Projects / Canada · Licensing
NB Power ARC-100 at Point Lepreau
NB Power applied to the CNSC for a license to prepare site for one ARC-100 at Point Lepreau on 30 June 2023.
Current status
- How current
- General record check . Bounded evidence review . 7 of 11 listed sources have a publication or document date recorded here; the newest is 7 May 2024. NB Power license to prepare site application: status (under review) confirmed against CNSC NB Power ARC-100 Project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: NB Power license to prepare site application. An application under review is not a permit. All permissions and applications
- Latest development
- 30 Jun 2023 · Application submitted: Application submitted: NB Power license to prepare site application. Site preparation license application for ARC-100. Source: CNSC NB Power ARC-100 Project. Updates entry
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 3 tracked: 1 licensing, 2 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Sodium-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The CNSC project page lists the application as awaiting additional submissions from NB Power, installed capacity as TBD, and no recent Commission proceedings; it does not record issuance of the license or a construction start. The same day NB Power registered the project for a provincial environmental impact assessment with New Brunswick's Department of Environment and Local Government. In December 2022 the federal environment minister decided the project does not warrant designation for a federal impact assessment. Project sources give the output as at least 100 MWe or 100 to 150 MWe without a net or gross basis; the CNSC lists installed capacity as TBD.
Key facts
- Design
- ARC-100 (SMR)
- Technology
- Sodium-cooled fast reactor (SFR) · sodium
- Operator(s)
- NB Power
- Vendor for linked design
- ARC Clean Technology
- Location
- Point Lepreau Nuclear Generating Station site · Canada · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Point Lepreau station, which the export also uses for its ARC-100 and SSR-W entries (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker). Station-area point: the SMR parcels are separate from the CANDU unit and are not published, so this is not an exact location. - Coordinates
- 45.0686, -66.4543 · site-area point (approximate)
- Electrical capacity
- 100 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
NB Power ARC-100 at Point Lepreau is recorded at Point Lepreau Nuclear Generating Station site, New Brunswick, Canada. Operator: NB Power. Recorded vendor: ARC Clean Technology. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Moltex SSR-W at Point Lepreau.
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'point-lepreau-nuclear-power-plant-smr-1' (45.0686, -66.4543)
Recorded electrical output is 100 MWe (gross/net unspecified), scope module. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 286 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Operator or intended licensed owner
- OperatorNB Power
- Reactor supplier
- Vendor for the linked designARC Clean Technology
- Customer or offtaker
Source-backed project statement NB Power's 30 June 2023 release presents the ARC-100 at Point Lepreau as part of its own plan to phase out coal by 2030 and reach net-zero supply by 2035 for New Brunswick customers, and the CNSC lists NB Power as licensee. The output would serve NB Power's own system. No external buyer, industrial offtake or purchase agreement is named. NB Power: NB Power Submits Environmental Impact Assessment Registration and Licence to Prepare Site Application for Advanced Small Modular Reactor Project; CNSC: Status of new nuclear projects - NB Power ARC-100 at Point Lepreau
- Contractor
Source-backed project statement World Nuclear News reported on 30 June 2022 that ARC Canada signed a teaming agreement with Hatch for digital plant design in the New Brunswick deployment effort. This identifies preparatory engineering work, not a Point Lepreau construction award. The report also discusses wider industrial applications; those are not treated as site-specific contracts. ARC teams up with Hatch for New Brunswick SMR deployment
- Funding and government decisions
Source-backed project statement An April 2022 company release, reprinted by Financial Post, announced CAD 30 million in Series A financing for ARC Clean Energy Canada, with Point Lepreau deployment among its stated uses. An October 2023 company release announced a $7 million federal predevelopment award for ARC Clean Technology Canada, supporting a future fleet beginning with Point Lepreau; that release does not specify a currency code. These are company financing and predevelopment support, not a disclosed NB Power construction budget or a standalone unit financing allocation. Cash disbursement is not established. The two historical company names are retained as stated, without treating them as proved legal aliases. ARC Canada announces Series A financing; ARC announces federal predevelopment award
- Programs and agreements naming the project
- Cooperation agreement or MOU; status not establishedKHNP, ARC Clean Technology and NB Power collaboration on global ARC-100 fleet deployment (2023-2024)
Not found in the sources we checked (2): Fuel; Comparable schedule revision
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
The June 2023 Revision 0 Point Lepreau EIA registration document states that fuel would be sourced from outside Canada and describes planned transport in certified containers. This proponent plan identifies no supplier or fabricator and establishes no fuel-delivery agreement. Geography and a planned handling method do not establish procurement. ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D
- Comparable schedule revision
Nuclear Engineering International's 7 May 2024 report gives both commissioning by 2029 and commissioning by the end of 2030 for the Point Lepreau ARC-100. The dates conflict within that account; they are not treated as a documented revision between two dated forecasts. NB Power's June 2023 EIA registration, which predates that report, shows an estimated schedule with a license to operate in January 2029 and commercial operation in the early 2030s. It is an older estimate and does not settle which of the report's dates is current. A later dated NB Power or ARC statement is needed to settle the target. KHNP to collaborate with Canadian firms on SMR deployment; ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D
Not recorded in SMRMap's reviewed evidence (1): Site host or owner
- Site host or owner
Timeline
Recorded developments
- · Application submitted
Application submitted: NB Power license to prepare site application - · Regulatory step
Federal minister declines to designate the Point Lepreau SMR for a federal impact assessment
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- NB Power license to prepare site application
Site permission sought · Under review · CNSC · submitted 30 Jun 2023
Site preparation license application for ARC-100.
Sources: CNSC NB Power ARC-100 ProjectStatus confirmed on against CNSC NB Power ARC-100 Project. This confirms the recorded status only; the general record check date remains separate.
Assessments of the design (not of this site)
(1)
- CNSC vendor design review, Phase 2 (ARC-100) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Jul 2025
CNSC lists Phase 1 (executive summary dated October 2019) and Phase 2 (executive summary dated July 2025) of its pre-licensing vendor design review of ARC Clean Technology's ARC-100 among completed reviews. CNSC entered into the Phase 2 agreement with ARC on 9 March 2022; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barriers to licensing at that time and listed further design work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. NB Power's Point Lepreau site application is a separate process.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: ARC-100 Phase 2 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. The CNSC project page (modified 26 January 2026, opened 19 October 2026) says NB Power, in partnership with ARC Clean Technology Canada, proposes to deploy one ARC-100 small modular reactor at the Point Lepreau Nuclear Generating Station site in New Brunswick, and lists NB Power as licensee. NB Power's release of 30 June 2023 says it submitted a license to prepare site application to the CNSC and an environmental impact assessment registration to New Brunswick's Department of Environment and Local Government that day. The CNSC lists that application as submitted on 30 June 2023 and awaiting additional submissions from NB Power; no license to prepare site has been issued, no Commission proceeding is listed, and no license to construct has been applied for. No opened source reports any site preparation or nuclear construction at Point Lepreau for this unit. On 22 December 2022 the federal environment minister decided the project does not warrant designation under the Impact Assessment Act; that is not a project approval, and the CNSC page says the project is also undergoing a provincial environmental impact assessment. Output is not settled: the CNSC lists installed capacity as TBD, NB Power's 2023 release says the ARC-100 will generate at least 100 megawatts of electricity, and the minister's response gives 286 to 429 MWth (100 to 150 MWe); no source gives a gross or net basis. ARC's 30 June 2023 statement gives completion by the end of this decade. NB Power's June 2023 EIA registration (Figure 4.14, Estimated Project Schedule) shows a license to prepare site in September 2026, a license to construct in September 2027, a license to operate in January 2029 and commercial operation in the early 2030s. Those are June 2023 estimates, not current commitments; the CNSC page read on 19 October 2026 still lists the site application as awaiting additional submissions. The licensing stage, one unit and NB Power as intended operator (CNSC licensee) stay stored; the stored 100 MWe is the lower end of developer statements and is not confirmed by the CNSC. Last checked 19 Oct 2026. CNSC NB Power ARC-100 Project; NB Power: NB Power Submits Environmental Impact Assessment Registration and Licence to Prepare Site Application for Advanced Small Modular Reactor Project; Impact Assessment Agency of Canada: Minister's response to the designation request, Small Modular Reactor Demonstration Project; Canadian Impact Assessment Registry: Small Modular Reactor Demonstration Project (Point Lepreau), project 83998; ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D
What would change this
NB Power's additional submissions to the CNSC, a CNSC hearing notice or decision on the license to prepare site, or New Brunswick's EIA determination for the Point Lepreau ARC-100. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next regulatory step is NB Power's additional submissions on its June 2023 site-preparation license application, which the CNSC lists as awaited, followed by a CNSC decision; the provincial comprehensive environmental impact assessment runs in parallel. The sources give no hearing date. Last checked 23 Oct 2026. CNSC NB Power ARC-100 Project
What would change this
A CNSC hearing notice, a decision on the license to prepare site, or the provincial EIA decision. Next scheduled check: 21 Jan 2027.
- Permissions and public process. NB Power applied to the CNSC for a license to prepare site on 30 June 2023; the CNSC page lists it as awaiting additional submissions from NB Power, and says New Brunswick is running a comprehensive provincial environmental impact assessment. In December 2022 the federal environment minister decided not to designate the project for a federal impact assessment, citing the CNSC licensing and provincial processes, including public and Indigenous consultation. No site, construction or operating license has been issued. Last checked 23 Oct 2026. CNSC NB Power ARC-100 Project; Canadian Impact Assessment Registry: Small Modular Reactor Demonstration Project (Point Lepreau), project 83998; Impact Assessment Agency of Canada: Minister's response to the designation request, Small Modular Reactor Demonstration Project
What would change this
A CNSC hearing notice or decision on the site-preparation license, or the provincial EIA decision. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Federal and regulator records place the single demonstration unit on the existing Point Lepreau Nuclear Generating Station property along the Bay of Fundy. These records describe no transmission connection, cooling-water intake or other infrastructure arrangement. NB Power's June 2023 provincial EIA registration (Revision 0) says the unit requires 345 kV network transmission service into the existing terminal serving the generating station, with an Electrical Connection Assessment under way and a new or expanded switchyard envisioned. It describes seawater cooling, with mechanical draft towers as one design option and once-through cooling as an alternative under investigation, and says that design has not been finalized. It says the existing Hanson Stream supply has surplus capacity for fresh water. These are proposals in a registration document, not an approved design, a connection agreement or a water authorization. Last checked 23 Oct 2026. Impact Assessment Agency of Canada: Minister's response to the designation request, Small Modular Reactor Demonstration Project; CNSC NB Power ARC-100 Project; ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D
What would change this
NB Power's completed Electrical Connection Assessment, a final cooling-system selection, a New Brunswick EIA determination or CNSC license documents describing grid, cooling-water and site infrastructure. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. NB Power's June 2023 provincial EIA registration document says ARC-100 used fuel would first cool in storage positions inside the reactor vessel, then move after about two years into commercially available dry storage modules in an on-site interim facility sized for at least 60 years plus decommissioning. It states that the Nuclear Waste Management Organization is responsible for long-term management under the Nuclear Fuel Waste Act and that NB Power and ARC have been working with it on the disposal option. This is a plan under review, not an approved storage license or a disposal agreement. Last checked 23 Oct 2026. ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D
What would change this
A New Brunswick EIA determination, a CNSC license decision or an NB Power-NWMO agreement covering ARC-100 used fuel would change this answer. Next scheduled check: 23 Apr 2027.
Evidence dates
(7 of 11 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(11)
- CNSC NB Power ARC-100 Project (regulator, accessed 3 Nov 2026)
- CNSC: Status of new nuclear projects - NB Power ARC-100 at Point Lepreau (regulator, accessed 9 Oct 2026)
- NB Power: NB Power Submits Environmental Impact Assessment Registration and Licence to Prepare Site Application for Advanced Small Modular Reactor Project (company, published 30 Jun 2023, accessed 18 Oct 2026)
- Canadian Impact Assessment Registry: Small Modular Reactor Demonstration Project (Point Lepreau), project 83998 (government, accessed 18 Oct 2026)
- Impact Assessment Agency of Canada: Minister's response to the designation request, Small Modular Reactor Demonstration Project (government, dated 22 Dec 2022, accessed 18 Oct 2026)
- CNSC: Status of new nuclear projects - NB Power ARC-100 at Point Lepreau (regulator, accessed 19 Oct 2026)
- ARC teams up with Hatch for New Brunswick SMR deployment (news report, published 30 Jun 2022, accessed 21 Oct 2026)
- KHNP to collaborate with Canadian firms on SMR deployment (news report, published 7 May 2024, accessed 21 Oct 2026)
- ARC Clean Technology Advanced Small Modular Reactor - Commercial Demonstration Unit, Point Lepreau: New Brunswick Environmental Impact Assessment Registration D (company, published Jun 2023, accessed 23 Oct 2026)
- ARC Canada announces Series A financing (company, published 4 Apr 2022, accessed 26 Oct 2026)
- ARC announces federal predevelopment award (company, published 26 Oct 2023, accessed 26 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: NB Power ARC-100 at Point Lepreau — https://smrmap.com/projects/arc-100-point-lepreau/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “NB Power ARC-100 at Point Lepreau”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/arc-100-point-lepreau/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.