Projects / United States · Licensing

Long Mott Generating Station (Xe-100 at Dow Seadrift)

Four Xe-100 modules are proposed for electricity and industrial steam at Dow's Seadrift site in Texas.

Current status

Stage
LicensingConstruction permit issued; physical construction is not recorded as started.
How current
General record check . Bounded evidence review . 20 of 25 listed sources have a publication or document date recorded here; the newest is 12 Nov 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: Long Mott construction permit (9 Nov 2026); Long Mott environmental assessment, FONSI and review exemptions (18 May 2026). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
9 Nov 2026 · Regulatory step: NRC issues the Long Mott construction permit. The NRC says it has issued the construction permit for the four-reactor Long Mott Generating Station in Texas. Source: NRC news release 26-083: first construction permit in nearly 60 years for a high-temperature gas-cooled reactor (Long Mott) (published 9 Nov 2026); Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance (published 12 Nov 2026); NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133) (dated 9 Nov 2026). Updates entry
More on this development

The permit authorizes construction, not operation. No construction start is recorded.

Next dated milestone
No upcoming target date is recorded. Most recent target: Planned step: Nov 2026 (target). NRC target for the Long Mott final safety evaluation. Met on . Source: NRC: Long Mott Generating Station Xe-100 application page (page updated 14 Sep 2026); X-energy: NRC completes safety review of the Xe-100 for Long Mott (final safety evaluation report), 30 Oct 2026 (published 30 Oct 2026); NRC news release 26-083: first construction permit in nearly 60 years for a high-temperature gas-cooled reactor (Long Mott) (published 9 Nov 2026).
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
Same design
4 tracked: 1 licensing, 1 siting, 2 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
High-temperature gas-cooled reactor. How it works, with a 3D view.

Description

The NRC lists the four-module plant at 800 MWth/320 MWe and describes each module as able to produce 80 MWe of electricity or about 200 MWth of steam; how output will be split between electricity and steam is not stated. The 320 MWe is recorded as net, as in the IAEA's 2026 tables. The NRC issued Construction Permit No. CPAR-3 on 9 November 2026 (announced in release 26-083 and noticed at 91 FR 72925 on 12 November) for the application submitted on 31 March 2025; the permit authorizes construction but not operation, sets 1 July 2033 as the earliest and 31 December 2033 as the latest construction completion date, and staff completed the safety evaluation in October. X-energy's release of the same day still calls Long Mott a proposed project and says Dow is considering its next phases before allocating major capital for full-scale construction, with first delivery in the early 2030s. No construction start or final investment decision is recorded, and a permit alone does not make a Construction stage, so the stage remains Licensing. NRC's 20 May 2026 notice says its environmental assessment and finding of no significant impact for the application were available on 18 May, and it issued exemptions allowing this review in place of an environmental impact statement on the same day. In the contested proceeding, the Licensing Board admitted an intervenor in January 2026 and later dismissed both admitted contentions as moot; on 7 August 2026 the Commission dismissed the applicant's related appeal as moot, and on 6 November 2026 it denied the intervenor's separate petition for review (CLI-26-15), ending the adjudication. The NRC held its uncontested (mandatory) hearing on 22 September 2026 in Port Lavaca (noticed at 91 FR 53900; held per CLI-26-15); the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance of the permit, while listing work still needed for an operating license. The NRC hearing notice names Long Mott Energy, LLC as the applicant, and the IAEA's 2026 reactor tables list it as operator of the planned station; Dow is recorded as site host, not operator. The NRC says the project is supported by DOE's Advanced Reactor Demonstration Program.

Key facts

Design
Xe-100 (SMR)
Technology
High-temperature gas-cooled reactor (HTGR) · helium
Operator(s)
Long Mott Energy, LLC
Vendor for linked design
X-energy
Location
Dow UCC Seadrift / Long Mott · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Long Mott unit 1 (Xe-100) at Dow's Seadrift Operations (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point, not a surveyed plot. Replaces an earlier point on the town of Seadrift about 12 km away.
Coordinates
28.5033, -96.7745 · site-area point (approximate)
Electrical capacity
320 MWe (net) · scope: plant
The NRC application page lists a four-module plant at 800 MWth/320 MWe, intended to supply electricity and steam to Dow's adjacent Seadrift Operations, and says each module could produce 80 MWe of electricity or about 200 MWth of steam.
Thermal capacity
800 MWth (nameplate; basis unspecified)
Modules planned
4
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Long Mott Generating Station (Xe-100 at Dow Seadrift) is recorded at Dow UCC Seadrift / Long Mott, Texas, United States. Operator: Long Mott Energy, LLC. Recorded vendor: X-energy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'long-mott-nuclear-power-plant-1' (28.5033, -96.7745)

Recorded electrical output is 320 MWe (net), scope plant. The NRC application page lists a four-module plant at 800 MWth/320 MWe, intended to supply electricity and steam to Dow's adjacent Seadrift Operations, and says each module could produce 80 MWe of electricity or about 200 MWth of steam. Modules planned: 4. Recorded thermal output is 800 MWth (nameplate; basis unspecified). The linked design record states 80 MWe (net); the project figure is kept separate.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Customer or offtaker
  • Prospective customer / offtaker (binding offtake not established)Dow · sourceNRC release 26-083: the facility will primarily generate high-temperature steam for Dow's Seadrift Operations site; CLI-26-15 (as recited): that site is owned and operated by a Dow affiliate. Intra-group supply; no sale contract is stated.
Source-backed project statement

NRC release 26-083 (9 November 2026) says the four-reactor facility will primarily generate high-temperature steam for industrial use at the Dow Seadrift Operations site and that excess electricity will be exported to the grid. The Commission's order CLI-26-15 (6 November 2026), describing the application, says Long Mott Energy is a wholly owned subsidiary of Dow, that the facility would be built on land owned by The Dow Chemical Company to create and deliver steam to the adjacent Seadrift Operations, and that Seadrift Operations is owned and operated by a Dow affiliate. X-energy and Dow's 9 November release says the plant is intended to provide both electricity and high-temperature steam to Dow's site. This is intended supply within the Dow group. No supply contract, price or power purchase agreement is stated, and the buyer of the excess electricity is not named. NRC news release 26-083: first construction permit in nearly 60 years for a high-temperature gas-cooled reactor (Long Mott); NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP); X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site

Contractor

Source-backed project statement X-energy's 5 November 2026 release calls its agreement with Fluor for the Cascade facility in Washington the companies' second commercial contract for nuclear island engineering and design, building on Fluor's ongoing work for X-energy's first proposed Xe-100 project in Texas under DOE's Advanced Reactor Demonstration Program; the release does not name Long Mott or Dow. Nuclear Engineering International reported on 9 April 2026 that Fluor signed a contract with X-energy to support the proposed Seadrift project, initially delivering Front-End Loading Stage 2 services (trade press; the April 2026 Fluor release on Business Wire returned an Access Denied page and was not read). X-energy's 9 November release says X-energy served as technical and licensing lead for the Long Mott Energy permit application. The Fluor work is described as a contract with X-energy; no contract between Fluor and Long Mott Energy is stated, and its value is undisclosed. No engineering, procurement and construction contractor or construction contractor is named in the sources read. X-energy: Fluor selected for Cascade nuclear-island engineering and design; X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; NEI: Fluor joins Seadrift SMR project

Funding and government decisions
  • Funder or lender named for this projectU.S. Department of Energy · sourceApplication relies on X-energy's DOE ARDP award (CLI-26-15: no copy included). X-energy: intended to rise to $2.15 billion total for a plant and TRISO-X facility, no Long Mott share; ANS: +$1 billion (Aug 2026). No modification recorded.
  • Public award or selection; not a disbursement; awardedARDP demonstration award: X-energy (Xe-100) · sourceDOE's ARDP projects page places the funded Xe-100 demonstration at Dow's Seadrift Operations.
Source-backed project statement

The Commission's order CLI-26-15 (6 November 2026) recounts that Long Mott Energy's application originally relied on an award from DOE's Advanced Reactor Demonstration Program without including a copy of the award, and that on 3 March 2026 it supplemented the application with a non-public financial agreement between itself and Dow that the order describes as a conditional commitment by Dow to fund at least half of the estimated construction costs (the order also words this as 'more than half'). Dollar amounts and contractual terms were redacted in the Licensing Board's public description, and the order does not state the conditions. X-energy's 9 November 2026 release says X-energy has been informed that its DOE award is intended to be increased to 2.15 billion dollars in total, to deliver a first-of-a-kind commercial advanced nuclear plant and the TRISO-X fuel fabrication facility; the release does not say how much applies to Long Mott. ANS reported on 17 August 2026 an additional 1 billion dollars of cost-shared funding, and NEI reported in April 2026 a 2024 joint development agreement of up to 50 million dollars; the sources read do not reconcile these figures. The construction permit states that the NRC found Long Mott Energy financially qualified to design and construct the facility under its regulations. The DOE award is held by X-energy. No signed award modification, Dow final investment decision or project financing is stated. NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP); X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); ANS Nuclear News: X-energy, TerraPower share updates on advanced reactor projects; NEI: Fluor joins Seadrift SMR project

Fuel
  • Fuel supplier named for this projectTRISO-X, LLC · sourceDOE says the initial production of TRISO-X's TX-1 facility, under construction, will support this plant; no fuel supply contract with Long Mott Energy is stated.
  • Fuel form stated for Xe-100Graphite pebbles with TRISO particle fuel
Source-backed project statement

X-energy and Dow's 9 November 2026 release says that in April 2025 TRISO-X was allocated an initial tranche of high-assay low-enriched uranium (HALEU) through DOE's HALEU Availability Program, which will be used to manufacture fuel for the first core loads at Long Mott. DOE's 9 April 2025 release lists TRISO-X among five developers given conditional commitments for HALEU and does not name Long Mott. DOE said on 17 November 2025 that TX-1, TRISO-X's fuel facility, was under construction with initial production supporting the proposed Seadrift plant. The NRC's May 2026 environmental assessment says the source of fresh fuel was not stated in the applicant's environmental report, although the report described the fuel production process and discussed the TRISO-X facility (section 5.7.1); for its transport analysis the assessment considers shipments between a fuel fabrication facility in Oak Ridge, Tennessee and the site. TRISO-X is X-energy's affiliate. No fuel supply contract with Long Mott Energy, no delivery, and no start of TX-1 production are stated in the sources read. X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; DOE: U.S. Department of Energy to Distribute First Amounts of HALEU to U.S. Advanced Reactor Developers; DOE: X-energy starts building construction of advanced nuclear fuel facility; Environmental Assessment and Finding of No Significant Impact for the Construction Permit and Environmental Review Exemptions for the Long Mott Generating Stati

Site host or owner
Not found in the sources we checked (1): Comparable schedule revision
Comparable schedule revision

Comparable schedule revision not established. X-energy and Dow's 9 November 2026 release describes first delivery in the early 2030s as the long-established timeline and says Dow is expected to consider a preliminary investment decision in 2027, with full-scale construction following a final investment decision. The construction permit sets a completion window of 1 July to 31 December 2033, which is a permit term, not an operation target. NEI reported on 9 April 2026 that the 2024 joint development agreement aimed to deploy the four-unit plant by 2030, but no company or regulator document read states both an earlier and a later operation target for this plant. Dated 2023 and 2024 Dow and X-energy schedule statements were not captured in this review. X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); NEI: Fluor joins Seadrift SMR project

Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
Programs and agreements naming the project

Timeline

Recorded developments

Earlier developments (7)

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Construction permit: 9 Nov 2026.

Permissions and applications

Construction applications and decisions

Environmental decision

Assessments of the design (not of this site)

(2)
  • Xe-100 UK Generic Design Assessment (requested) — applies to the design, not to a site
    Design assessment sought · Application received · ONR/EA (UK)
    On 15 September 2026 ONR said the Department for Energy Security and Net Zero had asked it, the Environment Agency and Natural Resources Wales to begin a three-step Generic Design Assessment of X-energy UK Holdings Ltd's Xe-100 after a readiness review. The assessment begins once timescale and resource arrangements are in place, so no step is recorded as started. ONR's page, updated 28 September 2026 and re-read on 28 October 2026, still says so.
    Sources: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026)

    Could not be confirmed on . Attempted official source: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026). This is an access or status observation only; the record review date is unchanged.

  • CNSC vendor design review, Phases 1 and 2 (Xe-100) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Dec 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: X-energy Xe-100 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. The NRC page (updated 14 September 2026) says Long Mott Energy, LLC applied on 31 March 2025 for a construction permit for the Xe-100 power reactor in Calhoun County, Texas, a four-module high-temperature gas-cooled plant of 800 MWth/320 MWe supported by DOE's Advanced Reactor Demonstration program; its environmental section says the four Xe-100 modules would supply electricity and steam to the adjacent Seadrift Operations facility, each module able to produce 80 MWe of electricity or about 200 MWth of steam. The NRC's environmental assessment notice (dated 18 May 2026, published 20 May 2026) says the application was accepted for docketing on 12 May 2025 and that a construction permit would authorize construction only; Long Mott Energy would need a separate application and NRC approval before it could operate the reactors. The environmental assessment and finding of no significant impact were issued on 18 May 2026; they are not a construction permit. The NRC page lists the draft safety evaluation (February 2026) and advanced safety evaluation (August 2026) as completed, targets the final safety evaluation for November 2026, and lists the hearing and the construction permit decision as TBD; a separate NRC meeting notice (updated 18 September 2026) scheduled the uncontested hearing for 22 September 2026, with written comments open to 6 October 2026, and no outcome was found. The Commission's order of 7 August 2026 dismissed Long Mott Energy's appeal as moot and took no position on the intervenor's separate petition for review; the NRC's 2026 order index lists no later Long Mott order through 1 October 2026. No opened source reports site preparation or nuclear construction; ANS (20 May 2026) reports that X-energy and Dow gave no construction timeline and that Dow did not expect a final investment decision before 2028. The licensing stage, four modules, 800 MWth and 320 MWe, and Long Mott Energy as intended operator stay stored; the net basis for 320 MWe rests on the IAEA 2026 table reading, as the NRC and ANS state no basis. Last checked 19 Oct 2026. NRC: Long Mott Generating Station Xe-100 application page; NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions; NRC meeting notice: mandatory hearing on the Long Mott construction permit application; NRC Commission order CLI-26-10, Long Mott Energy, LLC (Docket 50-614-CP); NRC / ANS Dow Long Mott Xe-100 EA-FONSI; IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026)
    What would change this

    The NRC's final safety evaluation (targeted November 2026), the construction permit decision, or a Commission ruling on the Waterkeeper petition for review. Next scheduled check: 7 Dec 2026.

  • Plant capacity (scope qualified). The NRC application page lists a four-module plant at 800 MWth/320 MWe, intended to supply electricity and steam to Dow's adjacent Seadrift Operations, and says each module could produce 80 MWe of electricity or about 200 MWth of steam. The IAEA's 2026 tables list 800 MW thermal and 320 MW net with no gross figure. The figures are not additive deliveries, and the split between electricity and steam is not stated. Last checked 16 Oct 2026. NRC: Long Mott Generating Station Xe-100 application page; IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026)
    What would change this

    The NRC issues its final safety evaluation or permit decision, or the applicant states a different electricity and steam split. Next scheduled check: 14 Jan 2027.

  • Next decision and prerequisites. The NRC issued Construction Permit CPAR-3 on 9 November 2026, effective on issuance, with a construction-completion window of 1 July to 31 December 2033; the permit expires on the latest date. X-energy and Dow's 9 November release says they will continue design finalization and supply-chain work and develop an operating license application, that Dow is expected to consider a preliminary investment decision in 2027, and that full-scale nuclear construction would follow a final investment decision by Dow's Board of Directors. The permit says an operating license will not be issued until a complete final safety analysis report is submitted and further Commission findings are made, and condition 3.D requires notifying the NRC when the site grading and flood-protection design is available (expected before safety-significant foundation concrete) and condition 3.E when excavation geology is mapped. The Commission denied the intervenor's petition for review on 6 November 2026. No construction start, final investment decision or operating license application date is stated. Last checked 13 Nov 2026. Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP)
    What would change this

    Dow's preliminary investment decision (expected 2027), an operating license application, a final investment decision or construction start, or a court challenge to the permit. Next scheduled check: 13 Feb 2027.

  • Permissions and public process. The Commission's order CLI-26-15 of 6 November 2026 denied San Antonio Bay Estuarine Waterkeeper's petition for review of the Licensing Board's rulings, which had rejected or dismissed all of its contentions and ended the adjudication; it also records that the NRC held its uncontested (mandatory) hearing on 22 September 2026 in Port Lavaca, Texas. The NRC issued an environmental assessment and finding of no significant impact in May 2026 with environmental-review exemptions. The permit says it was issued after a public hearing. The NRC's project page (updated 12 November 2026) lists the hearing as 22 September 2026 and the construction permit decision as 8 November 2026, while the permit and the Federal Register notice date issuance to 9 November 2026; the one-day difference is unexplained in the sources read. Whether any court challenge to the permit has been filed was not searched and is not recorded. Last checked 13 Nov 2026. NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP); NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance; NRC: Long Mott Generating Station Xe-100 application page; NRC: Commission orders (CLI) issued in 2026; NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions
    What would change this

    A court petition for review of the permit, an NRC hearing or enforcement action on a permit condition, or an operating license application opening a new hearing opportunity. Next scheduled check: 13 May 2027.

  • Site dependencies (land, grid, water). The NRC project page says the plant would be built on about 1,537 acres adjacent to Dow's Seadrift Operations. The Commission's order CLI-26-15, describing the application, says the facility would be built on land owned by The Dow Chemical Company to deliver steam to Seadrift Operations, an adjacent facility owned and operated by a Dow affiliate. The NRC's May 2026 environmental assessment, citing the applicant's environmental report, says operating water would be supplied by existing surface water rights held by Dow, from Basin #5 at Seadrift Operations with Calhoun Canal withdrawals maintaining basin levels, and that the plant would be dry cooled with no reactor-cooling withdrawals. It describes new intake structures and supply pipelines and a new switchyard with transmission lines to the existing Seadrift substation, and says no new offsite transmission corridors are planned. Permit conditions 3.D and 3.E require notifying the NRC when the site grading and flood-protection design and the geologic mapping of safety-related excavations are available. These are planned facilities and rights held by Dow; no land lease or transfer, water agreement, or interconnection agreement for exported electricity involving Long Mott Energy is stated in the sources read. The environmental assessment's permits appendix was not read. Last checked 13 Nov 2026. NRC: Long Mott Generating Station Xe-100 application page; NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP); Environmental Assessment and Finding of No Significant Impact for the Construction Permit and Environmental Review Exemptions for the Long Mott Generating Stati; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133)
    What would change this

    A water-supply contract or permit, a site lease or transfer between Dow and Long Mott Energy, or an interconnection agreement for exported electricity. Next scheduled check: 13 May 2027.

  • Spent fuel, waste and closure. The NRC's May 2026 environmental assessment says a single Spent Fuel Intermediate Storage Facility unit is required for the full life cycle of each Xe-100 module, each unit holding multiple rows of spent-fuel containers cooled by natural circulation, treats the impacts of continued storage of spent fuel at the site as not significant for foreseeable time periods, and says spent resins and planned higher-activity wastes from the liquid waste system would be packaged for transport offsite to be disposed of by a third party. The construction permit (CPAR-3, 9 November 2026) lists no spent-fuel condition and says an operating license will not be issued until a complete final safety analysis report is submitted and further Commission findings are made. This is the applicant's planned design as reviewed for a construction permit, not a built or licensed storage facility. No storage license or offsite spent-fuel disposal arrangement is named in the sources read. Last checked 13 Nov 2026. Environmental Assessment and Finding of No Significant Impact for the Construction Permit and Environmental Review Exemptions for the Long Mott Generating Stati; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133)
    What would change this

    An operating license application, a storage license or a decommissioning funding plan describing the spent-fuel arrangement. Next scheduled check: 13 May 2027.

Evidence dates

(20 of 25 sources with a publication or document date)
Latest dated listed source publication: Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance: 12 Nov 2026.Latest dated listed source document: NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133): 9 Nov 2026.Latest dated recorded event: NRC issues the Long Mott construction permit: 9 Nov 2026.5 of 25 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(25)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Long Mott Generating Station (Xe-100 at Dow Seadrift) — https://smrmap.com/projects/long-mott-xe-100/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Long Mott Generating Station (Xe-100 at Dow Seadrift)”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/long-mott-xe-100/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.