Projects / prj-huizhou-huapeng-one
Huizhou HuaPeng-1 heating demonstration proposal
Tsinghua University Asset Management describes preparatory work for the HuaPeng-1 low-temperature heating demonstration in Huizhou. HuaPeng Technology’s conference presentation identifies the reactor as an optimized NHR200-II development suited to modular manufacture and factory assembly. The precise site, operator, module count, plant output and permission are unverified. This is distinct from the existing large-reactor units at Taipingling and does not inherit their construction status.
What this record says
Last verified 2026-10-13. This is a record review date, not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
Site and deployment
Huizhou HuaPeng-1 heating demonstration proposal is recorded at Huizhou HuaPeng-1 demonstration location (undisclosed), Guangdong, China. Operator: No operator is recorded. Vendor for a linked design: China General Nuclear Power Group. Stage: Siting. Location precision: undisclosed.
Capacity
This project is recorded as thermal only (no MWe). Module count is not recorded. Thermal output is not recorded on this project.
Permission recorded
- No project-specific regulatory action is recorded here. This is not a finding that no permission exists.
Latest supported development
No actual dated development is recorded.
Next documented milestone
No next milestone date is recorded.
Material unknowns
- Thermal output is not recorded on this project.
- No operator is recorded.
- No map pin is shown for this record.
View on map and table · Permissions and applications · Sources and check dates
- Design
- HuaPeng-1 (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Operator(s)
- Not recorded
- Vendor for linked design
- China General Nuclear Power Group
- Location
- Huizhou HuaPeng-1 demonstration location (undisclosed) · China · precision: undisclosed
Tsinghua’s asset-management company names Huizhou only; no Taipingling large-reactor coordinates borrowed. - Coordinates
- undisclosed / not plotted
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- smr_by_design_class
- Confidence
- medium
- Last verified
- 2026-10-13 (publication/verification date)
Milestones & dated events
- No dated milestones recorded yet.
Regulatory actions
- None recorded in this release.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Sources
- Tsinghua University Asset Management: regional economic and social development projects (company_primary, accessed 2026-10-13)
- HuaPeng Technology technical manager: small reactors coupled to petrochemical decarbonisation (company_primary, published 8 Jan 2026, accessed 2026-10-13)