How a sodium-cooled fast reactor works

Natrium is a pool-type sodium-cooled fast reactor (SFR): the whole primary sodium circuit sits inside the reactor vessel.[1, p. 297] Heat leaves through a second sodium loop, which passes it to molten salt; the hot salt is stored in a tank, and that stored heat makes the steam.[1, p. 296]

This page explains the type on one documented design, simplified; other designs of the type can differ. It describes the design, not a project: see the Natrium record. SMRMap tracks 2 projects using it, and each project's record carries its status.

Natrium sodium-cooled fast reactor, simplified side section with numbered partsOn the left, a wide reactor vessel inside a guard vessel holds the core low down, with control rods from above, an upper structure, one heat exchanger and one pump. Solid arrows run from the pump along the bottom into the space under the core, up through the core into the upper part of the vessel, across and down through the heat exchanger, and back into the pump, with the up-and-down sense following the drawn layering of the pools. A second line carries heat out through the head to a sodium-salt heat exchanger on the right. A third line runs down from there to a hot salt tank and a steam facility. Dashed lines come back and are not described in the section's text.123456789Hot poolCold poolCore inlet plenumSteam out
Simplified from the IAEA SMR Technology Catalogue 2026, Natrium section (printed pages 295–300). Parts and proportions not stated in the source are schematic. The figure shows one intermediate heat exchanger and one pump; the section's text speaks of both in the plural but gives no count. The numbers of rods, tubes and assemblies are schematic, and hexagonal assemblies are drawn as plain rods. The vessel's height and diameter are the catalog's; the guard vessel, the deck between the pools and everything on the right are not to scale. Numbers match the sections below; arrows show the coolant path.
  • Primary sodium, in the order the section's text gives
  • Intermediate sodium carrying heat out, as the section's text gives
  • Intermediate sodium coming back, not described in the section's text: drawn only to close the loop
  • Salt moving heat to the tank and on to make steam, as the section's text gives
  • Salt coming back, not described in the section's text: drawn only to close the loop
  • Steam going on to make electricity or heat

The parts, numbered as in the figure

1. Reactor vessel

The catalog's table gives the vessel as 20.4 m high and 11.6 m in diameter, weighing 2450 metric tons.[1, p. 295] It is part of a reactor enclosure system that also includes the head, the internal structures and a guard vessel, drawn here as the outer shell.[1, p. 297] The boundary that holds the primary sodium has no openings below the reactor head, and the section describes a low-pressure system with no pressurizer.[1, p. 297]

2. Core

"Fast" here describes the neutrons, not the sodium: the section calls this a fast neutron spectrum reactor, and says that is why it uses high assay low enriched uranium.[1, p. 296] The fuel is uranium metal, enriched up to 19.75%.[1, p. 296] The core is made of removable assemblies: fuel, control, reflectors, shields and others.[1, p. 296]

3. Control rods and drive mechanisms

Drive mechanisms on top of the reactor head move long drivelines that carry the control absorber bundles, the neutron-absorbing parts, inside the core.[1, p. 297] There are two types of absorber bundle, and the section says the rods also insert by gravity.[1, p. 297]

4. Upper internal structure

Sodium leaving the core mixes in the hot pool, then flows past this structure.[1, p. 297] The section gives it no size or shape, so it is a plain sleeve here.[1, pp. 295–300]

5. Intermediate heat exchanger

These exchangers sit in the reactor pool.[1, p. 296] Primary sodium flows through and passes its heat to the separate intermediate sodium, so that second loop carries the heat out of the vessel.[1, pp. 296, 297]

6. Primary sodium pump

These pumps drive the primary sodium around its closed path during normal operation.[1, p. 297] When the pumps are not running, the section says natural circulation between the hot and cold pools moves it instead.[1, p. 297]

7. Sodium-salt heat exchanger

The intermediate sodium loop brings the heat here and hands it to the salt transport system.[1, p. 296]

8. Hot salt storage tank

The salt moves heat into this tank for storage, outside the reactor vessel, in the part of the plant the section calls the Energy Island.[1, pp. 296, 299] The section says this lets the plant vary its output to the grid, up to 500 MW(e) net, while reactor power stays constant.[1, p. 296] The section names the hot salt storage tank and refers to storage tanks in the plural; only the hot tank is drawn here, and the salt's way back is not described.[1, pp. 296, 299]

9. Steam Generation Facility

Heat from the hot salt tank makes steam here, for electricity or industrial heat.[1, p. 296] It sits in the Energy Island with the turbine facility, apart from the Nuclear Island that holds the reactor building.[1, p. 299]

The coolant path

  1. The pumps send cooled sodium into the core inlet plenum, the space feeding the core.[1, p. 297]
  2. It passes through the core and mixes in the hot pool, then flows past the upper internal structure.[1, p. 297]
  3. It flows into the intermediate heat exchangers and gives up heat to the intermediate sodium.[1, p. 297]
  4. Cooled, it leaves those exchangers and enters the pumps again, all without leaving the vessel.[1, p. 297]
  5. The section names a hot pool and a cold pool but does not say where they sit. The figure puts the hot pool above a deck and the cold pool below it, which is why the sodium is drawn flowing down through the heat exchanger and down the pump; that layering is drawn, not quoted.[1, pp. 295–300]
  6. The intermediate sodium carries the heat to sodium-salt heat exchangers, salt moves it to the hot salt storage tank, and heat from that tank makes steam.[1, p. 296]
  7. The section's text does not describe how the intermediate sodium or the salt comes back, so the dashed lines only close those loops.[1, pp. 295–300]
  8. The catalog's picture of the vessel shows tall parts hanging from the head and horizontal decks but labels none of them, so where each part sits inside the vessel is schematic.[1, p. 295]

Is the molten salt the coolant?

No. In this design sodium cools the core, and the molten salt is a separate heat storage system outside the reactor.[1, p. 295] This is Natrium. Other sodium-cooled reactors can differ, and the interactive view shows Natrium only.

  • Sodium. Primary sodium flows through the core and stays inside the vessel; intermediate sodium takes the heat out.[1, pp. 296, 297]
  • Salt. It takes heat from the intermediate sodium and carries it to the hot salt storage tank, in the Energy Island.[1, pp. 296, 299]
  • Pressurizer. The section says this is a low-pressure system with no pressurizer.[1, p. 297]

Design values

These are values listed in the catalog section, which the developer supplied.[1, p. 295]

  • Power. 840 MW(t) of heat and 345 MW(e) of electricity.[1, p. 295]
  • Stored heat. Drawing on the salt store, the section says the plant can raise its output to the grid to 500 MW(e) net for a limited time, stated as up to 5.5 hours in its introduction and as more than five and a half hours later on, while reactor power stays constant.[1, pp. 295, 296]
  • Coolant temperature. The table lists one value, 540 °C, under core inlet and outlet temperature, and does not say which end it is.[1, p. 295]
  • Pressure. The table says low pressure, atmospheric, and gives no number.[1, p. 295]
  • Fuel. Enrichment up to 19.75%; the table gives no assembly count, and the text says a one-third reload of the first fuel is 54 assemblies.[1, pp. 295, 296, 299]
  • Refueling. The table lists 18 to 24 months; the text describes 12-month cycles at first and 24-month cycles with later fuel.[1, pp. 295, 299]

Designs on SMRMap recorded as this type

12 designs, with 12 tracked projects between them. Each design's type comes from its own record on SMRMap; the example above is one of them, and the others can differ from it.

DesignClassElectrical output Tracked projects
4SSMR—1
ARC-100SMR100 MWe (net) · module3
AuroraMicroreactor—4
HEXANASMR—1
NatriumSMR345 MWe (gross/net unspecified) · module2
Otrera 2x300SMR—None tracked here
OTRERA 300SMR—None tracked here
OTRERA ONEThe IAEA's 2026 catalog section for OTRERA 300, supplied by its contributor, gives reactor type SFR in a table that also carries OTRERA ONE's 200 MW(t) rating, and describes OTRERA ONE as the industrial precursor configuration of the same sodium fast reactor design, sharing its core and MOX fuel.SMR—None tracked here
PGSFR (Prototype Gen-IV Sodium-cooled Fast Reactor)SMR150 MWe (gross/net unspecified) · moduleNone tracked here
PRISMSMR—1
RAPIDMicroreactor1 MWe (gross/net unspecified) · moduleNone tracked here
SALUS-100SMR100 MWe (gross/net unspecified) · moduleNone tracked here

Sources

  1. Small Modular Reactor Technology Catalogue, 2026 edition (contributor material; printed September 2026) — IAEA ARIS (catalog host; profiles supplied by contributors). Natrium section, printed pages 295–300. Each section is contributor material; the Natrium section was supplied by TerraPower.