's general role as a power supplier. TVA construction permit announcement
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
The NRC construction permit, TVA's 29 September 2026 announcement, DOE's December 2025 selection and World Nuclear News' January 2025 contractor report name no fuel supplier, fabrication contract or delivery for Clinch River Unit 1. TVA construction permit announcement
Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
TVA announces NRC construction permit for Clinch River Unit 1 - · Construction permission recorded
Construction permit issued for TVA's Clinch River Unit 1 - · Recorded development
NRC holds mandatory hearing on Clinch River construction permit - · Regulatory step
NRC issues the final safety evaluation report for the Clinch River construction permit application - Announced · Recorded development
DOE selects TVA for $400 million in cost-shared funding for Clinch River BWRX-300
Earlier developments (6)
- · Selections announced
Selections announced: Gen III+ SMR selection: TVA (Clinch River BWRX-300) - · Regulatory step
NRC completes PSAR acceptance review (application docketed) - · Regulatory step
TVA submits construction permit application Part Two (PSAR) - · Application submitted
Application for the Clinch River Unit 1 construction permit - · Site permission recorded
Site permission recorded: Clinch River Nuclear Site early site permit ESP-006 - · Application submitted
Application for the Clinch River early site permit
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step · Met on
NRC target: final safety evaluation for the Clinch River construction permit
Schedule changes
The same milestone as stated at two dates. A revised target is still a target; the earlier target is kept for comparison and no longer counts as upcoming.
- NRC target: final safety evaluation for the Clinch River construction permit
Nov 2026 (stated 25 Jul 2025) → Jun 2026 (stated 18 Jun 2026) · Moved earlier
Source: NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308) (dated 18 Jun 2026).
Dates on the project record: Construction permit: 28 Sep 2026.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- Clinch River Nuclear Site early site permit ESP-006
Site permission · Issued / approved · NRC · decided 19 Dec 2019 · submitted 12 May 2016 · permit ESP-006
NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.
Sources: U.S. NRC: Clinch River Nuclear Site early site permit ESP-006
Construction applications and decisions
- Clinch River Unit 1 construction permit
Construction permission · Issued / approved · NRC · decided 28 Sep 2026 · submitted 28 Apr 2025 · permit CPAR-2 · docket 50-615 · ADAMS ML26244A257, ML26243A056 · 91 FR 63311
The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: Federal Register 91 FR 63311 (5 Oct 2026): Clinch River Nuclear Unit 1 construction permit and record of decision; TVA construction permit announcement; NRC: TVA Clinch River construction permit application; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. Construction Permit No. CPAR-2, dated 28 September 2026, is issued to the Tennessee Valley Authority for Clinch River Nuclear Unit 1, a facility owned by TVA in Roane County, Tennessee, on an application that references early site permit ESP-006; TVA's release of 29 September 2026 says Unit 1 is a GE Vernova Hitachi BWRX-300 at its Clinch River Nuclear Site near Oak Ridge. The NRC page (updated 30 September 2026) lists the environmental report (Part One) submitted on 28 April 2025, the preliminary safety analysis report acceptance on 9 July 2025, the final safety evaluation report on 25 June 2026, the mandatory hearing on 13 August 2026 and the permit decision on 28 September 2026. The permit authorizes construction of one unit; it is not an operating license, which needs a final safety analysis report and further Commission findings. TVA says no construction date has been announced and it continues negotiating cost sharing with partners, so no nuclear construction start is documented; the NRC page lists a granted exemption allowing excavation before the permit, which is site work, and no opened source says when or whether excavation began. The permit sets earliest construction completion on 1 October 2031 and latest on 30 September 2032; these are permit limits, not achieved dates. The permit states no output; World Nuclear News (30 September 2026) calls the BWRX-300 design a 300 MWe reactor, and the stored 300 MWe net per unit rests on the IAEA 2026 table reading. DOE's 2 December 2025 release selected TVA for $400 million to advance a BWRX-300 at Clinch River; a funding selection is not a construction decision. The licensing stage stays because a permit alone is not documented nuclear construction. World Nuclear News dates TVA's application to May 2025, while the NRC page shows Part One on 28 April 2025 and Part Two on 20 May 2025. Last checked 19 Oct 2026. IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); TVA construction permit announcement; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056); NRC: TVA Clinch River construction permit application; WNN: First construction permit issued for BWRX-300 SMR in US; DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025)
What would change this
A TVA construction-start or investment decision for Clinch River Unit 1, an NRC inspection or TVA notice of safety-related construction, or an operating license application. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified). The IAEA's 2026 reactor tables, which report Member State data to 31 December 2025, list Clinch River SMR-1 at 300 MW gross and 300 MW net with no thermal figure. Construction permit CPAR-2 incorporates the application by reference and does not restate an output rating, so the recorded figure is not a permit rating. Last checked 16 Oct 2026. IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)
What would change this
TVA applies for an operating license, or the NRC or IAEA publishes a different output for Clinch River Unit 1. Next scheduled check: 14 Jan 2027.
- Next decision and prerequisites. Construction permit CPAR-2, issued 28 September 2026, sets the earliest date for completing construction of Clinch River Unit 1 as 1 October 2031 and the latest as 30 September 2032. The permit also anticipates a later operating license or combined license application referencing it, which TVA would need before operating the unit. No filing date for that application is given in these sources; the construction dates are permit bounds, not achieved events. Last checked 23 Oct 2026. NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)
What would change this
TVA's operating license application, a construction-start announcement, or a permit amendment changing the completion dates. Next scheduled check: 23 Apr 2027.
- Permissions and public process. The NRC issued construction permit CPAR-2 for Clinch River Unit 1 on 28 September 2026; the permit states it follows a public hearing and references TVA's 2019 early site permit. The NRC and Army Corps' April 2026 final supplemental environmental impact statement records a public comment period on the draft from 7 November to 22 December 2025. The same document says TVA had not yet applied for the Army Corps permit needed for fill or dredging in waters of the U.S. Operation needs a separate NRC operating license, which has not been issued. Last checked 23 Oct 2026. NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056); Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
What would change this
TVA's Army Corps permit application, an operating license application, or a challenge to CPAR-2. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). The April 2026 final supplemental environmental impact statement says TVA would build Clinch River Unit 1 on 1,200 acres of its own Clinch River property in Roane County, Tennessee. TVA proposes a new 161 kV switchyard looping in two existing TVA 161 kV lines, including a relocated line through a new corridor, and a closed-cycle cooling tower with makeup water from the Clinch River arm of Watts Bar Reservoir. These are TVA's proposals as reviewed for the permit; the Army Corps permit for in-water work had not been applied for. Last checked 23 Oct 2026. Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
What would change this
Completion of the switchyard and line relocation, or the Army Corps permit decision for the intake and discharge works. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. TVA's representations for Clinch River Unit 1, summarized in the April 2026 final supplemental environmental impact statement, say the fuel pool can hold eight years of spent fuel plus a full core offload, after which spent fuel would be stored onsite in dry casks at an independent spent fuel storage installation. This is TVA's stated plan reviewed for the construction permit, not a built or licensed storage installation, and no offsite disposal arrangement is named. Last checked 23 Oct 2026. Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226)
What would change this
An operating license application or ISFSI filing that changes or confirms the onsite storage plan. Next scheduled check: 23 Apr 2027.
Evidence dates
(7 of 15 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(15)
- Federal Register 91 FR 63311 (5 Oct 2026): Clinch River Nuclear Unit 1 construction permit and record of decision (regulator, accessed 5 Oct 2026)
- TVA construction permit announcement (company, accessed 18 Oct 2026)
- NRC: TVA Clinch River construction permit application (regulator, accessed 3 Nov 2026)
- WNN: First construction permit issued for BWRX-300 SMR in US (news report, accessed 2 Oct 2026)
- Nuclear News Network — SMRs explained (news report, accessed 1 Oct 2026)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056) (regulator, dated 28 Sep 2026, accessed 16 Oct 2026)
- IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026) (IAEA/NEA, accessed 9 Oct 2026)
- DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025) (government, accessed 3 Nov 2026)
- TVA names contractors for Clinch River SMR project - World Nuclear News (news report, published 24 Jan 2025, accessed 21 Oct 2026)
- NRC letter: Clinch River Unit 1 construction permit application review status (ADAMS ML26160A308) (regulator, dated 18 Jun 2026, accessed 21 Oct 2026)
- Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site, Final Report (Supplement to NUREG-2226) (regulator, published Apr 2026, accessed 23 Oct 2026)
- TVA approves further funding for Clinch River SMR (news report, published 23 Aug 2024, accessed 24 Oct 2026)
- TVA Boosts Nuclear Funding with $150M for SMR Development at Clinch River (news report, published 22 Aug 2024, accessed 24 Oct 2026)
- NRC safety evaluation for Clinch River Nuclear Unit 1, ML26168A505 (regulator, published Jun 2026, accessed 26 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: TVA Clinch River BWRX-300 — https://smrmap.com/projects/clinch-river-bwrx-300/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “TVA Clinch River BWRX-300”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/clinch-river-bwrx-300/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.