Projects / Japan · Operating
HTTR test reactor with planned hydrogen coupling, Oarai
JAEA's HTTR at the Oarai Nuclear Engineering Institute in Japan is an operating test reactor (30 MWt) that generates no electricity, with hydrogen coupling planned.
Current status
- How current
- General record check . Bounded evidence review . 5 of 8 listed sources have a publication or document date recorded here; the newest is 27 Mar 2025. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: NRA decision to grant the HTTR installation-change permit (3 Jun 2020). All permissions and applications
- Latest development
- 26 Sep 2025 · Recorded development: JAEA files an amendment to the HTTR hydrogen-coupling application. Source: JAEA: amendment to HTTR licence application for hydrogen plant connection. Updates entry
- Next dated milestone
- Planned step: 2030 (target). HTTR hydrogen production (JAEA target). This is not an achieved milestone. Source: JAEA: amendment to HTTR licence application for hydrogen plant connection.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
JAEA's HTTR first reached criticality in 1998; in 2025 JAEA applied to the regulator to connect a hydrogen production plant, targeting hydrogen by 2030. JAEA's August 2026 slides record six regulator review meetings on the hydrogen-coupling license change between May 2025 and April 2026 with no permit yet, and place the hydrogen production test around fiscal 2029 to 2030. On 3 June 2020 the Nuclear Regulation Authority decided to grant an installation-change permit for HTTR under article 26(1) of the Reactor Regulation Act, on an application received 26 November 2014. The draft permit letter has a blank number and a blank date, so no permit number is stored. This is not an operating license. JAEA dates the restart to 30 July 2021 and records 100% reactor power at 850 °C on 19 September 2021. Its August 2026 symposium slides document a further full-power thermal safety demonstration in March 2024. These are thermal test milestones, not electricity generation or commercial service. The hydrogen-coupling permit remains unissued. No electricity-generation output is assigned to this thermal test reactor. JAEA's history says the installation-permit application was made in February 1989, the permit was obtained in November 1990 and construction began in 1991.
Key facts
- Design
- HTTR (SMR)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Reactor vessel of this design
- 13.2 m tall, 5.5 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 235.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Japan Atomic Energy Agency
- Vendor for linked design
- Japan Atomic Energy Agency
- Location
- JAEA Oarai Nuclear Engineering Institute · Japan · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate institute-area point from OpenStreetMap for the facility named by the regulator or operator; not the reactor building. - Coordinates
- 36.2655, 140.5502 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- 30 MWth (nameplate; basis unspecified)
- Purpose
- Research or test reactor
- Construction start
- 1991HTTR construction begins
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
HTTR test reactor with planned hydrogen coupling, Oarai is recorded at JAEA Oarai Nuclear Engineering Institute, Ibaraki, Japan. Operator: Japan Atomic Energy Agency. Recorded vendor: Japan Atomic Energy Agency. Stage: Operating. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: institute-area point for the JAEA Oarai Nuclear Engineering Institute (query not recorded)
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 30 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorJapan Atomic Energy Agency
- Reactor supplier
- Vendor for the linked designJapan Atomic Energy Agency
- Funding and government decisions
- Funder or lender named for this projectAgency for Natural Resources and Energy (METI) · sourceCommissions JAEA's project to install and connect a hydrogen production facility to the HTTR; amount not stated.
Source-backed project statement
JAEA's 27 March 2025 notice says the work to install and connect a hydrogen facility to HTTR is in a project commissioned by the Agency for Natural Resources and Energy. No amount is stated, and the notice does not say construction costs have been paid. JAEA: HTTR hydrogen production facility (press release)
- Fuel
- Fuel form stated for HTTR (catalog profile as of 14 Feb 2025)UO2 TRISO ceramic coated particle
Source-backed project statement
The 7 August 2026 slides say the second HTTR fuel charge, delivered in March 2005, was the last fuel manufactured for HTTR, and that transfer of domestic fuel-manufacturing technology to JAEA has been agreed. No current fabrication contract or new delivery is stated. JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
- Programs and agreements naming the project
- Government program; activeJapan's HTGR demonstration reactor program (METI/ANRE, MHI core company, site not selected)
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
JAEA says it aims to produce hydrogen with HTTR heat by 2030 and to show that a high-temperature reactor can supply hydrogen for hard-to-abate industry. The August 2026 slides say the agency, JAEA and Mitsubishi Heavy Industries are exchanging views with steel, chemical and wholesale companies about future needs. No company is named as a buyer of HTTR hydrogen. JAEA: HTTR hydrogen production facility (press release); JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
- Contractor
The notices say JAEA applied to connect a hydrogen facility to HTTR. They do not name a construction contractor. A statement that Mitsubishi Heavy Industries is carrying out basic design appears under the separate demonstration-reactor section of the August 2026 slides, not as an HTTR construction award. JAEA: HTTR hydrogen production facility (press release); JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
- Comparable schedule revision
Comparable schedule revision not established. The September 2025 notice aims to make hydrogen with HTTR heat by 2030. The August 2026 slides say the HTTR hydrogen demonstration is planned for 2028 or later. Those statements describe the hydrogen test, not two forecasts of the reactor's operating date. A demonstration reactor aimed at the 2030s is a different plant. JAEA: amendment to HTTR licence application for hydrogen plant connection; JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
Timeline
Recorded developments
- · Recorded development
JAEA files an amendment to the HTTR hydrogen-coupling application - · Regulatory step
JAEA applies to the NRA to connect a hydrogen production plant to HTTR - · Recorded development
HTTR full-power thermal safety demonstration - · Recorded development
HTTR reaches 100% power and 850°C after restart - · Recorded development
HTTR resumes operation after new-regulatory-standard review
Earlier developments (8)
- · Other regulatory action recorded
Other regulatory action recorded: NRA decision to grant the HTTR installation-change permit - · Application submitted
Application for the HTTR installation-change permit - · Recorded development
HTTR 50-day continuous operation at 950°C - · Recorded development
HTTR reaches full-power operation - · First criticality
HTTR first criticality - · Construction start
HTTR construction begins - · Regulatory step
HTTR installation permit granted - · Regulatory step
HTTR installation-permit application filed
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
HTTR hydrogen production (JAEA target)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Other applications and decisions
- NRA decision to grant the HTTR installation-change permit
Other regulatory action · Issued / approved · NRA · decided 3 Jun 2020 · submitted 26 Nov 2014
On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating license and is distinct from the July 2021 restart.
Sources: NRA commission paper deciding the HTTR installation-change permit (3 June 2020)
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. HTTR is the Japan Atomic Energy Agency's 30 MWt graphite-moderated, helium-cooled test reactor at its Oarai site (World Nuclear News, 26 July 2023; JAEA press release, 26 September 2025). JAEA's history says it applied for the installation permit in February 1989, obtained it in November 1990 and began construction in 1991. The NRA's 3 June 2020 paper says design, manufacture and construction ran from 1990, equipment installation finished in 1996, rated power at an 850 °C outlet was reached in December 2001 and service operation began in May 2002. First criticality was in November 1998. These are thermal test milestones. No opened source describes electricity generation, grid connection or commercial service. On 3 June 2020 the NRA decided to grant an installation-change permit under article 26(1) of the Reactor Regulation Act, on an application received 26 November 2014. This is a change to the installation permit, not a separately titled operating license. JAEA's notice of 22 September 2021 says operation resumed on 30 July 2021, 100% power at 850 °C was reached on 19 September 2021, and the periodic licensee inspection was completed that day. JAEA's slides of 7 August 2026 quote the national energy plan on a March 2024 test at 100% reactor power. That is the latest operation any opened source describes. For hydrogen coupling, JAEA applied to the NRA on 27 March 2025 and filed an amendment on 26 September 2025. The slides list six review meetings and no permit, and say the hydrogen demonstration is planned for 2028 or later. JAEA's stated aim is hydrogen by 2030. Stored values match the sources. MHI's role as principal construction company for HTTR (WNN) is not stored as a participant role. SMRMap's saved copy of the ATOMICA page could not be converted to text when checked, so its two passages are carried from the 18 October reading. Last checked 19 Oct 2026. JAEA: amendment to HTTR licence application for hydrogen plant connection; WNN: MHI to lead development of Japanese HTGR; NRA commission paper deciding the HTTR installation-change permit (3 June 2020); JAEA Oarai: completion of HTTR periodic licensee inspection after restart (22 September 2021); JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026); JAEA ATOMICA 03-03-06-01: Development of HTGR technology in Japan and international cooperation (updated August 2016)
What would change this
The NRA's decision, or a further review-meeting record, on JAEA's 27 March 2025 HTTR installation-change application for the hydrogen production facility, as amended 26 September 2025. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage. On 3 June 2020 the NRA decided to grant the HTTR installation-change permit under article 26(1) of the Reactor Regulation Act, on an application received 26 November 2014 (NRA commission paper, re-read 13 November 2026). JAEA's history says the original installation permit was obtained in November 1990 on a February 1989 application. JAEA's 22 September 2021 notice says operation resumed on 30 July 2021 and that the periodic licensee inspection ended on the date of the notice. No opened source names a separately titled operating license. HTTR operates on its NRA-permitted installation, and the stored action keeps type 'other'. JAEA's slides of 7 August 2026 (not re-read on 13 November 2026) list six regulator review meetings, the latest dated 23 April 2026, on the hydrogen-coupling installation-change application of 27 March 2025 (amended 26 September 2025), and no permit; no NRA decision on it was found in the sources read. On 13 November 2026 NRA-hosted records of that review, identified by search, could not be fetched (not found, HTTP 404 for each of five addresses tried), so the NRA's own record of the 2025 review is unread. Last checked 13 Nov 2026. NRA commission paper deciding the HTTR installation-change permit (3 June 2020); JAEA ATOMICA 03-03-06-01: Development of HTGR technology in Japan and international cooperation (updated August 2016); JAEA Oarai: completion of HTTR periodic licensee inspection after restart (22 September 2021); JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
What would change this
The NRA decision on JAEA's 27 March 2025 hydrogen-coupling installation-change application, as amended 26 September 2025, or an NRA review-meeting record for it. Next scheduled check: 12 Feb 2027.
- Construction start evidence. JAEA's history states that construction began in 1991, with installation work largely finished in 1996 and first criticality on 10 November 1998. Last checked 18 Oct 2026. JAEA ATOMICA 03-03-06-01: Development of HTGR technology in Japan and international cooperation (updated August 2016)
What would change this
None; historical fact. Next scheduled check: 18 Apr 2027.
- Next decision and prerequisites. The next decision named for this change is the Nuclear Regulation Authority's decision on the 27 March 2025 application, as amended on 26 September 2025. The August 2026 slides still list review questions, the latest dated 23 April 2026, and do not say a permit has been issued. Last checked 23 Oct 2026. JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026); JAEA: amendment to HTTR licence application for hydrogen plant connection
What would change this
The regulator's decision on the HTTR hydrogen-connection application. Next scheduled check: 21 Jan 2027.
- Permissions and public process. On 3 June 2020 the Nuclear Regulation Authority decided to grant an HTTR installation-change permit under the reactor law, on an application received on 26 November 2014. That decision is not the hydrogen connection. JAEA applied on 27 March 2025 to connect a hydrogen facility, amended the application on 26 September 2025, and the August 2026 slides record review meetings through 23 April 2026. Those slides do not say the hydrogen permit has been granted. Last checked 23 Oct 2026. NRA commission paper deciding the HTTR installation-change permit (3 June 2020); JAEA: amendment to HTTR licence application for hydrogen plant connection; JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026)
What would change this
The regulator's decision on the 27 March 2025 HTTR hydrogen-connection application. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). JAEA locates HTTR at the Oarai Nuclear Engineering Institute and has applied to connect a hydrogen facility there. The August 2026 slides say the secondary helium system would be taken outside the reactor building. No new land transfer, water right or grid connection is stated. Last checked 23 Oct 2026. JAEA: HTTR hydrogen production facility (press release); JAEA: amendment to HTTR licence application for hydrogen plant connection
What would change this
A land, water or grid instrument for the hydrogen facility at Oarai. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The 3 June 2020 review describes spent-fuel storage pools and a design that does not impair spent-fuel cooling at the HTTR facility. It does not name a disposal site or a disposal contract for HTTR spent fuel. Last checked 23 Oct 2026. NRA commission paper deciding the HTTR installation-change permit (3 June 2020)
What would change this
A disposal site or disposal contract for HTTR spent fuel. Next scheduled check: 21 Jan 2027.
Evidence dates
(5 of 8 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(8)
- JAEA: amendment to HTTR licence application for hydrogen plant connection (company, accessed 2 Oct 2026)
- WNN: MHI to lead development of Japanese HTGR (news report, accessed 2 Oct 2026)
- JAEA: HTTR hydrogen-coupling status and schedule (symposium slides, 7 August 2026) (company, accessed 18 Oct 2026)
- NRA commission paper deciding the HTTR installation-change permit (3 June 2020) (regulator, dated 3 Jun 2020, accessed 15 Oct 2026)
- JAEA Oarai: HTTR restart notice with METI minister's message (30 July 2021) (company, dated 30 Jul 2021, accessed 16 Oct 2026)
- JAEA Oarai: completion of HTTR periodic licensee inspection after restart (22 September 2021) (company, dated 22 Sep 2021, accessed 16 Oct 2026)
- JAEA ATOMICA 03-03-06-01: Development of HTGR technology in Japan and international cooperation (updated August 2016) (company, revised Aug 2016, accessed 18 Oct 2026)
- JAEA: HTTR hydrogen production facility (press release) (government, published 27 Mar 2025, accessed 21 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: HTTR test reactor with planned hydrogen coupling, Oarai — https://smrmap.com/projects/httr-oarai/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “HTTR test reactor with planned hydrogen coupling, Oarai”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/httr-oarai/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.