Projects / United States · Siting
Deep Fission Gravity pilot, Parsons
Gravity pilot proposed at the Justin Freeman Energy Center in Great Plains Industrial Park, Parsons.
Current status
- How current
- General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: 17 Jul 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 6 Aug 2026 · Regulatory step: Deep Fission announces DOE approval of its Gravity pilot NSDA. Deep Fission announced approval of the NSDA for its Gravity pilot at Parsons. Source: deepfission.com: DOE approves Nuclear Safety Design Agreement for the Gravity reactor (Reactor Pilot Program); Deep Fission: public Gravity pilot Nuclear Safety Design Agreement, Revision 0 (dated 17 Jul 2026). Updates entry
More on this development
The agreement defines an early safety framework and separate later readiness, startup and operating steps. The announcement is not an NRC license or evidence of operating authority.
- Next dated milestone
- Planned step: 2027 (target). Deep Fission Parsons DOE pilot targeted. This is not an achieved milestone. Source: Deep Fission Parsons project page.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The company reports a 6,000-foot data well and a non-nuclear prototype canister, targeting a DOE pilot in 2027 and commercial scale-up in 2027–28. Its public NSDA Revision 0, issued 17 July 2026, plans initial zero-power criticality followed by power demonstration up to 19.5 MWt. This is a pilot design bound, not achieved output. The generic FAQ's up-to-15-MWe commercial target does not establish this pilot's fixed electrical rating. The NSDA's cover attributes approval to a 14 July DOE letter that was not opened. Later safety, readiness, startup and operating decisions remain distinct. These sources establish neither achieved criticality nor operating authority.
Key facts
- Design
- Gravity (SMR)
- Technology
- Pressurized water reactor (PWR) · light water
- Operator(s)
- Deep Fission
- Vendor for linked design
- Deep Fission
- Location
- Great Plains Industrial Park, Parsons · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Point from the Wikipedia article for the former Kansas Army Ammunition Plant; the Parsons article says the Great Plains Industrial Park that Deep Fission names was built on that plant's site. Industrial-park area point, not the borehole position. - Coordinates
- 37.28528, -95.17889 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Deep Fission Gravity pilot, Parsons is recorded at Great Plains Industrial Park, Parsons, Kansas, United States. Operator: Deep Fission. Recorded vendor: Deep Fission. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Wikipedia: Kansas Army Ammunition Plant (article coordinates), Article coordinate 37.28528, -95.17889 on 'Kansas Army Ammunition Plant', read 30 October 2026
Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorDeep Fission
- Reactor supplier
- Vendor for the linked designDeep Fission
- Fuel
- Fuel form stated for Gravityconventional LEU PWR fuel
- Enrichment stated for GravityLEU
Deep Fission's FAQ says it will use low-enriched uranium from qualified suppliers, and the public safety design agreement describes conventional low-enriched PWR fuel assemblies. These are design-fuel statements. No supplier, allocation, fabrication order or delivery is named for the Parsons pilot. The site page anticipates interim storage of used fuel pending a national solution. Deep Fission Gravity reactor FAQ; Deep Fission: public Gravity pilot Nuclear Safety Design Agreement, Revision 0; Deep Fission Parsons project page
- Programs and agreements naming the project
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
Deep Fission's Parsons site page and FAQ name no electricity or heat recipient for the Justin Freeman Energy Center pilot. The site page notes that Kansas law requires commercial power to be sold to a regulated utility, and the FAQ lists possible future users in general terms. Neither is an offtake agreement or a named customer. Deep Fission Parsons project page; Deep Fission Gravity reactor FAQ
- Contractor
The Parsons site page credits the Deep Fission team with fabricating and delivering the first prototype canister, and the public safety design agreement says Deep Fission's engineering group and unnamed subcontractors design and implement the plant. No engineering, drilling, licensing or construction contractor is named for the Parsons pilot. Deep Fission Parsons project page; Deep Fission: public Gravity pilot Nuclear Safety Design Agreement, Revision 0; Deep Fission Gravity reactor FAQ
- Funding and government decisions
The Parsons site page says Deep Fission was one of ten companies selected for the US Department of Energy Reactor Pilot Program and that the demonstration is subject to DOE authorization. Selection is program participation, not a stated grant, loan, cost share or amount. The opened pages give no project capital figure or financing instrument for the pilot. Deep Fission Parsons project page
- Comparable schedule revision
Comparable schedule revision not established. The undated Parsons site page targets Phase 1 for 2026–2027, the DOE pilot for 2027 and commercial operation for 2027–2028. Each phase target is stated once, so no comparable earlier and later target for the same milestone is recorded. The December 2025 groundbreaking ceremony is an achieved event, not a target change. Deep Fission Parsons project page; Deep Fission: public Gravity pilot Nuclear Safety Design Agreement, Revision 0
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
Timeline
Recorded developments
- Announced · Regulatory step
Deep Fission announces DOE approval of its Gravity pilot NSDA - · Groundbreaking
Groundbreaking for the Gravity pilot at Great Plains Industrial Park, Parsons
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Deep Fission Parsons DOE pilot targeted
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. Deep Fission identifies its Gravity pilot at the Great Plains Industrial Park in Parsons, Kansas, as the Justin Freeman Energy Center. Its site page explicitly says the company plans to construct and operate the pilot under DOE authorization; this identifies an intended operator, not an operating authorization already granted. The reported data well and factory-built prototype canister are preparation and non-nuclear demonstration steps. The company's public NSDA Revision 0 and FAQ describe a planned zero-power criticality phase followed by power demonstrations up to 19.5 MWt; this is a pilot limit, not achieved output or a commercial electrical rating. The NSDA cover refers to a separate DOE approval letter that was not opened. The site's published next steps are obtaining DOE authorization to construct and operate the pilot and applying to NRC for commercial operation, with the DOE pilot targeted for 2027. These statements do not establish that either authority has been granted or that criticality occurred. The named industrial park is recorded as a site area; siting remains and no broad review date changes. Last checked 19 Oct 2026. Deep Fission Parsons project page; Deep Fission Gravity reactor FAQ
What would change this
An opened DOE approval/readiness or operating-authorization decision for the Parsons pilot, or an NRC commercial-license application; a construction or criticality report must name the actual milestone. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. The company names Great Plains Industrial Park in Parsons and its Justin Freeman Energy Center pilot. A named site is supported; neither an exact reactor point nor a surveyed boundary is published in the opened page. Last checked 19 Oct 2026. Deep Fission Parsons project page
What would change this
A published site address, boundary or reactor survey point for the Parsons pilot. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Deep Fission lists its next steps as obtaining DOE authorization to construct and operate the pilot and completing its tests, then applying to the NRC for a commercial operating license for the same reactor. Its DOE pilot phase targets 2027. These are company plans; no DOE authorization decision is recorded. Last checked 23 Oct 2026. Deep Fission Parsons project page
What would change this
A DOE authorization decision for the Parsons pilot or an NRC license application. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Deep Fission's Parsons page names DOE, the Kansas Department of Health and Environment and the Kansas Corporation Commission as oversight bodies, and says the pilot would be built and operated under DOE authorization while a separate NRC commercial operating license is sought. Its public safety design agreement cites DOE approval of that agreement, which is not authorization to build or operate. A community advisory group is participation, not consent. Last checked 23 Oct 2026. Deep Fission Parsons project page
What would change this
A DOE authorization to construct or operate the Parsons pilot, or an NRC application for it. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Deep Fission reports a long-term lease of about 100 acres in the Great Plains Industrial Park at Parsons. For power sales, its site page notes that Kansas law requires commercial generation to be sold to a regulated utility. No grid-interconnection agreement or named utility is recorded. Last checked 23 Oct 2026. Deep Fission Gravity reactor FAQ; Deep Fission Parsons project page
What would change this
A grid-interconnection request or utility agreement for the Parsons site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The Parsons page says the reactor will produce used fuel to be stored and disposed of under applicable law, and that Deep Fission's deployment model anticipates interim storage pending a national long-term solution, possibly with on-site storage and transport. This is a stated approach, not a storage license or disposal contract. Last checked 23 Oct 2026. Deep Fission Parsons project page
What would change this
A DOE or NRC filing describing used-fuel storage for the Parsons pilot. Next scheduled check: 21 Jan 2027.
Evidence dates
(1 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- Deep Fission Parsons project page (company, accessed 13 Oct 2026)
- Deep Fission Gravity reactor FAQ (company, accessed 2 Oct 2026)
- Deep Fission: public Gravity pilot Nuclear Safety Design Agreement, Revision 0 (company, dated 17 Jul 2026, accessed 17 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Deep Fission Gravity pilot, Parsons — https://smrmap.com/projects/deep-fission-parsons/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Deep Fission Gravity pilot, Parsons”. Record reviewed 13 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/deep-fission-parsons/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.