Projects / United States · Siting

Westinghouse eVinci at Malmstrom Air Force Base (ANPI)

The Department of the Air Force named Malmstrom a potential microreactor site and, in April 2026, paired Westinghouse to evaluate siting and construction of an eVinci there.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: 23 Apr 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
Same design
5 tracked: 1 siting, 2 announced. Separately: 2 canceled. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Heat-pipe microreactor. How it works, with a 3D view.
Schematic of eVinci. A horizontal canister holds a graphite core block with rows of fuel compacts, with control drums above and below it and shutdown rods coming in from the left.
Schematic of eVinci.

Description

Reporting describes ANPI reactors as contractor-owned and operated and names Westinghouse Government Services, the company paired with Malmstrom, as a selected potential developer and operator. No operator profile is linked: the selection is described as potential and the awardee is a separately named Westinghouse company. The Air Force is the host, not the operator. Environmental review is the next step; output is not stated.

Key facts

Design
eVinci (Microreactor)
Technology
Other · other
Operator(s)
Not recorded
Vendor for linked design
Westinghouse Electric Company
Location
Malmstrom Air Force Base · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Installation point from the Wikipedia article for Malmstrom Air Force Base; the sources name the installation but no pad or parcel on it, so this marks the base area, not a reactor site (Eielson and Buckley precedent).
Coordinates
47.50472, -111.18722 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
10 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Westinghouse eVinci at Malmstrom Air Force Base (ANPI) is recorded at Malmstrom Air Force Base, Montana, United States. Operator: No operator is recorded. Recorded vendor: Westinghouse Electric Company. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: Wikipedia: Malmstrom Air Force Base (article coordinates), Article coordinate 47.50472, -111.18722 on 'Malmstrom Air Force Base', read 30 October 2026

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Fuel
  • Fuel form stated for eVinciUCO TRISO
No project-specific fuel supply arrangement is recorded as a structured fact.

The 23 April 2026 Westinghouse release and the 24 April 2026 World Nuclear News report name no fuel supplier, fabrication or delivery for the Malmstrom unit. The release's eight-plus years without refuelling is an eVinci design claim, not a fuel commitment for this base. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments

Site host or owner
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
Customer or offtaker

The 23 April 2026 Westinghouse release and the 24 April 2026 World Nuclear News report name no buyer, quantity or power purchase agreement for the Malmstrom eVinci. They describe a contractor-owned and operated microreactor on an Air Force installation and energy for mission-critical operations, but the Air Force is named as host and program sponsor, not as a contracted buyer. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments

Contractor

The 23 April 2026 Westinghouse release and the 24 April 2026 World Nuclear News report name no engineering or construction contractor for the Malmstrom eVinci. The release says Westinghouse Government Services, the vendor's government arm, holds the ANPI contract with the Air Force and the Defense Innovation Unit, and that Westinghouse and unnamed deployment partners will evaluate siting and construction. That is the vendor's own program selection, not a construction award. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments

Funding and government decisions

The 23 April 2026 Westinghouse release calls the Malmstrom proposal the next step in an ongoing contract with the Air Force and the Defense Innovation Unit but states no value or payment, and the 24 April 2026 World Nuclear News report states no Malmstrom amount. A contractor-owned program model does not say who finances this unit. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments

Comparable schedule revision

Comparable schedule revision not established. The 24 April 2026 World Nuclear News report gives the ANPI program aim of at least one reactor operating on an Air Force installation by 2030 or sooner, and the 23 April 2026 Westinghouse release gives no Malmstrom date. The program aim is stated once and is not a date for this unit, so no schedule revision is shown. WNN: US Air Force announces selections for microreactor deployments; Westinghouse eVinci microreactor selected for Malmstrom Air Force Base

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Operator or intended licensed owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Assessments of the design (not of this site)

(1)
  • CNSC vendor design review, Phase 2 (eVinci) — applies to the design, not to a site
    Design assessment · On hold · CNSC
    CNSC's table of current vendor design review agreements lists Westinghouse's eVinci (about 5 MWe) for Phase 2, with the review starting in June 2023 and its status on hold; Phase 1 objectives are addressed within the Phase 2 scope. The Canadian status does not describe eVinci's separate US test and deployment paths. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews

    Status confirmed on against CNSC: vendor design review service agreements and completed reviews. This confirms the recorded status only; the general record check date remains separate.

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes, 1 not yet reviewed)
  • Evidence review. Westinghouse's release of 23 April 2026 says the eVinci microreactor has been proposed for Malmstrom Air Force Base by the Department of the Air Force with the Defense Innovation Unit under the ANPI program, as the next step in Westinghouse Government Services' contract for a contractor-owned and operated microreactor on an Air Force installation. Under that agreement Westinghouse and its deployment partners will evaluate siting and construction of an eVinci at Malmstrom. World Nuclear News (24 April 2026) reports that the Air Force named Buckley and Malmstrom as the first two ANPI sites earlier that month and paired Westinghouse Government Services with Malmstrom. Neither source gives a location on the base, a unit count or a plant output; the release's 5 MW electric is the eVinci design rating. The next documentary step is the siting evaluation and environmental review for the base, then a licensing filing. The stored eVinci design, Westinghouse as vendor, the Air Force as site host and the siting stage stay; output stays unknown. Last checked 19 Oct 2026. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments
    What would change this

    An Air Force NEPA notice or environmental assessment for the Malmstrom microreactor, or a Westinghouse licensing filing, giving the location on the base and the unit count. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed. WNN reports that the Air Force chose Malmstrom Air Force Base in Montana as one of the first two ANPI sites, and Westinghouse says the eVinci has been proposed for the base. No location on the base or coordinate is published, so the map shows a base-area point, as for other named installations. Last checked 19 Oct 2026. WNN: US Air Force announces selections for microreactor deployments; Westinghouse eVinci microreactor selected for Malmstrom Air Force Base
    What would change this

    An Air Force environmental assessment or siting document identifying the microreactor parcel on Malmstrom AFB. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Breaking Defense reported in April 2026 that the selected companies and the government must next carry out an environmental assessment, and that ANPI aims to have at least one reactor operating on an Air Force installation by 2030 or sooner. Westinghouse's release says it will evaluate siting and construction at Malmstrom. The 2030 aim is program-wide, not a Malmstrom date, and no assessment or license decision is recorded in these sources. Last checked 23 Oct 2026. Department of Air Force picks bidders for nuclear microreactors, assigns locations; WNN: US Air Force announces selections for microreactor deployments
    What would change this

    Publication of the environmental assessment for Malmstrom or an Air Force decision to proceed with deployment there. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. Westinghouse's April 2026 release says the Department of the Air Force, with the Defense Innovation Unit, selected its eVinci for Malmstrom Air Force Base under ANPI, and that under the ANPI agreement Westinghouse and partners will evaluate siting and construction there. Breaking Defense reported on 23 April 2026 that the selected companies and the government must now carry out an environmental assessment. This is a selection under a contract, not a permit; these sources name no license decision or public comment process yet. Last checked 23 Oct 2026. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; Department of Air Force picks bidders for nuclear microreactors, assigns locations
    What would change this

    A published draft environmental assessment or NEPA notice for a Malmstrom microreactor, or a license application. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Westinghouse's April 2026 release says it will evaluate siting and construction of an eVinci at Malmstrom Air Force Base, Montana, and World Nuclear News reports Malmstrom as one of the first two ANPI sites chosen. These sources name the base only; no specific plot, land-use agreement, connection to the base electrical system or water arrangement is identified, and siting is still being evaluated. Last checked 23 Oct 2026. Westinghouse eVinci microreactor selected for Malmstrom Air Force Base; WNN: US Air Force announces selections for microreactor deployments
    What would change this

    Identification of a specific Malmstrom site in an environmental assessment or a land-use agreement. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(1 of 3 sources with a publication or document date)
Latest dated listed source publication: Department of Air Force picks bidders for nuclear microreactors, assigns locations: 23 Apr 2026.Latest dated recorded event: no date recorded.2 of 3 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(3)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Westinghouse eVinci at Malmstrom Air Force Base (ANPI) — https://smrmap.com/projects/anpi-malmstrom-evinci/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Westinghouse eVinci at Malmstrom Air Force Base (ANPI)”. Record reviewed 10 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/anpi-malmstrom-evinci/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.