Projects / Estonia · Siting

Fermi Energia Estonian BWRX-300 plant

Fermi Energia proposes one plant with two about 300 MWe BWRX-300 units under Estonia national special spatial planning.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 2 of 7 listed sources have a publication or document date recorded here; the newest is 6 Nov 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
Planned step: 2035 (target). Fermi Energia application: first reactor could start operating in 2035 at the earliest. This is not a commitment and is not an achieved milestone. Source: Government initiated the national designated spatial plan for a nuclear power plant; Fermi Energia national special plan.
Selected limitations
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.
  • State or province is not recorded.
  • Expected for this stage but not recorded as a structured fact: Site location recorded as disclosed (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

Candidate municipalities are not separate projects or pins. Estonia initiated a national designated spatial plan in May 2025; in July 2026 the state's baseline positions shortlisted six candidate areas in Lüganuse and Viru-Nigula parishes. On 6 November 2026 the economy ministry said planning continues with three possible areas in Viru-Nigula parish (Madala, Malla and Letipea); the Lüganuse areas dropped out for national-defense reasons, and route corridors are to be presented in 2027. In May 2026 Viru-Nigula municipality signed a contract to transfer the Madala property near Kunda port to Fermi Energia if the national plan selects it. No site is final. The national planning page updated on 9 September 2026 still describes stage one, location pre-selection, with public information sessions on 6 to 21 October 2026. Fermi reported that Skepast&Puhkim and Steiger won the national planning consultancy tender to advise the ministry on site pre-selection, impact assessment and the first planning stage. This is preparatory planning work, not a construction or EPC award by Fermi. Estonia's government said in May 2025 that the first of the two reactors could, according to Fermi's application, start operating in 2035 at the earliest, assuming smooth processes, and Fermi's planning page says the first reactor would produce electricity in the second half of 2035. These are the applicant's earliest-case dates for the first reactor.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Fermi Energia
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Design origin
United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Fermi Energia Estonian plant site not yet selected · Estonia · precision: no site named
National special plan candidate areas are not a final selected site; no map pin.
Coordinates
No site named, no map pin
Electrical capacity
600 MWe (net) · scope: plant
Thermal capacity
Not recorded
Modules planned
2
Inclusion basis
SMR by design class
Confidence
high
Record reviewed
6 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Fermi Energia Estonian BWRX-300 plant is recorded at Fermi Energia Estonian plant site not yet selected, state or province not recorded, Estonia. Operator: Fermi Energia. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Siting. Location precision: no site named; no site named, no map pin.

Recorded electrical output is 600 MWe (net), scope plant. Modules planned: 2. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 300 MWe (net); the project figure is kept separate.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Contractor

Source-backed project statement Fermi reported that Skepast&Puhkim and Steiger won the national planning consultancy tender to advise the ministry on site pre-selection, impact assessment and the first planning stage. This is preparatory work for the ministry, not a construction or EPC award by Fermi. Fermi Energia national special plan; Government initiated the national designated spatial plan for a nuclear power plant; Fermi Energia: Estonian firms won the nuclear planning consultancy tender (25 March 2026)

Not found in the sources we checked (4): Customer or offtaker; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Fermi Energia national special plan; Government initiated the national designated spatial plan for a nuclear power plant; Riigiplaneering: national designated spatial plan for a nuclear power plant (page updated 9 September 2026); Fermi Energia: conditional Madala property agreement with Viru-Nigula (14 May 2026)

Funding and government decisions

The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Fermi Energia national special plan; Fermi Energia: conditional Madala property agreement with Viru-Nigula (14 May 2026); Government initiated the national designated spatial plan for a nuclear power plant

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Fermi Energia national special plan

Comparable schedule revision

Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Government initiated the national designated spatial plan for a nuclear power plant; Fermi Energia national special plan; Riigiplaneering: national designated spatial plan for a nuclear power plant (page updated 9 September 2026); Elektriala: state ready with baseline positions for the nuclear plant plan

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner
Programs and agreements naming the project

Timeline

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Planned commercial operation: 2035 (planned).

Permissions and applications

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. Fermi proposes two 300 MW reactors; this is planned capacity, not operating output. Multiple candidate locations remain. Madala is a conditional property transaction, not final site selection. The developer explicitly selected GE Hitachi BWRX-300; this does not constitute state approval. Fermi is developer/planning applicant, GE Hitachi is selected technology supplier, and Viru-Nigula is the conditional property counterparty. No operating appointment is inferred. Government Order 102 of 22 May 2025 initiates national spatial planning and strategic assessment; neither it nor the property contract grants reactor construction permission. Preliminary site selection precedes detailed planning. Madala transfer remains conditional on planning, safety assessments and permits; no final selection is established. Last checked 20 Oct 2026. Fermi Energia national special plan; Fermi Energia: conditional Madala property agreement with Viru-Nigula (14 May 2026); Government initiated the national designated spatial plan for a nuclear power plant; Riigiplaneering: national designated spatial plan for a nuclear power plant (page updated 9 September 2026)
    What would change this

    A project-specific adopted assessment program, final site/design selection or permission instrument; preserve the distinction between proposal and approval. Next scheduled check: 20 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The opened Fermi page names candidate areas in Viru-Nigula near Kunda and in Aa village in Lüganuse, and says the land requirement depends on the chosen site. It does not select a facility point. Annex titles include coordinates, but that annex was not opened and no point is stored. Last checked 19 Oct 2026. Fermi Energia national special plan
    What would change this

    The Estonian national plan selects one site, or the coordinates annex is opened and supports a facility point. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The state planning site says the process has two stages, preliminary site selection and then a detailed solution at the chosen site. The May 2025 government release says the nuclear safety legal framework, developed in parallel, is a prerequisite for the preliminary site-selection decision. It says the first of two reactors could start operating in 2035 at the earliest, according to Fermi's application. The selection date is not given in these sources, and 2035 is the applicant's earliest case. Last checked 23 Oct 2026. Government initiated the national designated spatial plan for a nuclear power plant; Riigiplaneering: national designated spatial plan for a nuclear power plant (page updated 9 September 2026)
    What would change this

    Adoption of Estonia's nuclear safety law or the government's preliminary site-selection decision. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. Estonia's government initiated a national designated spatial plan and strategic environmental assessment for the 600 MW plant in May 2025, after Fermi Energia's application; the state planning site says the economy ministry runs the process and the government adopts the plan. Elektriala reported in 2026 that the plan's starting positions and assessment program were ready, with public information meetings in Lääne- and Ida-Virumaa in August. This is a planning procedure, not a nuclear license; the sources say the nuclear safety legal framework was still being developed. Last checked 23 Oct 2026. Government initiated the national designated spatial plan for a nuclear power plant; Riigiplaneering: national designated spatial plan for a nuclear power plant (page updated 9 September 2026); Elektriala: state ready with baseline positions for the nuclear plant plan
    What would change this

    The government's preliminary site-selection decision under the national plan, or adoption of Estonia's nuclear safety law. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Elektriala's 2026 report says six candidate areas in Lüganuse and Viru-Nigula parishes are in the preliminary selection, with power connections, cooling-water routes and access roads also to be assessed; the May 2025 government release expects a 330 kV line and substation extension to be planned. In May 2026 Viru-Nigula signed a conditional agreement to transfer the Madala property near Kunda port to Fermi Energia, completing only if planning, safety assessments and permits confirm the site. No site is selected, and no grid or cooling-water arrangement is secured. Last checked 23 Oct 2026. Elektriala: state ready with baseline positions for the nuclear plant plan; Government initiated the national designated spatial plan for a nuclear power plant; Fermi Energia: conditional Madala property agreement with Viru-Nigula (14 May 2026)
    What would change this

    The preliminary site selection, or completion of the Madala transfer. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The May 2025 government release starting the national plan and Fermi Energia's planning page do not assign spent-fuel responsibility or name a storage or disposal arrangement for this plant. The release mentions a 2022-2023 national analysis of possible areas for a nuclear plant and a radioactive waste disposal site, and Fermi lists a 2021 low- and intermediate-level waste strategy among its planning studies; both are studies, not arrangements. Last checked 23 Oct 2026. Government initiated the national designated spatial plan for a nuclear power plant; Fermi Energia national special plan
    What would change this

    An Estonian waste-management decision or plan document assigning spent-fuel storage or disposal for this plant. Next scheduled check: 23 Apr 2027.

Evidence dates

(2 of 7 sources with a publication or document date)
Latest dated listed source publication: Estonian Ministry of Economic Affairs and Communications: nuclear plant planning moves forward with three locations: 6 Nov 2026.Latest dated recorded event: no date recorded.5 of 7 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(7)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Fermi Energia Estonian BWRX-300 plant — https://smrmap.com/projects/fermi-energia-estonia/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Fermi Energia Estonian BWRX-300 plant”. Record reviewed 6 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/fermi-energia-estonia/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.