Canada SMR projects

11 tracked projects and proposals in this directory. Named proposals, demonstrations and achieved deployments retain their recorded stages.

Announced: 4 · Siting: 3 · Licensing: 1 · Construction: 1 · Suspended: 1 · Canceled: 1

Open these projects in Projects (on the map) · Coverage and stage definitions

Counts describe the selected dataset, not a complete national or worldwide census. Sources and check dates are linked from each record.

Country brief

Recorded answers for these 11 projects — customer or offtaker: 1 of 11; contractor: 1 of 11; funding and government decisions: 1 of 11; fuel supplier named for this project: 1 of 11; programs and agreements naming the project: 3 of 11. Who is involved, project by project.

Latest recorded developments

Newest first: steps of these projects, the latest step of each of this country's policy measures, and agreements or programs that concern it.

Next documented targets

Targets are plans, not achievements or commitments.

Documented schedule changes

Projects

Showing 11 of 11 projects

Project and categoryStageDesignCapacityRecorded organizationsLocationRecord reviewed
ARC-100 proposal at the Port of Belledune Green Energy HubSMRAnnouncedARC-100—Port of Belledune Green Energy HubNew Brunswick · site-area point (approximate)2 Oct 2026Latest source: none datedLatest event: none dated
Belledune Prodigy transportable nuclear proposalMicroreactorAnnouncedBWXT BANR—BelleduneNew Brunswick · town named, no map pin13 Oct 2026Latest source 5 Oct 2026Latest event 5 Oct 2026
Darlington BWRX-300 Unit 1SMRConstructionBWRX-300300 MWe (net) · module · 870 MWth (nameplate; basis unspecified)Darlington New Nuclear Project siteOntario · site-area point (approximate)18 Oct 2026Latest source 11 Nov 2026Latest event 10 Nov 2026
Darlington BWRX-300 Units 2-4SMRSitingBWRX-300—Darlington New Nuclear Project siteOntario · site-area point (approximate)2 Oct 2026Latest source, document dated 12 Mar 2026Latest event: none dated
Global First Power Chalk River MMR (paused)MicroreactorSuspendedGlobal First Power Micro Modular Reactor—Chalk River Laboratories site, Renfrew CountyOntario · site-area point (approximate)19 Oct 2026Latest source 14 Nov 2023Latest event: none dated
Moltex SSR-W at Point LepreauSMRAnnouncedSSR-W—Point Lepreau Nuclear Generating Station siteNew Brunswick · site-area point (approximate)2 Oct 2026Latest source: none datedLatest event: none dated
NB Power ARC-100 at Point LepreauSMRLicensingARC-100100 MWe (gross/net unspecified) · modulePoint Lepreau Nuclear Generating Station siteNew Brunswick · site-area point (approximate)18 Oct 2026Latest source 7 May 2024Latest event 22 Dec 2022
SaskPower Rafferty SMR (Estevan area)SMRSitingBWRX-300600 MWe (net) · plantRafferty site near EstevanSaskatchewan · town-level point (approximate)1 Oct 2026Latest source: none datedLatest event: none dated
SRC initial eVinci demonstration proposal (canceled)MicroreactorCanceledeVinci≈ 5 MWe (derived)Saskatchewanregion only, no map pin14 Oct 2026Latest source 15 Apr 2026Latest event: none dated
StarCore demonstration reactor at the Whiteshell Laboratories site, PinawaSMRAnnouncedDesign profile not linked—Whiteshell Laboratories site, PinawaManitoba · site-area point (approximate)13 Oct 2026Latest source: none datedLatest event: none dated
U-Battery first-of-a-kind siting bid at Chalk River (2019-2023)MicroreactorSitingU-Battery—Chalk River Laboratories campus (U-Battery siting bid)Ontario · site-area point (approximate)3 Oct 2026Latest source: none datedLatest event: none dated

Research coverage for the 11 matching projects: of 99 answers to nine review questions, 44 have a supported statement, 52 were reviewed with a stated limit and 3 are not reviewed yet. This counts recorded research, not readiness or the likelihood of construction.

Coverage by question

Each project is asked the same nine questions: five commercial questions and four reader questions. Only completed source reviews are counted. A supported statement can describe a conditional plan or preparatory work; read it on the project page. Not disclosed, not applicable, conflicting evidence and source unavailable are reviewed limits. Not reviewed is unfinished research, not a finding that nothing exists. The counts cover every page of matching projects, not only the page shown or the projects chosen for comparison.

QuestionSupported statementNot disclosedNot applicableConflicting evidenceSource unavailableNot reviewedProjects
Customer or offtaker38000011
Contractor38000011
Funding47000011
Project fuel commitment110000011
Comparable schedule revision17030011
Permissions and public process74000011
Site dependencies (land, grid, water)101000011
Spent fuel, waste and closure61100311
Next decision and prerequisites91100011
All nine questions4447230399

Agreements

(16)

Agreements, plans, studies and government programs that concern this country. They are not deployment projects and are not counted as projects or reactors.

Recorded project permissions and applications

These documents concern the linked projects only. A country-wide approval is not inferred; design assessments, site permissions, construction permissions and operating authority remain separate.

Site applications and decisions

Construction applications and decisions

Operating-license applications and decisions

Designs developed here (12)

Designs whose developer organization is based in this country. A design developed here is not a deployment here.

Organizations here (24)

The first 12 of 24, alphabetically. All 24 organizations in the directory.

Cite or share this page

SMRMap. “Canada SMR projects”. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/countries/ca/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.