Projects / United States · Announced
Aalo fleet proposal at Idaho Falls Power's Energy Research Park
In September 2024 Idaho Falls Power announced negotiations with Aalo Atomics toward a fleet of seven commercial Aalo-1 reactors on land leased at its Energy Research Park.
Current status
- How current
- General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 15 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Aalo's NRC pre-application for a seven-unit Aalo-1 plant is titled the Idaho Nuclear Project; its 2026 reference-license plan names no site, so the current site commitment is unconfirmed. The 2024 applicant plan describes Aalo-1 at 10 MWe per reactor without a gross/net basis; later project status is not established and cancellation is not inferred.
Key facts
- Design
- Aalo-1 (Microreactor)
- Technology
- Other · sodium
- Operator(s)
- Not recorded
- Vendor for linked design
- Aalo Atomics
- Location
- Idaho Falls Power Energy Research Park · United States · precision: town or locality only
NuclearChain reactors export point for this Aalo Idaho proposal (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker). The export uses nearly the same point for other Idaho National Laboratory entries, so it stands for Idaho Falls, not the Energy Research Park: a town-level point. - Coordinates
- 43.5194849, -112.0459647 · town-level point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 9 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Aalo fleet proposal at Idaho Falls Power's Energy Research Park is recorded at Idaho Falls Power Energy Research Park, Idaho, United States. Operator: No operator is recorded. Recorded vendor: Aalo Atomics. Stage: Announced. Location precision: town or locality only; town-level point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'aalo-atomics-idaho-nuclear-power-plant-1' (43.5194849, -112.0459647)
Electrical output is not recorded on this project. Modules planned: 7. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerAalo Atomics · source
- Reactor supplier
- Vendor for the linked designAalo Atomics
- Customer or offtaker
Source-backed project statement Idaho Falls Power announced on 16 September 2024 that it is negotiating a power purchase agreement with Aalo Atomics, which would give the city utility the right to eventually buy energy from Aalo's Idaho Falls project at its Energy Research Park. Idaho Falls Power is therefore a prospective buyer. The agreement was under negotiation, not signed, and Aalo's page the same day calls the instrument a memorandum of understanding. Idaho Falls Power negotiating agreement with Aalo Atomics
- Fuel
- Fuel form stated for Aalo-1UO₂ ceramic
- Enrichment stated for Aalo-18 % LEU+
Aalo's July 2024 NRC engagement plan says the Aalo-1 uses uranium zirconium hydride fuel that does not depend on HALEU and that the reactors would be fueled on site. That is a design and plan description, not a supply commitment. Neither that plan nor the 16 September 2024 city and Aalo announcements name a fuel fabricator, quantity or delivery for the Idaho Falls reactors. Aalo-1 regulatory engagement plan (ML24193A003)
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
Aalo's 16 September 2024 announcement says the seven Aalo-1 reactors for the Idaho Falls project would be built in Aalo's own Austin reactor factory. That is the vendor's manufacturing plan, not an outside engineering or construction appointment. Idaho Falls Power's announcement the same day and Aalo's July 2024 NRC engagement plan name no engineering, construction or other contractor for the Energy Research Park plant. Aalo Atomics: signs MOU with Idaho Falls Power for fleet of seven Aalo-1 reactors; Idaho Falls Power negotiating agreement with Aalo Atomics
- Funding and government decisions
Aalo's 16 September 2024 announcement says the memorandum lets the project proceed to full construction only after cost and uncertainty milestones are met, and it states no amount. Idaho Falls Power's announcement the same day gives no price for power or the land lease, and Aalo's July 2024 NRC engagement plan discusses capital costs without a figure or funder for this plant. Aalo Atomics: signs MOU with Idaho Falls Power for fleet of seven Aalo-1 reactors; Aalo-1 regulatory engagement plan (ML24193A003)
- Comparable schedule revision
On 16 September 2024 Idaho Falls Power said Aalo's Idaho Falls project is not expected to come online before 2030, while Aalo's announcement the same day said it was slated to go online before the end of the 2020s. These are two differing same-day statements of one online date, not a dated revision. Aalo's July 2024 NRC engagement plan says its unnamed-site Idaho Nuclear Project is to be operational by 2029. Idaho Falls Power negotiating agreement with Aalo Atomics; Aalo Atomics: signs MOU with Idaho Falls Power for fleet of seven Aalo-1 reactors; Aalo-1 regulatory engagement plan (ML24193A003)
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. On 16 September 2024 Idaho Falls Power said it was negotiating a power purchase agreement with Aalo Atomics, and that under the agreement Aalo would lease land for up to 80 years at Idaho Falls Power's Energy Research Park. Aalo's same-day page calls the instrument a memorandum of understanding for seven factory-built Aalo-1 reactors totaling 75 MW. Aalo's 1 July 2024 regulatory engagement plan tells the NRC the Idaho Nuclear Project would comprise seven Aalo-1 microreactors under a Class 103 combined license. The plan does not, in the quoted project description, name Energy Research Park, so the page and the plan are the same company project only to the extent both say seven Aalo-1 units. The stored design, seven modules, Aalo as proposer and vendor, and announced stage stay. The 75 MW figure has no gross or net basis and is not proposed as a stored plant rating. The PPA was being negotiated, not signed. Last checked 19 Oct 2026. Idaho Falls Power negotiating agreement with Aalo Atomics; Aalo Atomics: signs MOU with Idaho Falls Power for fleet of seven Aalo-1 reactors; Aalo-1 regulatory engagement plan (ML24193A003)
What would change this
A signed power purchase agreement or lease, or an NRC application that names the Energy Research Park, would change this record. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. Idaho Falls Power names its Energy Research Park as the land Aalo would lease. No coordinates are given. Last checked 19 Oct 2026. Idaho Falls Power negotiating agreement with Aalo Atomics
What would change this
The lease or an NRC application with a site description would fix the footprint. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Aalo's September 2026 engagement plan says it will submit its reference combined license application after approval and full-power operation of its Aalo-X reactor, currently anticipated in the second quarter of 2027, and that the date may be affected by the Aalo-X timeline. Idaho Falls Power said in 2024 the project was not expected online before 2030. The plan does not confirm that the application will name the Energy Research Park, and the outcome of the power purchase negotiation is not reported in the sources reviewed. Last checked 23 Oct 2026. Regulatory Engagement Plan for the Aalo R-COLA, PLN-AALO-2026-008-NP, Revision A; Idaho Falls Power negotiating agreement with Aalo Atomics
What would change this
Aalo's R-COLA filing, or an Idaho Falls Power announcement on the agreement. Next scheduled check: 23 Apr 2027.
- Permissions and public process. The NRC lists pre-application activities for Aalo's Idaho Nuclear Project, a seven-unit Aalo-1 plant, including Aalo's 2024 engagement plan for a combined license and a September 2026 plan for a reference combined license application under the NRC's new Part 53 rules. Idaho Falls Power's September 2024 release says it was negotiating a power purchase agreement with Aalo. No NRC application, license, city approval of a final agreement or public hearing is recorded in these sources. Last checked 23 Oct 2026. NRC: Aalo Atomics Idaho Nuclear Project (pre-application); Regulatory Engagement Plan for the Aalo R-COLA, PLN-AALO-2026-008-NP, Revision A; Idaho Falls Power negotiating agreement with Aalo Atomics
What would change this
Aalo's combined license application filing, or Idaho Falls Power board or city approval of the Aalo agreement. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Idaho Falls Power's September 2024 release says that, under the agreement then being negotiated, Aalo would lease land for up to 80 years at the utility's new Energy Research Park, where a peaking plant was under construction. Aalo's September 2026 engagement plan for its reference license application speaks of building after selecting a suitable site and does not name the Energy Research Park. A lease under negotiation is not secured land, and no grid or water arrangement is stated. Last checked 23 Oct 2026. Idaho Falls Power negotiating agreement with Aalo Atomics; Regulatory Engagement Plan for the Aalo R-COLA, PLN-AALO-2026-008-NP, Revision A
What would change this
An executed Aalo lease at the Energy Research Park, or a license application naming the site. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Idaho Falls Power's September 2024 release, Aalo's 2024 engagement plan for the Idaho Nuclear Project and its September 2026 reference-application plan do not say who would be responsible for spent fuel from the seven-reactor plant or how it would be stored or disposed of. Last checked 23 Oct 2026. Regulatory Engagement Plan for the Aalo R-COLA, PLN-AALO-2026-008-NP, Revision A
What would change this
A license application or environmental report for the Aalo plant describing spent-fuel storage. Next scheduled check: 23 Apr 2027.
Evidence dates
(1 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- Idaho Falls Power negotiating agreement with Aalo Atomics (company, accessed 8 Oct 2026)
- Aalo Atomics: signs MOU with Idaho Falls Power for fleet of seven Aalo-1 reactors (company, accessed 2 Oct 2026)
- NRC: Aalo Atomics Idaho Nuclear Project (pre-application) (regulator, accessed 2 Oct 2026)
- Aalo-1 regulatory engagement plan (ML24193A003) (regulator, accessed 9 Oct 2026)
- Regulatory Engagement Plan for the Aalo R-COLA, PLN-AALO-2026-008-NP, Revision A (company, published 15 Sep 2026, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Aalo fleet proposal at Idaho Falls Power's Energy Research Park — https://smrmap.com/projects/aalo-idaho-falls-erp/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Aalo fleet proposal at Idaho Falls Power's Energy Research Park”. Record reviewed 9 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/aalo-idaho-falls-erp/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.