Projects / United States · Siting
Cascade Advanced Energy Facility
Energy Northwest / X-energy Xe-100 project on the DOE Hanford Site adjacent to Columbia Generating Station, named Cascade.
Current status
- How current
- General record check . Bounded evidence review . 4 of 7 listed sources have a publication or document date recorded here; the newest is 5 Nov 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 5 Nov 2026 · Announcement: X-energy selects Fluor for Cascade nuclear-island engineering. X-energy said Fluor will provide design and engineering services for the plant areas containing the Xe-100 reactors. Source: X-energy: Fluor selected for Cascade nuclear-island engineering and design (published 5 Nov 2026). Updates entry
More on this development
An engineering and design contract between X-energy and Fluor, not a construction contract or an NRC application.
- Next dated milestone
- Planned commercial operation: 2030s. The target text has no usable date; no dated milestone or achievement is inferred.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 1 licensing, 1 siting, 2 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Energy Northwest New Nuclear, LLC, a wholly owned Energy Northwest subsidiary, intends to construct and operate up to 12 modules, starting with four (about 320 MWe), with possible expansion to about 960 MWe. Amazon is funding the initial feasibility phase and has the right to buy electricity from the first four modules. Energy Northwest is negotiating with Cascade Nuclear Partners, a Kiewit, Black & Veatch and Aecon joint venture, for progressive design-build of the first four modules; that is not a signed construction contract. The NRC lists only pre-application activity (since August 2024) for a future construction permit application, planned in two parts with dates withheld, so the stage is siting, not licensing. X-energy said on 5 November 2026 that it selected Fluor for engineering and design of Cascade's nuclear island under a contract between the two companies, and described Cascade Nuclear Partners as Energy Northwest's progressive design-builder for the conventional island; that wording does not establish an executed design-build contract.
Key facts
- Design
- Xe-100 (SMR)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Energy Northwest New Nuclear, LLC
- Vendor for linked design
- X-energy
- Location
- Hanford Reservation Cascade / Columbia GS area · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Cascade Xe-100 entry next to Columbia Generating Station on the Hanford Site (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plant centroid. - Coordinates
- 46.4569, -119.3287 · site-area point (approximate)
- Electrical capacity
- 320 MWe (net) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Cascade Advanced Energy Facility is recorded at Hanford Reservation Cascade / Columbia GS area, Washington, United States. Operator: Energy Northwest New Nuclear, LLC. Recorded vendor: X-energy. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'cascade-smr-nuclear-power-plant-1' (46.4569, -119.3287)
Recorded electrical output is 320 MWe (net), scope plant. Modules planned: 4. Thermal output is not recorded on this project. The linked design record states 200 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 80 MWe (net); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Parent companyEnergy Northwest · source
- Application filing entityEnergy Northwest New Nuclear, LLC · source
- Operator or intended licensed owner
- Reactor supplier
- Vendor for the linked designX-energy
- Customer or offtaker
Source-backed project statement
Energy Northwest's 16 October 2024 release says Amazon will have the right to purchase electricity from the first four-module project, expected to be about 320 megawatts, with further output available to Amazon and other Northwest utilities. That is a purchase right, not a binding power-sales contract. The 26 March 2026 regulatory plan says the plant would serve subscribers and names no other customer. Energy Northwest: Amazon, Energy Northwest announce plans to develop advanced nuclear technology in Washington; NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
- Contractor
- Planned construction contractorCascade Nuclear Partners · sourceNegotiations for progressive design-build of the first four of twelve Xe-100 units. The development phase precedes full execution; no executed construction contract is established.
Source-backed project statement
Energy Northwest's 23 October 2025 release says it is negotiating with Cascade Nuclear Partners, a joint venture of Kiewit, Black & Veatch and Aecon, to plan, design and construct the first four Xe-100 modules under a progressive design-build model. The development phase is to define scope, schedule and cost before full execution. No construction contract is stated. Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility
- Funding and government decisions
- Funder or lender named for this projectAmazon · sourceAgreement funds the initial feasibility phase near Richland. No amount or disbursement is stated. This does not establish full construction financing.
Source-backed project statement
Energy Northwest's 16 October 2024 release says Amazon will fund the initial feasibility phase, with no amount or payment stated. The 26 March 2026 regulatory plan says the company is exploring financing and that the Department of Energy loan office approved Part I of Energy Northwest's loan application, which only allows a Part II application to be prepared. That is not a loan or construction funding. Energy Northwest: Amazon, Energy Northwest announce plans to develop advanced nuclear technology in Washington; NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
- Fuel
- Fuel form stated for Xe-100Graphite pebbles with TRISO particle fuel
Energy Northwest's 2024 Amazon agreement release and its 2025 design-builder release describe X-energy as a developer of reactor and fuel technology and the Xe-100 as a high-temperature gas-cooled design. They name no fuel supplier, fabrication contract or delivery for the Cascade modules. Energy Northwest: Amazon, Energy Northwest announce plans to develop advanced nuclear technology in Washington; Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility
Not found in the sources we checked (1): Comparable schedule revision
- Comparable schedule revision
Comparable schedule revision not established. Energy Northwest's 2025 Cascade naming release and its design-builder release both say construction is anticipated to begin by the end of the decade, with operations targeted for the 2030s. The same target repeated is not a revision, and the releases read give no earlier or later date for either milestone. Energy Northwest Cascade naming release; Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility
Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
X-energy selects Fluor for Cascade nuclear-island engineering - Filed · Regulatory step
Cascade licensing plan updated with a two-part permit application - Announced · Announcement
Kiewit, Black & Veatch and Aecon venture chosen to negotiate Cascade design-build - Announced · Announcement
Amazon to fund Cascade feasibility work, with rights to first-phase power - Began · Regulatory step
NRC pre-application engagement begins for Cascade
Dates on the project record: Planned commercial operation: 2030s.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(2)
- Xe-100 UK Generic Design Assessment (requested) — applies to the design, not to a site
Design assessment sought · Application received · ONR/EA (UK)
On 15 September 2026 ONR said the Department for Energy Security and Net Zero had asked it, the Environment Agency and Natural Resources Wales to begin a three-step Generic Design Assessment of X-energy UK Holdings Ltd's Xe-100 after a readiness review. The assessment begins once timescale and resource arrangements are in place, so no step is recorded as started. ONR's page, updated 28 September 2026 and re-read on 28 October 2026, still says so.
Sources: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026)Could not be confirmed on . Attempted official source: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026). This is an access or status observation only; the record review date is unchanged.
- CNSC vendor design review, Phases 1 and 2 (Xe-100) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Dec 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: X-energy Xe-100 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. Energy Northwest New Nuclear, LLC (ENNN), a wholly owned Energy Northwest subsidiary, states its intention to construct and operate up to 12 Xe-100 modules on DOE's Hanford Site next to Columbia Generating Station in Benton County, Washington. Energy Northwest's 2024 agreement announcement separately identifies a first four-module project expected to provide 320 MW and possible expansion by up to eight further modules; the buildout ceiling is not an adopted first-phase total. Amazon would fund the initial feasibility phase and has a right to purchase electricity from the first four modules, rather than a report that power is being delivered or the whole plant financed. Energy Northwest's 2025 design-builder release describes negotiations with Cascade Nuclear Partners, a Kiewit/Black & Veatch/Aecon joint venture, not a completed construction contract. NRC records pre-application activities for a future Part 50 construction-permit application; ENNN's engagement plan lists that application in two parts without public dates. The permit application and later permissions remain future steps, so siting stays. Existing recorded operator, first-phase scale and participant distinctions remain; no broad review date is advanced. Last checked 19 Oct 2026. NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3; Energy Northwest: Amazon, Energy Northwest announce plans to develop advanced nuclear technology in Washington; Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility; NRC pre-application activities: Energy Northwest New Nuclear
What would change this
NRC acceptance of ENNN's Cascade construction-permit application, or an executed design-build contract or amendment to the first-phase Amazon agreement. Next scheduled check: 19 Jan 2027.
- Operator or intended licensed owner. Energy Northwest New Nuclear, LLC, a wholly owned subsidiary of Energy Northwest, states in its NRC-docketed engagement plan that it intends to construct and operate up to 12 Xe-100 modules. Last checked 18 Oct 2026. NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
Construction permit application names a different applicant or operator. Next scheduled check: 18 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. No construction permit application has been filed. The NRC page, updated 23 September 2026, lists pre-application activity only, and the March 2026 engagement plan withholds the planned filing dates. Last checked 18 Oct 2026. NRC pre-application activities: Energy Northwest New Nuclear; NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
NRC dockets Part 1 of the Cascade construction permit application. Next scheduled check: 18 Jan 2027.
- Operation or grid target (type stated). Energy Northwest anticipates construction by the end of the decade with operations targeted for the 2030s. No more precise public date was found. Last checked 18 Oct 2026. Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility
What would change this
Energy Northwest or the NRC publishes a dated schedule. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The 26 March 2026 plan still lists submission of the construction permit application, a revised Department of Energy lease, and a Washington site-certification agreement as steps ahead. The dates for the two application parts are withheld in the public copy. These are planned steps, not approvals already given. Last checked 23 Oct 2026. NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
A submitted construction permit application or a revised Hanford lease for Cascade. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The NRC pre-application page says engagement with Energy Northwest on a future construction permit application for this project has run from August 2024 to the present. The 26 March 2026 plan says the construction permit application is still to be submitted and that a Washington site-certification agreement is still to be obtained. Neither document is a permit. Last checked 23 Oct 2026. NRC pre-application Energy Northwest Cascade; NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
The docketed construction permit application, or an issued site-certification agreement. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The 26 March 2026 plan says Energy Northwest leases the Hanford site from the Department of Energy field office, that the lease expires on 30 June 2032 with an option toward 1 January 2052, and that the project company subleases a portion. The lease authorizes remediation and limited reuse. A lease amendment is still required before construction. The site is about two miles west of the Columbia River. No water right or grid interconnection is stated. This covers land tenure only. Last checked 23 Oct 2026. NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
A lease amendment authorizing construction, or a stated water or grid agreement. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The 26 March 2026 plan says the Xe-100 would use X-energy TRISO-X fuel and that fuel would be received on site after an operating license. It also lists a future topic for describing decommissioning plans. It states no spent-fuel storage, transport or closure arrangement. Last checked 23 Oct 2026. NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3
What would change this
A spent-fuel, waste or decommissioning plan for Cascade. Next scheduled check: 21 Jan 2027.
Evidence dates
(4 of 7 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(7)
- Energy Northwest Cascade naming release (company, accessed 18 Oct 2026)
- NRC pre-application Energy Northwest Cascade (regulator, accessed 1 Oct 2026)
- NRC pre-application activities: Energy Northwest New Nuclear (regulator, accessed 18 Oct 2026)
- NRC ADAMS ML26085A601: Energy Northwest New Nuclear Regulatory Engagement Plan, Revision 3 (regulator, dated 26 Mar 2026, accessed 18 Oct 2026)
- Energy Northwest: Amazon, Energy Northwest announce plans to develop advanced nuclear technology in Washington (company, published 16 Oct 2024, accessed 18 Oct 2026)
- Energy Northwest: Energy Northwest selects design builder for Cascade Advanced Energy Facility (company, published 23 Oct 2025, accessed 18 Oct 2026)
- X-energy: Fluor selected for Cascade nuclear-island engineering and design (company, published 5 Nov 2026, accessed 11 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Cascade Advanced Energy Facility — https://smrmap.com/projects/cascade-advanced-energy-facility/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Cascade Advanced Energy Facility”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/cascade-advanced-energy-facility/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.