Projects / United States · Announced
Radiant Kaleidos microreactors at Fort Benning (Army Janus)
The Army paired Radiant Industries, Inc. with Fort Benning under the Janus Program in August 2026 and says three microreactors of one megawatt each are planned there.
Current status
- How current
- General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 1 commissioning, 1 siting, 2 announced. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The Army says the site on post is still under evaluation. The Army says Janus prototype reactors will be contractor-owned and operated, and Radiant describes deploying and operating them, so Radiant is recorded as the intended operator; the Army is the host. The Army's 10 September 2026 article reports Radiant's stated responsibility for fueling, refueling and spent-fuel management of the Fort Benning units, not completed fuel deliveries. Radiant's agreement (up to $750 million) covers 15 Kaleidos units through the Janus Program; that program total is not a Fort Benning count.
Key facts
- Design
- Kaleidos (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Radiant Industries
- Vendor for linked design
- Radiant Industries
- Location
- Fort Benning · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Installation point from the Wikipedia article for Fort Benning; the sources name the installation but no pad or parcel on it, so this marks the base area, not a reactor site (Eielson and Buckley precedent). - Coordinates
- 32.36611, -84.96917 · site-area point (approximate)
- Electrical capacity
- 3 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 10 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Radiant Kaleidos microreactors at Fort Benning (Army Janus) is recorded at Fort Benning, Georgia, United States. Operator: Radiant Industries. Recorded vendor: Radiant Industries. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Wikipedia: Fort Benning (article coordinates), Article coordinate 32.36611, -84.96917 on 'Fort Benning', read 30 October 2026
Recorded electrical output is 3 MWe (gross/net unspecified), scope plant. Modules planned: 3. Thermal output is not recorded on this project. The linked design record states 3.5 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 1.2 MWe (gross/net unspecified); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerRadiant Industries · source
- Operator or intended licensed owner
- OperatorRadiant Industries
- Reactor supplier
- Vendor for the linked designRadiant Industries
- Customer or offtaker
Source-backed project statement The Army's 10 September 2026 Fort Benning article says the three planned Radiant microreactors will each generate 1 MW and continuously tie into the installation's electrical network. The installation, which is also the host, is the stated user of the power under a contractor-owned and operated model. No power purchase agreement, price or other buyer is named, and Radiant's separate Equinix agreement is not stated to involve Fort Benning. Fort Benning set to host next generation nuclear power initiative
- Fuel
- Fuel form stated for KaleidosTRISO
- Enrichment stated for Kaleidos19.75%
Source-backed project statement
The Army's 10 September 2026 Fort Benning article reports Radiant saying it will be responsible for operating the Fort Benning units as well as fueling, refueling and spent-fuel management. That assigns fuel responsibility for these units to Radiant. No fuel fabricator, quantity or delivery date is named, and no fuel has been reported delivered. Fort Benning set to host next generation nuclear power initiative
- Programs and agreements naming the project
- Government program; activeU.S. Army Janus Program for commercial microreactors on Army installations
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
The Army's 10 September 2026 article says the three Fort Benning microreactors will be contractor-owned and operated by Radiant, and Radiant's 26 August 2026 release says it will deploy 15 reactors under the Janus Program. Radiant is the project's own vendor and intended operator, so its Janus selection is not a separate contractor appointment. Neither source names an engineering or construction contractor, and candidate parcels are still under evaluation. Fort Benning set to host next generation nuclear power initiative; Radiant: U.S. Army Janus agreement for Kaleidos microreactors
- Funding and government decisions
Radiant’s agreement of up to US$750 million covers 15 Kaleidos reactors through the Janus program. The cited release does not allocate that program ceiling to Fort Benning; it is not a disclosed Fort Benning funding amount. Radiant: U.S. Army Janus agreement for Kaleidos microreactors
- Comparable schedule revision
Comparable schedule revision not established. Radiant's 26 August 2026 release says it will deploy 15 reactors by 2030, beginning at Fort Benning, and the Army's Fort Benning article says the program is working toward first microreactors operating by 2028. These are a fleet date and a program date stated once each, not an earlier and later date for the same Fort Benning milestone. Radiant: U.S. Army Janus agreement for Kaleidos microreactors
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. On 26 August 2026 the Army paired Radiant Industries, Inc. with Fort Benning and said Janus prototype reactors will be contractor-owned and operated. The program award is up to a combined $2.2 billion, and the Army expects more than 20 microreactors across installations. Fort Benning's 10 September 2026 article says the post will host three Radiant microreactors of one megawatt each, 3 megawatts combined, and that candidate parcels have been identified while the final site is still under evaluation. Radiant says the pictured location is to be determined, and that a binding agreement of up to $750 million covers 15 Kaleidos reactors through Janus. POWER reports the same 15-unit ceiling and a three-unit start at Fort Benning, and describes Kaleidos as TRISO-fueled and helium-cooled. The 15 units, the $750 million ceiling and the $2.2 billion ceiling are not this post's count or price. Last checked 19 Oct 2026. Army reaches agreement with private industry for nuclear micro reactors; Fort Benning set to host next generation nuclear power initiative; Radiant: U.S. Army Janus agreement for Kaleidos microreactors; POWER: U.S. Army mobilizes $2.2B Janus program
What would change this
An Army selection of the Fort Benning parcel, or a change in the three-unit assignment, would change this record. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. Fort Benning is the host installation. The post says candidate parcels are identified and the final site is still under evaluation. Radiant says the reactor location is to be determined. Lawson Army Airfield is described as infrastructure the power could support, not as the reactor plot. Last checked 19 Oct 2026. Fort Benning set to host next generation nuclear power initiative; Radiant: U.S. Army Janus agreement for Kaleidos microreactors
What would change this
An Army parcel decision would settle the site. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The Fort Benning site is still being chosen among candidate parcels. Janus reactors are to be authorized under an Army-run licensing regime, with installations still subject to environmental review. The program targets a first Army-regulated reactor operating on a military installation by September 2028, and vendors are paid only on reaching technical milestones. No Fort Benning-specific decision date is given. Last checked 23 Oct 2026. Fort Benning set to host next generation nuclear power initiative; POWER: U.S. Army mobilizes $2.2B Janus program; Army reaches agreement with private industry for nuclear micro reactors
What would change this
An Army licensing or NEPA decision, or a milestone payment report, for this installation. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Army paired Radiant with Fort Benning under the Janus program in August 2026, a selection under milestone-based agreements rather than a permit. Army officials said in August 2026, as reported by POWER, that Janus reactors will be licensed under an Army-run defense regime rather than by the NRC, and that installations remain subject to NEPA and other environmental reviews. No Army license or completed environmental review for this installation is recorded. Last checked 23 Oct 2026. POWER: U.S. Army mobilizes $2.2B Janus program
What would change this
An Army licensing decision or a NEPA document for the reactor at this installation. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Fort Benning's 2026 article says candidate land parcels are being assessed for three Radiant microreactors, with the final site still under evaluation, favouring places with few surrounding structures, safe distance from water and proximity to plug into the post's grid. Army officials said Janus installations will stay connected to the grid. Last checked 23 Oct 2026. Fort Benning set to host next generation nuclear power initiative; POWER: U.S. Army mobilizes $2.2B Janus program
What would change this
A NEPA document or Army site decision describing the reactor plot and its grid tie-in. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. Army officials said in August 2026, as reported by POWER, that all nuclear waste must leave a Janus installation within two years of a reactor shutting down, and that the Army plans to negotiate one arrangement under which the Department of Energy would receive the spent fuel and take title for payment. That arrangement was still to be negotiated; no contract or receiving facility is named. Last checked 23 Oct 2026. POWER: U.S. Army mobilizes $2.2B Janus program
What would change this
An Army–DOE spent-fuel agreement or a NEPA document for the reactor at this installation. Next scheduled check: 21 Jan 2027.
Evidence dates
(0 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- Army reaches agreement with private industry for nuclear micro reactors (government, accessed 17 Oct 2026)
- Fort Benning set to host next generation nuclear power initiative (government, accessed 2 Oct 2026)
- POWER: U.S. Army mobilizes $2.2B Janus program (news report, accessed 2 Oct 2026)
- Radiant: U.S. Army Janus agreement for Kaleidos microreactors (company, accessed 10 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Radiant Kaleidos microreactors at Fort Benning (Army Janus) — https://smrmap.com/projects/janus-fort-benning-kaleidos/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Radiant Kaleidos microreactors at Fort Benning (Army Janus)”. Record reviewed 10 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/janus-fort-benning-kaleidos/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.