Projects / United States · Canceled

Toshiba 4S proposal at Galena, Alaska (mid-2000s)

This historical proposal by the City of Galena, Alaska, for a Toshiba 4S plant (10 MW of electricity) to replace diesel power has ended.

Current status

Stage
Canceled
How current
General record check . Bounded evidence review . 1 of 2 listed sources has a publication or document date recorded here: 6 May 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Sodium-cooled fast reactor. How it works, with a 3D view.
Schematic of Natrium, this type's example. On the left, a wide reactor vessel inside a guard vessel holds the core low down, with control rods from above, an upper structure, one heat exchanger and one pump.
Schematic of Natrium, this type's example.

Description

In 2006 congressional testimony, Galena's city manager described the city's plan to license, construct and operate a Toshiba 4S plant (10 MW of electricity, built in modules) to replace diesel power. ANS Nuclear Newswire's May 2026 history of the 4S reports that, as deadlines slipped, Galena decided in 2011 to pursue a new fossil-fired power plant instead, and that NRC reviews of the design ceased two years later. That retrospective is the basis for the ended status; no city decision document or exact decision date was found. No license application or construction is established.

Key facts

Design
4S (SMR)
Technology
Sodium-cooled fast reactor (SFR) · sodium
Operator(s)
City of Galena, Alaska
Vendor for linked design
Toshiba Energy Systems & Solutions Corporation
Design origin
Japan: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Galena, Alaska · United States · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
10 MWe (gross/net unspecified) · scope: plant
Thermal capacity
Not recorded
Modules planned
1
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 23 Oct 2026. How current names both.
Site and capacity notes

Toshiba 4S proposal at Galena, Alaska (mid-2000s) is recorded at Galena, Alaska, Alaska, United States. Operator: City of Galena, Alaska. Recorded vendor: Toshiba Energy Systems & Solutions Corporation. Stage: Canceled. Location precision: town or locality only; town named, no map pin.

Recorded electrical output is 10 MWe (gross/net unspecified), scope plant. Modules planned: 1. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Customer or offtaker

Source-backed project statement In 18 May 2006 House testimony, Galena's city manager said the city would probably be a purchaser of raw power from the 4S plant, whose eventual owner was not named, and that the plant could serve nearby villages. That is a probable intention by the city itself, not a power purchase agreement, and the villages and mining interests mentioned are not named. The Air Force base described as the city's largest customer was leaving and bought diesel power, not 4S output. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S

Contractor

Source-backed project statement The city manager's 18 May 2006 House testimony says the city worked with the U.S. Department of Energy in 2004 on a study of Galena's power options, and that with state funding it contracted Burns and Roe, Inc to prepare white papers for eventual NRC submittal. A Burns and Roe engineer attended as the city's nuclear engineer. These are preparatory study and licensing-support roles. No license application was filed and no construction contractor is named. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S

Funding and government decisions

Source-backed project statement The 18 May 2006 House testimony says Alaska's governor and legislature gave the city seed money to begin the white-paper process, and ANS Nuclear Newswire reported on 6 May 2026 that the legislature committed $500,000 for those white papers. The same testimony lists federal requests, $2.8 million from GNEP towards $20 million of environmental work and $2.8 million, $10.0 million and $7.2 million for FY07 to FY09 licensing, which were requests. No award or disbursement of the federal requests was read. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S

Fuel
  • Fuel form stated for 4S (catalog profile as of 14 Feb 2025)Metal fuel (U-Zr alloy)
No project-specific fuel supply arrangement is recorded as a structured fact.

The city manager's 18 May 2006 House testimony says the 4S is designed to be fueled once for 30 years, which is a design feature, and its 700,000 gallons of barge fuel are for the existing diesel plant. Neither the testimony nor the 6 May 2026 ANS article names a fuel manufacturer, quantity or delivery for a Galena 4S. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S

Not found in the sources we checked (1): Comparable schedule revision
Comparable schedule revision

Comparable schedule revision not established. The 18 May 2006 House testimony aimed for operation by 2012 and printed a 2010 to 2012 availability line. ANS Nuclear Newswire's 6 May 2026 retrospective says deadlines slipped, that Galena decided in 2011 to pursue a fossil-fired plant and that NRC reviews ceased two years later, but it gives no revised operation date. No source read states an earlier and a later date for the same Galena milestone. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S

Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. In 18 May 2006 House testimony, the Galena witness says the city heard of the Toshiba 4S in 2003 and wants a design certification and a license to construct and operate a 4S plant in Galena; a 10-megawatt sentence is quoted separately. ANS Nuclear Newswire's 6 May 2026 history of the 4S says Galena decided in 2011 to pursue a new fossil-fired power plant and that NRC reviews ceased two years later. The stage is set to canceled on that secondary retrospective, which describes the same Galena 4S plan; no city resolution or exact decision date was found. The stored 4S design, one module and Toshiba as vendor stay. Last checked 23 Oct 2026. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S
    What would change this

    A City of Galena record of its 2011 decision, or a revived Galena 4S proposal, would change this record. Next scheduled check: 23 Apr 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The testimony says a 4S plant in Galena. Galena is the city. No plot or facility footprint is named. Last checked 19 Oct 2026. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S
    What would change this

    A license application with a site description in Galena would settle the location. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites: Not applicable. ANS Nuclear Newswire reported in May 2026 that Galena decided in 2011 to pursue a new fossil-fired power plant instead, and that NRC reviews of the 4S ended in 2013. With the city's plan ended, no next decision is pending for this proposal. Last checked 23 Oct 2026. ANS: The revival of Toshiba’s 4S
    What would change this

    A revived Galena 4S proposal. Next scheduled check: 23 Oct 2027.

  • Permissions and public process. Galena's city manager told a House subcommittee in 2006 that the City Council passed a resolution in December 2004 to keep evaluating the 4S, and that the city met the NRC in February 2005 to state its intentions; city council members attended a 2003 community meeting with Toshiba. ANS Nuclear Newswire reported in May 2026 that Toshiba submitted technical reports to the NRC from 2007, and that the NRC reviews ended in 2013 without review documents. No license application or license for Galena was recorded. Last checked 23 Oct 2026. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S
    What would change this

    None expected; a record of a Galena 4S license application would change this. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The 2006 testimony says the 4S plant would take up about half an acre in Galena, be air-cooled, and could supply excess power to nearby villages. ANS reported in 2026 that Galena had no electrical grid or road connection and that the city worked with DOE on preliminary siting studies. No specific plot, land arrangement or permit for the site was recorded. Last checked 23 Oct 2026. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S; ANS: The revival of Toshiba’s 4S
    What would change this

    None expected for this historical proposal. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Galena's 2006 testimony says the 4S would be fueled once for 30 years and that there would be no spent fuel storage on site, but it does not say who would remove the core, or where it would be stored or disposed of at end of life. These were proposed arrangements for an unbuilt plant. The testimony does not establish financial or site-restoration liabilities. Last checked 23 Oct 2026. House hearing (18 May 2006): testimony of the City of Galena on the Toshiba 4S
    What would change this

    None expected for this historical proposal. Next scheduled check: 23 Apr 2027.

Evidence dates

(1 of 2 sources with a publication or document date)
Latest dated listed source publication: ANS: The revival of Toshiba’s 4S: 6 May 2026.Latest dated recorded event: no date recorded.1 of 2 listed sources has no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(2)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Toshiba 4S proposal at Galena, Alaska (mid-2000s) — https://smrmap.com/projects/galena-4s/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Toshiba 4S proposal at Galena, Alaska (mid-2000s)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/galena-4s/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.