AEP Joshua Falls SMR proposal

Appalachian Power has identified its Joshua Falls property in Campbell County for possible small modular reactor development.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
12 Nov 2025 · Published: Published: Virginia SCC final order: Appalachian Power Joshua Falls development costs. The caption prints AT RICHMOND, NOVEMBER 12, 2025. Source: Virginia SCC final order, Case No. PUR-2025-00085. Updates entry
More on this development

The order states no later effective date.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

On 12 November 2025 the Virginia State Corporation Commission approved the decision to incur early development costs. That order is not a construction permit and not cost recovery. The NRC records early-site-permit pre-application engagement for this named site; no site permit application or permit is established by that pre-application. Reactor technology remains unselected.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Not recorded
Vendor for linked design
No selected-design vendor recorded
Location
Joshua Falls, Campbell County · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate coordinates for the named Joshua Falls site from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker); AEP Joshua Falls SMR proposal.
Coordinates
37.4292, -79.0399 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
9 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

AEP Joshua Falls SMR proposal is recorded at Joshua Falls, Campbell County, Virginia, United States. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'joshua-falls-nuclear-power-plant' (37.4291821, -79.0399344)

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Contractor

Source-backed project statement The Virginia commission’s 12 November 2025 order records APCo’s statement that it had selected an early-site-permit contractor for Joshua Falls. The cited passage does not name the contractor. This is preparatory licensing work, not a construction award or an operator appointment. Virginia SCC final order, Case No. PUR-2025-00085

Funding and government decisions
Source-backed project statement

Virginia's State Corporation Commission approved on 12 November 2025 Appalachian Power's decision to incur early development costs for a possible SMR at its Joshua Falls site, without approving cost recovery, which the company expected to seek in mid-2026 through customer rates. AEP said in January 2025 that Appalachian Power had applied for a 35 million dollar DOE grant for the early site permit work. The utility is funding early development itself, and no DOE award for Joshua Falls is reported in the sources read. Virginia SCC final order, Case No. PUR-2025-00085; AEP potential new SMR sites

Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
Customer or offtaker

The Virginia order quotes the statute on a future certificate to construct a facility to serve customers in the Commonwealth or in West Virginia. That is a class of utility service, not a named buyer or quantity. Steel Dynamics, Inc. filed a notice of participation and was later excused from the hearing. That participation is not an offtake. No power-purchase agreement is stated. Virginia SCC final order, Case No. PUR-2025-00085

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The order lists reactor original-equipment-manufacturer evaluation and selection as an early-development activity. The AEP release says no technology provider has been identified at Joshua Falls. No fuel supplier, fuel form, or delivery is stated. Virginia SCC final order, Case No. PUR-2025-00085

Comparable schedule revision

Comparable schedule revision not established. The NRC page gives one plan: early-site-permit submittal in April 2027, during a pre-application period that began in December 2024. The order's 31 December 2026 report, and the company's expectation of a mid-2026 cost-recovery request, are different milestones. The order's estimate of seven to twelve years is one undated range for a whole project, not a revision of the April 2027 plan. NRC pre-application activities: APCo Joshua Falls

Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes, 1 not yet reviewed)
  • Evidence review. Appalachian Power proposes an SMR at its company-owned Joshua Falls property in Campbell County, Virginia. AEP's 17 January 2025 announcement distinguishes this proposal from the BWRX-300 work at Rockport and says no Joshua Falls technology provider had been identified. The Virginia commission's 12 November 2025 final order approves the decision to incur early development costs, not cost recovery or reactor construction; it directs a progress report by 31 December 2026 if the company does not apply for a cost-recovery adjustment during 2026. NRC's project page describes pre-application engagement for a future early site permit and a planned April 2027 submittal, not an application already filed or a permit granted. Appalachian Power is the proposer and property owner; neither that role nor an ESP contractor establishes an intended reactor operator. The next documented step is the planned ESP application; design selection and project permissions remain open. No broad record-review date or stage is advanced by this bounded passage review. Last checked 19 Oct 2026. AEP potential new SMR sites; Virginia SCC final order, Case No. PUR-2025-00085; NRC pre-application activities: APCo Joshua Falls
    What would change this

    Appalachian Power's Joshua Falls ESP application, a reactor-technology selection or the Virginia commission's required 2026 progress/cost-recovery filing. Next scheduled check: 7 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. On this page, Joshua Falls is the Campbell County property where Appalachian Power began an early site permit process. The GEH BWRX-300 sentences describe the Rockport Plant site in Indiana, not Joshua Falls. Last checked 19 Oct 2026. AEP potential new SMR sites
    What would change this

    An Appalachian Power or NRC document that names a reactor technology for the Joshua Falls property. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The next regulatory step is an early-site-permit application to the NRC for Joshua Falls, on which the SCC order requires progress reports; recovery of development costs would be decided in a later SCC proceeding. No application date is recorded in the opened sources. Last checked 23 Oct 2026. Virginia SCC final order, Case No. PUR-2025-00085
    What would change this

    An NRC docketing notice for a Joshua Falls early-site-permit application. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The Virginia State Corporation Commission's 12 November 2025 final order reviewed Appalachian Power's decision to incur early SMR development costs; the company sought no cost recovery in that case, and the order requires reports on its early-site-permit work at the NRC. AEP says it held a public meeting in December 2024. A cost-decision review is not a permit, and no NRC early site permit is recorded as issued. Last checked 23 Oct 2026. Virginia SCC final order, Case No. PUR-2025-00085; AEP potential new SMR sites
    What would change this

    An NRC early-site-permit application or decision for Joshua Falls, or an SCC cost-recovery proceeding. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). AEP describes Joshua Falls as company-owned property in Campbell County, Virginia, where Appalachian Power began the early-site-permit process. Ownership of the land is stated; no grid-connection, cooling-water or other infrastructure arrangement for a reactor is described in the opened sources. Last checked 23 Oct 2026. AEP potential new SMR sites
    What would change this

    An early-site-permit application or environmental report describing the Joshua Falls site. Next scheduled check: 21 Jan 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 4 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: AEP Joshua Falls SMR proposal documented: 17 Jan 2025.4 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: AEP Joshua Falls SMR proposal — https://smrmap.com/projects/aep-joshua-falls/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “AEP Joshua Falls SMR proposal”. Record reviewed 9 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/aep-joshua-falls/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.